Alcator C-MOD Weekly Highlights March 24, 1994 Progress continues toward bringing the vacuum break to a conclusion by the end of this month. All major in-vessel work has been completed. Flanges are now being installed where possible, calibrations are being finished up, and in-vessel cabling is being checked out. For the first time in many weeks there are no in-vessel components such as tiles, current shunts, or cables awaiting vacuum baking. A-port horizontal was leak checked successfully this week and its boot installed. Completion of this job allowed several more igloo blocks to be installed. These blocks were particularly important since they provide support for the torus gas feed system, and numerous thermocouple, heater, and TF scanner interface boxes. Installation of both dipole ICRF antennas is now complete. In addition, the stub tuners/phase shifters have been installed in the cell. Owing to a reporting error, the coating of the D-port antenna Faraday shield was mis-identified in last week's report; the D-port Faraday shield is TiC-coated, while the E-port antenna has the B4C-coated Faraday screen. Diagnostic installation and debugging continued this week. All new Rogowski coils have now been installed and their associated cables run. The calibration of the visible light reticon arrays was completed. All outer divertor current shunts (ten toroidal locations) have now been installed, and their coax cables checked out. Debugging of the first wall thermocouples is nearly complete. The divertor scanning probe was installed, operated, and its position calibrated. The outer divertor cover plates, which protect much of the divertor instrumentation cabling, have been installed. The last divertor bolometer can now be installed, aligned, and calibrated. Finally, the two-color interferometer path though the vessel vertical ports was roughly aligned this week and a new vacuum window tested in situ. PLC and PARAGON software for the CRYO system has now been checked out and the new hardware debugged. The system has been run up to the point of actually putting LN2 into the sump. However, the structure and coil thermocouples that allow us to monitor cooling are still being re-installed. Vessel heater and thermocouple re-installation is nearing completion, but several days of testing and debugging still remain once all connections are made. Work also continues on the TF scanner. Finally, bringing on line the CRYO system allowed the cryostat to be purged and coil HiPot and ringing tests performed. The magnets are now ready for operation. The ECDC system has been checked out and operated into a dummy load. Some enhancements to the interlock system are still planned before routine operation can begin. This work is now being carried out. Preparations for a neutron calibration, to be conducted over a two day period, have continued. The detectors are being connected to the data system, and moved into position where possible. The calibration requires all igloo blocks to be in place, which in turn requires all horizontal flanges to be installed. In addition, it must be done while up-to-air so that the source can be moved to various locations in the vessel. The calibration will therefore be one of the last operations to be completed before pumpdown. The second neutral particle analyzer is nearing completion. The analyzer (TFTR type with E||B) has been assembled and leak-checked. Baking of the vacuum components is underway. Final testing of the various power supplies and other subsystems are also underway. The analyzer will be installed at the midplane of F port with scanning capabilities in the horizontal and vertical directions. It is expected that the diagnostic will be ready with the start-up of the machine operations phase. It will be able of diagnose the effects of the ICRF on the hydrogen and deuterium populations, and obtain an independent measure of the ion temperature. Martin Greenwald is attending the ESNET Review meeting in Chicago; he will be making a presentation on computer network requirements for the Fusion Energy program. Miklos Porkolab, Earl Marmar, and Bruce Lipschultz are attending Field Work Proposal presentations at DoE Germantown.