Alcator C-Mod Weekly Highlights Mar 7, 2005 FY 2005 weeks of research operation planned: 17 weeks, completed: 1 week. Plasma operations resumed at Alcator C-Mod last week. Four run days were scheduled and completed, including three days of research operation and one conditioning run. Also during last week, the lower hybrid system operated into C-Mod plasmas for the first time. Operations are planned to continue this week. Operations ---------- Following the scheduled maintenance period, we resumed plasma operations on Tuesday, March 01. The operating schedule remains on a split shift, with runtime between noon and 19:00, in order to accommodate on-going work in the cell and power room. During four runs last week, we produced a total of 66 plasma discharges with a startup reliability of 72%. Experiments were carried out in support of research in the MHD and Divertor/Edge Topical Science areas, as well as one day dedicated to conditioning of the ICRF system. During the run on Friday, the Lower Hybrid system was operated into plasma for the first time. Tuesday's run was dedicated to MP#413, "B-field scaling of error threshold at constant q95 and normalized density", from the MHD Stability Group. For this run the locked mode threshold was observed in a series of discharges with 3