Alcator C-MOD Weekly Highlights June 25, 1996 Eight out of ten outer divertor modules have been installed in the machine. Work on the remaining modules is complete, and they have been inspected and approved for installation. These modules will be installed as work on the edge Thomson scattering system and the prototype divertor cryopump is completed. All tests of the divertor cryopump in the vacuum test stand are finished. The pump is currently installed in the divertor mock-up where the 300K shield and divertor pressure gauge tubing are undergoing fitups. Work on a variety of engineering and diagnostic systems continues. All glow discharge insulators are in house and have begun the vacuum bake out process. A full system test will be done in the vacuum test stand before any components are installed invessel. All clamps and spacers needed to install both the glow discharge components and the diborane manifold have been fabricated and are being cleaned and electro-polished prior to installation. An invessel test fitup of the manifold was completed successfully. TORVAC wiring is complete and PLC/PARAGON programming for the new foreline pump is ready to be tested. The ECE rack has been moved back to the diagnostic stand extension and new cabling is being installed. The strain gauge cables have been installed and the floor and inner divertor modules and tiles over the gauges and cables have been re-installed. The retro-reflector mount for the tangential interferometer has been fabricated and is being cleaned and electro-polished. The LN2 cooling manifold box has been sealed. Rapid progress continues on the edge Thomson Scattering system. The laser beam enclosure in the laser room is complete. Construction has started on the final section of the igloo beam enclosure. The interlock system design is complete and installation has started. The AFOL/DFOL racks are complete and are being installed. The alignment of the beam optics has been confirmed invessel. The alignment of the polychromator is complete and preparations are being made for its calibration. Focus tests of the beam optics are planned for the end of this week or early next week. A quarterly review of the Alcator C-MOD program was held at MIT on 6/19. Besides presentations from C-MOD personnel, Bill Rowan of the University of Texas presented a talk on the DNB and associated diagnostics Texas is planning to install, and Joel Hosea from PPPL discussed the MIT/PPPL collaboration. Rostom Dagazian represented DOE. Bob Granetz was at the ANS conference in Reno Nevada and gave an invited talk on "Design Issues for Tokamak Reactor Divertors".