Alcator C-Mod
Test Procedure for Diborane Gas System
Author: Catherine L. Fiore, Chris Reddy, Joe Bosco
Version: Version 3.3 Released 7/5/2002 by C. Fiore. Reviewed
by J. Irby, E. Marmar
Date: 1/9/96 revised 7/5/2002
Date: Translated to HTML 7/03/2002
Computer filename: User10:[fiore.www]dibtest.html
System: Diborane Gas System
Person responsible: C. Fiore, G. Dekow
I. Introduction
It has been postulated that an effective
way to coat the walls of the Alcator C-Mod vacuum vessel with a thin layer
of boron is to create a gaseous discharge in diborane gas inside the vacuum
vessel. Diborane is highly toxic and flammable, and presents an explosion
hazard. The gas delivery system must be of high integrity and leak
free. Leak detection and remote control are essential. Procedures for
handling, maintenance, process, and emergency response are required, as
is training of any personnel directly or peripherally involved with
using this material.
II. Required Elements:
-
A.
-
Scope/Purpose This document covers the testing requirements
for the Alcator C-Mod Diborane facility.
-
B.
-
Consequences of procedural failure.
-
-
Failure to adequately test the diborane system could result
in leakage of diborane gas into the cell or into the diborane housing,
which could lead to fire or explosion, or to personnel exposure to toxic
gas. Diborane is immediately dangerous to life and health at 40 ppm, and
an explosion hazard at 9000 ppm.
-
C.
-
Definitions
-
-
MDA-TLD-1-Gas monitor for the diborane system. One is located
at the diborane gas cabinet. The other is located on the igloo, first level
under B-port.
-
-
SCBA-Self Contained Breathing Apparatus. Two units are located
at the entrance to the C-Mod power room, in the control room.
-
D.
-
Responsibilities
-
-
Test of the performance of the system will be conducted by
Joe Bosco, Gary Dekow, and Bob Childs with Catherine Fiore in
attendance.
-
-
Installation of the diborane gas cylinder: Two persons, trained
and approved to wear SCBA, trained in diborane hazards, and trained in
all of these procedures will install the diborane gas bottle.
-
-
These procedures will be reviewed and approved by a committee of
no fewer than 3 knowledgeable persons, appointed by the Safety Officer.
-
E.
-
Required Equipment
-
-
SCBA
-
-
Adapter for helium gas bottle to diborane bottle fitting
-
-
Helium leak detector ("sniffer")
-
-
Wrenches for gas fittings
-
-
Walkie-talkies or cell phones
-
F.
-
Required Materials
-
-
-
G.
- Assumptions and Prerequisites
-
-
The PLC system has been installed and completed.
-
-
The diborane system has been installed and completed.
-
-
All alarms and warning systems have been installed and completed.
-
-
A tv camera for remote viewing of the toxic gas cabinet has been
installed and is functional.
-
H.
-
Procedure
-
-
Check function of the diborane monitors (MDA-TLD-1).
- 1.
- If this test is being done prior to installation of the
diborane gas bottle, open valve PV5 in order to observe that it is closed
during simulated fault conditions. The access control bit must be jumpered
out in order to open PV5. If the diborane is in the toxic
gas cabinet, do not open this valve.
- 2.
- Turn the Tape Load Lever to the ``open'' (9 o'clock) position,
remove the Chemcassette, and press the Alarm Test Key. The green
System Status Indicator will flash. The display will show the word ``VERIFY''.
- 3.
- Insert the test card with position#1 centered in the Detector
Head; be sure that the colored chip on the test card faces up and that the
card is inserted fully into the Detector Head.
- 4.
- Close the Tape Load Lever and press the Alarm Test Key. The
instrument will beep once.
- 5.
- Open the Tape Load Lever and reverse the Test Card, centering
position #2 in the Detector Head.
- 6.
- Close the Tape Load Lever and press the Alarm Test Key. If
all electronics and optical systems are operating properly, the instrument will
go into an alarm condition, with both the audible and visual alarms activated
and the alarm relay energized. Check that the process gas valve PV5 has
closed if it was opened for this test. Note that the 4-20 mA output will
deliver a signal equivalent to 100 ppb to the DIBORANE PLC.
- 7.
