Alcator C-Mod Weekly Highlights Nov. 17, 1997 There were no operations on Alcator C-Mod last week. As noted in the previous report, during the morning startup procedure on Thursday, Nov 6, a ground fault indication was observed on the newly re-wound alternator rotor. The fault showed up only at slow rotation speeds and did not occur during full load operation with excitation applied. In response to this indication, tokamak operations were suspended. MD&A, the company that performed the rewind, dispatched a team to MIT to carry out repairs. That work has proceeded on a double-shift, seven-day-week basis. The rotor has been pulled and inspected, and the fault location determined. The retaining ring at the affected end of the rotor was removed, and wedges were removed for a few feet from the #1 slot. The fault cleared as one of the wedges was removed; a small steel sliver which may have been responsible was observed during removal of the wedges. Inspections and further testing are continuing. The power systems group assisted MD&A and alternator staff in measurements on the rotor. In addition, testing of the TF current feedback circuit was undertaken to determine the cause of noise in the cabinet #1 regulator signal observed on one shot on November 5, and previously on a single shot in June; this work is still in progress. During the hiatus, several jobs involving the PLC control system are being carried out. The in-cell CRYO rack, which includes temperature sensors for the magnet systems and cryogenics controls, has been re-organized and cleaned up. Control power for the thermocouple sensors on the toroidal field magnet, and control power for the ECDC system, has been re-routed so that it no longer depends on the TF supply cabinet being energized. An evaluation of the default power-on status for all PLC control systems is in progress. Progress continues on the preparation of the diagnostic neutral beam system. The crowbar that will protect the DNB Mod/Reg tube was successfully bench tested to half of the required voltage. Based on these very postitive results, the testing will be completed after installation of the crowbar and its trigger source in the Mod/Reg cabinet. The high voltage, low capacitance transmission line continued its progress through the power area toward the cell and corona hardware for the section between the power supplies and the cell was completed. The conditioning system for the oil in the accelerator supply is now under construction. Most of the C-Mod physics team is attending the APS Division of Plasma Physics Meeting in Pittsburgh this week. A clean-up and replacement of ceiling tiles in the C-Mod Control Room is being carried out this week. As a result, most of the C-Mod computer cluster has been taken off-line. E-mail and data access should continue to function.