Alcator C-Mod Weekly Highlights Sept 22, 1997 The maintenance period continued at Alcator C-Mod last week. The alternator repair, DNB, and RF upgrades are progressing. We continued electron cyclotron discharge cleaning experiments. The last of the twenty field coils is being installed on the alternator rotor. All tests, including hi-pots to 6 kV, on all but the last coil have been successfully completed. Remaining tasks include installation of the field coil jumpers, support blocking, and retaining rings. A several day long bake to cure the rotor insulation is also required along with several more hi-pot tests. On the present schedule, installation of the rotor inside of the alternator housing will begin next week. Calibration and testing of the FMIT#1 and #2 interlock system is nearing completion. The phase balance detectors were tested and set. This interlock checks the phase between the top and bottom antenna current in one antenna strap. This phase is normally 180 deg. An arc is registered if the phase changes by +/-45 deg (0.25 V). The voltage limit was also tested and set. This interlock limits the peak voltage on the antenna to below a predetermined value (40 kV). The position feedback circuit is being bench tested. Position feedback is used to maintain the loading at a pre-set value to facilitate RF operations under H-mode conditions by variation of the plasma position. The PLC work on FMIT#3 and #4 continues as well. Design of the fueling systems for the DNB were completed. It was determined that existing components could be used, and construction is now underway. The largest of the transition boxes for the high voltage, low capacitance transmission line, and the frames for all of the other transition boxes were completed. Work continues on assembly of the vacuum system controls and layout of the beamline in the cell. A detailed design of the suppressor switch interface to the PLC and master control system has been started. Drawings and wirelists for the vacuum system were updated and corrected. The ECDC experiments continued with more scans of the resonance position and fill pressure as density and temperature data was obtained with the energy analyzer and Langmuir probe. Preliminary analysis indicates the electron density outside the resonance position is in the range of 1 to 1.5e16 m-3 and is spatially rather flat over a 30 cm range. The electron and ion temperatures are both approximately 2 eV and also have very broad spatial profiles. The density drops quickly inside the resonance with a decay length of < 3 cm. A stainless steel rod coated with 200 A of diamond-like graphite was inserted to within 4 cm of the resonance. The graphite was completely removed in less than 3 hours by the discharge in a region from 12 to 16 cm outside of the resonance position (the resonance position was not scanned during this experiment). Other regions of the probe showed less graphite removal and possibly some redeposition. Bill Wampler (Sandia Laboratory collaboration) will use a proton backscatter technique to provide quantitative information on the radial profile of the graphite. Left out of last week's report was the attendance of Martin Greenwald at the ESnet Steering committee meeting from Sept 8-12. Bob Granetz was in Lausanne, Switzerland last week attending an MHD Expert Group meeting. Most of the time was spent writing and editing sections of the ITER Physics Basis document.