Alcator C-MOD Weekly Highlights April 28, 1994 Final preparations were completed this week, and the Phase II Operating Campaign has now begun. The first attempt at plasma operation is scheduled for today. Additional discharge cleaning (ECDC) was carried out over the weekend. ECDC in D2 is being carried out this morning, prior to the run. Depending on results of the first plasma runs, we will now be employing our standard pre-run conditioning procedures. Cooldown of the machine structure to cryogenic operating temperature was completed on Tuesday. Diagnostic installation and calibration is continuing. The PCX neutral particle analyzer has now been installed in the cell. The TCI interferometer is operational. The SRL Shearing Interferometer has been installed. The new halo current rogowskis were calibrated during TF tests. Live power system tests were begun last Friday. The first experiment (Miniproposal #042) of the present campaign was a non-plasma experiment, carried out in conjunction with the power tests, to determine the dynamic response (transfer function) of the Hybrid/Power Supplies/Coils/Structure. Single supplies are driven with different frequency oscillating voltages (between 20 and 500 Hz) through the hybrid, and the resulting currents on all coils and on internal magnetics are observed. These results will be used to improve our modeling of the dynamic system response and better analyze the closed loop behavior of the control system. This experiment was also a very stringent test of the new PCS software, including the multiple segment feature; a couple of minor bugs were uncovered and fixed. During the power testing we found that one flux loop (out of 26) had been damaged during the recent vent. The analysis and control algorithm software have been modified to recognize the bad loop and compensate appropriately.