- Open the Tape Load Lever and press the Alarm Reset Key. Rethread
the Chemcassette Detection Tape and turn the Tape Load Lever to the closed (6
o'clock) position. The test is now complete.
- 8.
- Repeat steps 1-6 for the second monitor.
-
-
Vacuum system test procedure
- 1.
- Helium leak check system to 1×10-7 scc/s from the gas
bottle to the Piezo-electric valve by one of the
following two methods:
- Plug the diborane gas bottle connection.
Set the helium system regulator to 30 psi, and open manual valve MV2
to pressurize the system. PV4, PV5, PV3, PV6 and MV1
must be opened. The diborane regulator (REG1) must be set to 30 psi.
Use a helium sniffer to check all pressurized points in the system for leakage.
- Install the leak checker at the point where the diborane gas
cylinder is to be installed. Open the helium system regulator REG2 (make sure
the helium bottle valve is closed), and open manual valve MV2.
PV4, PV5, PV3, PV6 and MV1
must be opened. The diborane regulator (REG1) must be opened as far as
possible.
Pump the system out, start the leak checker, and
spray helium on the system connections to look for leaks.
-
-
PLC safety system test.
-
-
Note that the access control bit must be jumpered out in order
to open PV5 for these tests. DO NOT TEST PV5 INTERLOCKS WITH DIBORANE.
- 1.
- Install helium gas bottle in the place of the diborane
bottle. Note that an adaptor is needed to mate the helium bottle
to the diborane connector.
Open the valve on this bottle.
- 2.
-
Open the nitrogen gas bottle
valve for the venturi system and set the
regulator REG3 to 100 PSI. Open the helium purge
gas valve and set the regulator REG2 to 30 PSI. Open PV3 and PV4.
Set the diborane gas
regulator REG1 to 30 PSI. Close PV4. Open PV1, and PV2 to evacuate
the line.
Verify that the diborane transducer TR4 is registering a vacuum and
note the reading.
- 3.
- Open PV5 and note that the diborane transducer TR4
registers an increase in pressure. Note the value.
PV5 should close on all of the faults to be
tested, which will register as a decrease in the pressure measured by the
diborane transducer TR4. Should PV5 fail to close on any of the tests,
the test should be considered a failure. Close PV5.
- 4.
- Open PV5. Simulate a fault on the diborane cabinet
MDA-TLD1, as described above in the section on testing the MDA-TLD1's.
Note PV5 status. Reset. Close PV5.
- 5.
- Open PV5. Simulate a fault on the B-side (cell)
MDA-TLD1, as described as described above in the section on testing the
MDA-TLD1's. Note PV5 status. Reset. Close PV5.
- 6.
- Open PV5. Turn off cell exhaust blower. Note PV5 status.
Reset. Close PV5.
- 7.
- Open PV5. Close dampers on the diborane exhaust line.
Note PV5 status. Reset. Close PV5.
- 8.
- Open PV5. Close vaporizer valve MV5. Note PV5 status. Reset.
Close PV5.
- 9.
- Open PV5. Close house air valve MV6. Note PV5 status. Reset.
Close PV5
- 10.
- Search and lock the cell, placing it in full access control.
Open PV5. Breach access control system. Note PV5 status.
The system safety interlock test is now complete.
- 11.
- Reset the system. Close the valve on the helium gas
bottle (at the
diborane input point) and open PV5 to evacuate the line. Close PV2, PV3,
PV1, MV1 and close the diborane regulator REG1.
-
-
Inert gas test
- 1.
- Install the helium gas bottle in the space provided for
the diborane bottle, as described in the diborane gas installation
procedure. Note that an adaptor is needed to mate the helium bottle
to the diborane connector.
- 2.
- Search and lock the cell. Enter the cell under controlled
access to perform the next 2 items.
- 3.
- Verify that manual
valves MV1 and MV3 are open. Verify that
the diborane regulator (REG1) is set to 30 PSI, the venturi regulator (REG3) is
set to 100 PSI, and
the helium purge gas regulator (REG2) is set to 30 PSI. PV3 and PV4 and manual
valve MV2 will
have to be open to set the diborane regulator pressure.
- 4.
- Start the flow from the vaporizer into the diborane vent
work and the vacuum pump outlet by opening ball valve MV5 and the valve going
to the torus roughing pump. Verify that MV4 is open.
