Alcator C-Mod Weekly Highlights Sept 8, 1997 The maintenance period continued at Alcator C-Mod last week. No runs were scheduled. Physics activities concentrated on diagnostic preparation and data analysis. The alternator repair is progressing. Manufacture of the new pole-to-pole jumper connections and new main leads for the alternator field winding was completed. Fabrication of temporary wooden blocking to be used during re-installation of the field coils was completed. Cutting and preparation of the slot armor for assembly is in process. Installation of the field coils on the rotor has begun. Calibration of the core Thomson scattering system using Rayleigh scattering from Argon was carried out during the week. This completes the scattering calibration work for the core system. Based on J. Terry's derivation of the recombinations/photon we are now reviewing older data with spectrometer views of the outer divertor for information about the role of recombination there. We have found that a significant amount is occurring before detachment. At the onset of detachment we observe pressure peaking at the divertor plate that moves away from the separatrix into the common flux region, leaving low plasma pressure regions behind (detachment). The recombination increases during this period and follows the detachment up the plate. The amount of recomnbination (integrated over the plate) is less that the integrated current loss during detachment, indicating that an appreciable fraction of the current loss is due to a loss in ionization. Preliminary results using the new "helium probe" on C-Mod have now been obtained. The helium probe follows the technqiue developed at TEXTOR, where local values of electron density and temperature can be derived from the ratio of three near-IR lines of HeI. In the case of C-Mod, a crude "beam" of helium gas is formed using a capilliary that injects through the AB limiter at the outside mid-plane. The capilliary nozzle is at the leading edge of the limiter, typically within 10 mm of the separatrix. The helium atoms cross the SOL, penetrating several mm's inside of the separatrix. The helium emissions are observed with a tangentially-viewing fiber array. Initial results indicate a relatively robust signal level, with low background inteference (1%). Local conditions at the limiter location as deduced with the technique are Te = 10 eV to 20 eV and ne = 2 to 8 e19 m-3 in Ohmic discharges. A thorough comparison with the fast scanning probe has not yet been made, but these values are consistent with earlier probe measurements. These initial results are being presented this week at the ITER Diagnostic workshop in Varenna, Italy. The power systems group installed two new shunts in the EF4 bus. These provide independent measurement of the current in each of the two EF4 coils. Maintenance on the 80 MHz ICRF transmitters FMIT#1 and #2 is progressing. FMIT#2 testing into the detuned dummy load has been completed. An MIT arc detector was found to be producing false arc indications and was repaired. The E-port (FMIT#2) Princeton arc detector was also found to be malfunctioning. These faulty arc detectors are the most likely source of the problems running FMIT#2 in the previous campaign. Testing of the phase balance arc detectors will be started this week. Work on FMIT#3's and #4's PLC wiring progresses. The H-probe on the E-port external resonant loop was pressure tested. The repaired H-probe does not leak, but another on the same loop does. Work is under way to repair this probe as well. On last Thursday (09/04), the Final Design Review for the new Princeton four strap, ICRF antenna array was held at MIT. The Princeton collaborators were represented by the cognizant engineer R. Ellis and physicists J.R. Wilson and J. Hosea. In addition to the C-Mod ICRF physicists, several other PSFC staff members attended. R. Ellis presented the design and thermal, electromagnetic and stress analysis of the antenna. The design appears to be solid. Issues raised in the Preliminary Design Review were shown to have satisfactory solutions. For example, samples of the TZM rods for the Faraday shield were provided to show that the manufacturing of these rods as specified could be done. The design meets the thermal, electromagnetic and stress specifications. The thermal analysis indicates that a maximum of 9-10 4 MW 10 second pulses at 20 minute intervals is possible. The electromagnetic analysis indicates the insulating Faraday shield rod end connectors are critical to the success of the design. If the connectors short out, repairs to the Faraday shield would be necessary. The insulating connector design is the same which has been successfully used at C-Mod previously. For the stress analysis, a full finite element analysis was performed. The results indicate there were no excessive stresses and the location of maximum stress was where the current feed connect to the antenna straps. A few issues remain including relocation of the in-vessel mounting hardware and design of the side plate. These issues have straightforward solutions which were discussed. The antenna fabrication process is beginning. Contracts for parts which require longer lead time have been awarded and the C-Mod port mockup at PPPL has been built. The plan is to have the antenna built and tested in the mockup at PPPL in January 1998. It will then be disassembled and shipped to MIT in February and ready for installation in March. The associated coax system was also discussed. A scale drawing of the C-Mod diagnostic stand and cell were provided to PPPL. The tight physical space and two resonant frequencies are the primary factors influencing the design. Reconstruction of the suppresser switch for the diagnostic neutral beam has begun. On completion, all high voltage components, including input and output snubbers, will be fully enclosed within an interlocked cabinet. The CAMAC system for acquisition of the DNB thermocouple/secondary emission data was received after having been assembled and tested at UT-FRC. The system will accommodate 28 channels of thermocouple data and 19 channels of faster secondary electron emission data. These will be the principal diagnostics for beam operation and development. The beamline cryopumps and associated equipment were assembled and located in preparation for the routine maintenance that is required before regular operation can begin. With completion of required maintenance, the turbomolecular pumping system is now ready for long term operation. Earl Marmar attended the International Workshop on Diagnostics for Experimental Fusion Reactors in Varenna, Italy. He presented an invited paper discussing spectroscopic and other diagnostic techniques.