Alcator C-Mod Weekly Highlights Nov 15, 1999 Plasma operations continued on Alcator C-Mod last week. This was the final week of operation during the 1999 Experimental Campaign. Field and current were returned to their normal direction. Four run-days were scheduled and completed. A total of 66 plasma shots were produced, with a startup reliability of over 90%. The facility is now being warmed up to room temperature in preparation for the upcoming vent. All of the runs last week were devoted to obtaining performance data on the J-port four-strap ICRF antenna. Systematic scans of target plasma parameters, including field, density, current, outer gap, and vertical position were performed. J-port operation at 0-pi-0-pi phasing was compared with 0-pi-pi-0, and with the D-port dipole antenna. The J-port antenna appears to have a limit on power density above which significant impurity injection events occur. This limit, which was evaluated at ~700kW per strap pair (~1.4MW total) early in the week, was found to depend only weakly on target conditions. Most of the physics activity during the past week was concentrated on preparation of presentations for the APS Division of Plasma Physics Meeting this week. A total of four invited talks and forty-five contributed presentations are being given by C-Mod staff and collaborators. We continued work on the DNB last week. Now that machine operation has ended we expect to have more access to the power room where the DNB hardware is located. Installation of the HV cable tray in the cell was started. PLC program testing for mod/reg and HV supply continued. Some problems with the PLC system have been found and will be debugged and fixed early this week. Internal wiring for ground and return buses continued. MCL modification work has begun. Work continued this week on the DNB platform in the cell, and work began on bringing up the mod/reg control circuits. The mod/reg cabinet and cage was powered up remotely by PLC for the first time, and filament voltage and grid voltage were turned on (tube not installed). Problems were encountered in testing anode current monitors. Bad solder connections on the Hall sensor boards were found and fixed. The final calibration of the analog signal fiber optics was started. Travel and Visitors -------------------- Thomas Sunn Pedersen went to Columbia University to give their Friday seminar; his talk was entitled 'Measurements of H-mode impurity transport in the Alcator C-Mod edge' Gary Taylor (PPPL) was back at MIT continuing his discussions with Paul Bonoli and Eric Nelson-Melby on modeling of ICRF electron heating experiments. At PPPL, Cynthia Phillips supported these discussions with modeling calculations using the METS code. Norton Bretz continued to prepare the installation of the MSE external optics and data aquisition sytem for C-Mod, which he expects to bring up in early December when machine access becomes available. Raffi Nazikian is continuing to set up reflectometry hardware for checkout prior to installation at C-Mod during the coming opening. Stewart Zweben is preparing the preliminary design review for the new edge turbulence imaging diagnostic.