Alcator C-Mod Weekly Highlights December 7, 1998 Reassembly of Alcator C-Mod continued last week. All cooling lines are installed and have passed all required inspections. Nitrogen gas has been run through the coils to verify that all connections have been properly made, and that the proportional valves and cooling manifolds are operational. The magnets were successfully hi-potted and rung through the bus tunnel indicating that both the copper bus and the magnets are ready for operation. The curved bus around the cylinder also went through several inspections focused on bus connections and insulation. Resistance checks of the OH feltmetal indicate all three joints are well within spec (< 1 uOhm). With these tests completed, the remainder of the cryostat was installed, bolted together, and fiberglassed. The boots that seal the horizontal and vertical ports to the cryostat were put in place this week, and final sealing to the cryostat is underway. Insulation to protect the horizontal inner seals from liquid nitrogen was also installed. Installation of the igloo around the cryostat will begin early this week as the boot seals are completed. A great deal of work has been done by the Vacuum group over the last week. All upper vertical port crosses and tees have been installed. With completion of work on the horizontal port extensions, the lower cryostat was raised. This operation allowed work to begin on the lower vertical ports. Seven out of nine lower crosses and tees have been installed allowing the installation of diagnostic cabling and periscopes to begin. The lower TCI gatevalve has also been installed. Now that the cryostat upper cover is in place, we can also install the upper TCI and PCI gatevalves. Invessel work included the installation of a new inner wall strain gauge which is located between the two rangefinder retro-reflectors. Both relative movement and the resulting strain will therefore be measured at this location. This information will be very useful as we complete the design of the new inner divertor and plan for higher current operation. The AB split limiter was also installed last week and cabling for the new MHD coils located on the limiter was begun. Studs were also installed at the limiter midplane for the new TTCI retro-reflector mount. A test fitup of the CXRS optics was completed and minor alignment modifications made. Installation of the MSE optics continued. The installation of the J-port antenna has been delayed because of difficulties encountered in re-plating the current straps, and some rework required to the Faraday screens. A very thick coating of nickel was found under the copper plating which took several days to strip. However, the straps are now back in house, visually appear to be in very good condition, and have survived a very severe tape pull test and 400C bake cycle without blistering. They will be ready for installation early this week. The Faraday screens are back at PPPL being reformed to the proper shape after they suffered some distortion during their final bake process. We expect to have the screens back in house ready for installation late this week. Remaining activities invessel include installation and calibration of several diagnostics, re-attachment of the diborane gas feed manifold, and installation of the glow discharge cabling. Installation of the divertor bypass flaps is scheduled for midweek. Preparations by the RF group for the upcoming campaign are continuing. Antennas D and E and their feedthroughs are installed in the machine. Transmitters FMIT#1 and #2 which power the D and E antennas, respectively, have been tested (1.8 MW each into the dummy load). The associated resonant loops have been assembled and await installation. D and E antenna instrumentation installation is approaching completion. System testing remains to be done. FMIT#4, which together with FMIT#3 will power the new J-port antenna, is still awaiting arrival of the repaired FPA tube. We expect the tube to be in house within the next two to three weeks. The resonant loop design is undergoing a final design review. All components of the J-port antenna have now passed the tape pull test and a 400C bakeout without blistering. The J-port antenna feedthroughs have been leak checked, and the external support for them has been fabricated. A final alignment of the antenna at PPPL is now underway in preparation for installation. The layout for the board controlling the DNB Mod/Reg protection crowbar was completed, checked, and after a few modifications will be sent out for fabrication next week. Some parts on the grid drive board for the Mod/Reg were exchanged for modern components so that the layout of the PC board can begin next week. Work continued on the tube regulator and monitor boards for the Mod/Reg. Conditioning of the oil in the DNB accelerator power supply is complete. Travel and Visits: Many people from PPPL visited last week as part of the PPPL/MIT collaboration. David Mikkelsen, who visited all last week is now a regular part of the PPPL collaboration. He will be working on transport modelling. Gary Taylor visited to work on the GPC2 instrument. Norton Bretz and Dave Cylinder were here several days working to install the MSE diagnostic. Gerd Schilling returned to help both with the new J-port antenna and re-installation of the D and E port RF systems. Les Gereg and Joe Frangipani were also here working on the J-port antenna installation. Many of these people will also be here this week finishing up installation of their invessel components. Amanda Hubbard visited the Centre Canadien de Fusion Magnetique and INRS-Energie, in Varennes, Quebec, serving as external examiner for a Ph.D. thesis. Miklos Porkolab visited General Atomics on Monday, Nov. 30th, and gave a presentation on the Lower hybrid Current Profile Control Experimental Proposal for C-Mod. He also participated in discussions clarifying AT physics issues and requirements on profile control in ongoing tokamak experiments, including C-Mod, DIII-D and tokamaks abroad.