- 5.
- Activate the purge procedure from the PLC. The AUTO switch
on the DIBORANE PLC must be enabled, and the toggle switch for the
diborane bottle valve should be in the closed position. Enable PURGE60.
The PLC should
open PV valves 1,5,3, and 6.
- 6.
- Observe the purge cycle. PV2 will open, causing a drop in the
pressure measured by the diborane transducer TR4. PV2 should then close and
PV4 should open for 15 seconds, causing an increase the pressure measured by
the diborane transducer TR4. PV4 will then close, and PV2 will open for 15
seconds. This sequence will repeat 20 times.
- 7.
- At the end of the purge cycle, PV4 will close, and then
PV2 will close 15 seconds later. PV1, PV5, PV2, PV3, and PV6 will now close.
This is the end of the purge sequence, and the discharge cleaning
is ready to commence.
- 8.
- Enter the cell under controlled access, taking 2 walkie-talkies
with them. One should don the welding glove and open the diborane (helium)
bottle while the other watches the toxic gas detector on the cabinet. After
exiting, enable the DIBORANE OPN bit on the PLC.
- 9.
- Set up for the discharge cleaning cycle. Enable the Diborane
on button on the DIBORANE PLC.
Go into the TORVAC PLC. Turn off all filaments specified (IGT,
IGP1, IGP2, both RGA's, the Ratiomatic.) Close all of the diagnostic gate
valves. Close GV3. Close GV2. Close GV1. Open SV3. Open SV4 to 100.
Open GV2. Turn
IGP1 back on. If the pressure on IGP1 is less than 5×10-5 Torr turn
on the Dycor RGA. Go into the AFILL screen of TORVAC and clear the fault,
even if no fault is indicated.
- 10.
- Set the pressure by entering a requested pressure into the
DIBORANE PLC and enable the fill request. PV5, PV3
and PV6 must all open.
It will ask for a password
(FILL) in order to proceed. Activate the diborane discharge
cleaning mode from TORVAC.
- 11.
- Verify that all systems function as expected.
Set the piezo electric valve for the desired value and
initiate the discharge cleaning.
Verify that a discharge has formed in the machine. Maintain
discharge cleaning for the desired period.
- 12.
- Shut down discharge cleaning. Verify that the Piezo-electric
valve has been asked to close.
- 13.
- Evacuate the gas line. (This can be done automatically
from the DIBORANE PLC by enabling AUTO and enabling PURGE5.)
Begin by closing PV5. Open PV3. Open PV1.
Open PV2 until the diborane transducer indicates the line is under vacuum.
Close PV2. Open PV4. Cycle PV2 and PV4 every
15 seconds a total of 20 times.
- 14.
- Enter the cell under access control. Don the
welding glove and close the valve on the diborane (helium) bottle.
Exit the cell,
manually set the switch on the PLC which indicates that the diborane bottle
valve has been closed and initiate the PURGE60 cycle.
- 15.
- At completion of the purge cycle, shut PV6, PV1, and PV5 and the
Piezo-electric valve. PV2, PV3 and PV4 should already be closed.
Release the access control system. Close the REG1 regulator and MV1.
The discharge cleaning session is now complete.
- 16.
- When the vacuum vessel has been pumped out (1 to 1.6 mTorr on
TC3), GV1 may be reopened, and IGT turned on. The diagnostic valves which
were closed at the beginning of this procedure may be re-opened.
DO NOT OPEN GV3. Turn on the remaining filaments and RGA's.
-
I.
-
Training
-
-
Those responsible should review these procedures in detail, and
should receive training in toxic gas hazards, and SCBA usage.
-
J.
-
Summary Check List
-
1.
-
Toxic gas monitor function.
- a.
- Check gas monitor A.
- b.
- Check gas monitor B.
-
2.
-
Vacuum test of system lines
-
3.
-
PLC control system function.
- a.
- Toxic gas monitor fault, at cabinet
- b.
- Toxic gas monitor fault, B side
- c.
- Exhaust blower failure
- d.
- Vent damper closure
- e.
- House air loss
- f.
- Vaporizer gas loss
- g.
- Access system breach
-
4.
-
Inert gas system test.
- a.
- Setup for the test: Install
the helium gas bottle in the space provided for
the diborane bottle.
