Alcator C-Mod Weekly Highlights November 16, 1998 Engineering: The TF magnet was completed last week with the installation of the first-to-last turn leg and all remaining spring plates. The magnet successfully passed a DC hi-pot to well over twice the maximum operating voltage and a AC ringing test to similar voltages. Following completion of the magnet the retaining cylinder was installed. Cylinder installation was considerably more difficult than expected. During past assemblies the sliding joints on the arms and legs allowed some adjustment in radial extent as the cylinder was installed. Changes in spring plate pressure, together with new arm shimming techniques reduced this radial compliance, and each TF leg had to be adjusted individually during multiple fitups of the cylinder. This process has delayed reassembly by a few days. Installation of the cylinder is particularly important for vacuum work since horizontal and vertical ports can not be installed until the cylinder is in place. We have also made very good progress on other machine related systems. We have completed work on the inner central column cooling manifold with the addition of new thermocouples to measure the TF core temperatures. This system will be ready for installation following LN2 thermal cycle tests. We have also begun a general cleanup and checkout of all the cryogenic systems. The LN2 sump has been cleaned, the LN2 pump checked out, and the sump will soon be sealed up ready for operation. A great deal of work was also completed on the new heater system cabling and interface boxes. This change will free up a large amount of area around the machine for diagnostic installations, and also provide more reliable control of the the vessel heaters. The power systems group continued checkouts of the magnet power supplies last week. Only the TF supply remains to be brought back into operation. We also continued work on a new I^2t protection circuit for the TF magnet. Development of the DNB and its diagnostics continued. Pre-installation benchmarking of CXRS optics, including the optical fibers, was completed and the system is now ready for baking, in-vessel alignment, and installation. Ron Bravenec (UT-FRC) continued his visit to complete modifications to the BES filter spectrometer. Conditioning of the oil for the accelerator supply continued after modifications that will insure better circulation of the oil. Work continued on the additional boards required for the Mod/Reg. Work on invessel components intensified last week as we prepare for pumpdown. Work on the divertor bypass flappers is now in the final assembly phase. The first set of parts received from PPPL for the new antenna are undergoing a 3 day bake after an extensive cleanup effort. We now expect delivery of the remaining antenna parts early this week along with PPPL personnel arriving to perform the installation. Work continues on modifications and additions to the horizontal ports, MHD coils, limiters, tangential two-color interferometer mirror and retro-reflectors, and the rangefinder. The new bolometer box has been assembled and welded. Travel and Visits: Nearly all C-Mod scientists and most graduate students are attending the APS DPP meeting in New Orleans this week.