Alcator C-MOD Weekly Highlights Jan. 20, 1994 The scheduled maintenance period is continuing. This week saw progress in a number of areas. The vacuum pumping station was re-installed on H-port this week. The roughing pumps still need to be installed, after which the ECE and McPherson diagnostics can be moved back into operating position. In addition, we continued installation of inner flange blankets, and the attachment of insulation to the port boots. The blankets and boots must be installed on the machine before we can raise the cryostat, after which heaters, cable trays, and other equipment below the cyrostat can be re-installed. C-port extension has been re-installed and its secondary seal pumped down successfully. The secondary seal pressure signal is being used as a test signal for the new PLC monitoring program. The LN2 feedline emergency backup lines are nearing completion. Most of the fitup and welding work is now done, and components are being installed on the bus tunnel. Final installation of the feedline into the cryostat must wait until the cryostat is raised into position. Thirteen EF1-lower tile modules have now been installed in the vessel, along with six outer divertor modules. Twelve floor tile modules are now ready for installation with all inspection, cleaning, and torquing operations completed. Several upper EF1 modules are now being prepared for installation. Copper bus components for the TF crowbar bypass cabinets have now been fabricated and are ready for installation. The bus work as provided by Robicon was not considered acceptable for high current operation. The TF switch has also been modified to improve its bracing and current handing capability. Machining of all major components for the modification to the ICRF dipole antennas has now been completed. Considerable effort has been put into determining the direction and severity of disruptions during the last run period. We found that during the last month of operation, 90% of the disruptions went down. These disruptions were also in general considerably more severe, having on average twice the plasma current. These results are consistent with our finding nearly all the damaged tiles in the bottom of the machine. The results of this work will be added to the disruption database. Dr. Karl Lackner of IPP-Garching visited MIT on Friday, Jan. 14, for discussions on collaborations between Alcator C-MOD and Asdex Upgrade in the area of non-dimensional similarity experiments. C-MOD and Asdex-U should produce plasmas with nearly identical dimensionless parameters (beta, nu-star, rho-star, q, elongation, aspect ratio) but with very different absolute parameters. Therefore, comparisons of results from the two machines will allow testing of non-dimensional scaling concepts. Specific topics on which comparisons will be carried out include confinement, sawtooth period, H-mode threshold, and disruption behavior (thermal quench time scale).