- b.
- Enter the cell under
controlled access to perform the next 2 items.
- c.
- Verify that manual
valves MV1 and MV3 are open. Verify that
the diborane regulator (REG1) is set to 30 PSI, the venturi regulator (REG3) is
set to 100 PSI, and
the helium purge gas regulator (REG2) is set to 30 PSI. PV3 and PV4 and manual
valve MV2 will
have to be open to set the diborane regulator pressure.
- d.
- Start the flow from the vapor
work and the vacuum pump outlet by opening ball valve MV5 and the valve going
to the torus roughing pump.
- e.
- Verify that MV4 is open.
- f.
-
Activate the purge procedure from the PLC. The AUTO switch
on the DIBORANE PLC must be enabled. Enable PURGE60. This will not
work unless the
DIBORANE CLSD bit is enabled. Do not change this bit
without verification of the bottle valve status.
- g.
- Verify that the PURGE60
cycle is working. Make sure that PV5 is
open, and that TR4 is cycling between vacuum and pressure.
- h.
- Two people should enter
the cell under
controlled access, taking 2 walkie-talkies. One should don the welding glove
and open the diborane (helium) bottle while the other watches the toxic gas
detector on the cabinet. Enable the DIBORANE OPN bit on the PLC.
- i.
-
Set up for the discharge cleaning cycle. Enable the Diborane
on button on the DIBORANE PLC.
- j.
- Go into the TORVAC PLC.
Turn off all filaments specified (IGT,
IGP1, IGP2, both RGA's, the Ratiomatic.) Close all of the diagnostic
gate valves.
- k.
- Close GV3. Close GV2.
Close GV1. Open SV3. Open SV4 to 100.
Open GV2. Turn
IGP1 back on. If the pressure on IGP1 is less than 5×10-5 Torr turn
on the Dycor RGA. Go into the AFILL screen of TORVAC and clear the fault,
even if no fault is indicated.
- l.
- Set the pressure by
entering a requested pressure into the
DIBORANE PLC and enable the fill request.
It will ask for a password
(FILL) in order to proceed.
- m.
- Activate the diborane
discharge
cleaning mode from TORVAC.
Verify that a discharge has formed in the machine. Maintain
discharge cleaning for 30 minutes to check system function.
- n.
- Shut down discharge cleaning.
Verify that the Piezo-electric valve has been asked to close.
- o.
- Evacuate the gas line.
(This can be done automatically
from the DIBORANE PLC by enabling AUTO and enabling PURGE5.)
Begin by closing PV5. Open PV3. Open PV1.
Open PV2 until the diborane transducer indicates the line is under vacuum.
Close PV2. Open PV4. Cycle PV2 and PV4 every
15 seconds a total of 20 times.
- p.
- Enter the
cell under access control. Don the welding glove and close the valve on the
diborane (helium) bottle. Exit the cell.
- q.
- Enable the DIBORANE CLSD
switch on the DIBORANE PLC.
- r.
- Initiate the PURGE60 cycle.
- s.
- At completion of the purge
cycle verify that all automatic valves are shut.
- t.
- Release the access control
system.
- u.
- Enter the cell and close the
REG1 regulator and MV1. The discharge cleaning session is now complete.
- v.
- When the vacuum vessel has
been pumped out (1 to 1.6 mTorr on TC3), GV1 may be reopened, and IGT turned
on. The diagnostic valves which were closed at the beginning of this procedure
may be re-opened. Turn on the remaining filaments and RGA's.
-
K.
-
Cross references
-
-
Procedure for Installation of Diborane Gas.
-
-
Procedure for Diborane Gas System Discharge Cleaning.
-
-
Procedure for Diborane Gas System Maintenance.
-
-
Emergency Procedure for Diborane Gas System.
-
-
Safety Analysis Report for Diborane Injection in Alcator C-Mod
-
L.
-
Distribution
-
-
E. Marmar, J. Irby, C. Reddy, R. Clifford, J. Bosco, B. Childs, I.
Hutchinson, F. Silva.
-
M.
-
References
-
-
Matheson gas catalogue.
-
-
MDA Scientific `` TLD-1 Toxic Gas Detector Operating Instructions''
File translated from
TEX
by
TTHgold,
version 3.04.
On 3 Jul 2002, 13:39.