Alcator C-Mod Weekly Highlights October 6, 1997 The maintenance period on Alctor C-Mod continued last week. No runs were scheduled. The Alcator C-Mod vacuum vessel underwent a three day bake at 100C in preparation for operation. The vessel is now back at 35C, and Electron Cyclotron Discharge Cleaning (ECDC) is continuing. All blocking, insulation, and wedges were installed on the alternator rotor and a hi-pot to 6000 volts was completed successfully. The retaining rings were then installed and the final acceptance hi-pot (5000V) was completed over the weekend. The rewind of the alternator rotor is now complete. The tooling and machinery used in the rewind operation are being removed from the site. The re-assembly of the alternator will begin this week. Work on alternator instrumentation and auxiliary systems also continued last week. The varistor shunt signal has been wired to CAMAC through an isolation amplifier. Wiring to CAMAC to add a signal from a current transformer on the stator ground is done. The rotor V and I are wired into CAMAC. A four-channel isolation amplifier board was built and installed. In the RF area, the tuned arc detectors have been completed and are awaiting testing and calibration. Testing of FMIT#1 and #2 power feed back circuits has begun. Professor Yuichi Takase is visiting from the Tokyo University until late November. He will be heavily involved in commissioning D and E port antennas this upcoming campaign. He will also be involved in data analysis and discussions of future RF experiments. Data obtained during ECDC experiments carried out in September has been analyzed; characterization of the ECDC plasmas is of interest to ITER. We used the Omegatron diagnostic to make electron density, electron temperature, and ion temperature measurements of electron cyclotron discharge cleaning (ECDC) plasmas. By varying the strength of the toroidal field, we scanned the radial location of the cyclotron resonance, and effectively moved the plasma relative to the measurement point (the Omegatron). At each resonant location we recorded electron temperature and density with Langmuir probes on the Omegatron diagnostic. With deuterium fill pressure of approx. 3e-4 Torr, we recorded electron densities of approx. 1e16 m^-3, dropping sharply as the resonance location moves outside the measurement location. We recorded corresponding electron temperatures of approx 10 eV; for ECDC plasmas, the electron pressure profile looks approximately constant at .020 Pa, dropping sharply as the resonant location moves outside the measurement location. We measured ion temperatures with the retarding field energy analyzer (RFEA) component of the Omegatron diagnostic. We observed ion temperatures of 2 eV, approximately constant across the ECDC plasma, decreasing as the resonance location moves outside the Omegatron. Two additional SCSI busses were installed on the main data acquisition server bringing the total up to 5. This will allow each of the four CAMAC highways to be attached to its own bus. This was done to improve the reliability of the CAMAC highways by reducing their interdependancy. Installation of the high voltage, low capacitance transmission line for the DNB began with construction of supports for the principal transition box and test installation of the box itself. Relocation of the process gas system for the DNB plasma source was completed. Design of the suppressor switch control interface was completed and construction began. This unit will support communication with the DNB PLC and control by the fast logic. Dave Johnson and Ben LeBlanc from PPPL were onsite last week, working on the x-point Thomson scattering system.