Alcator C-Mod Weekly Highlights January 8, 2007 FY2007 weeks of research operations: tentative target: 15 weeks Completed: 0 weeks Physics ------- Several C-Mod Ideas Forum follow-up meetings took place last week on ICRF, Transport, Divertor/Edge, and Integrated Scenarios (ITER H-mode baseline). All were available for remote participation by video conference. Participating off-site institutions included U. Texas, GA, and PPPL. Additional follow-on meetings are scheduled for this week on MHD, Lower Hybrid, Diagnostics and Operations, and the Integrated Scenarios (Advanced Scenarios) thrust. The schedule for the meetings can be found at http://www.psfc.mit.edu/cmod/sciprogram/ideas2007/ Operations ---------- The cryopump shim plates have been installed in-vessel and will be torqued down following installation of other components. The upper chamber Rogowski coils were also installed last week with cabling for the new coils to be installed this week. The shutter assembly for the polarimeter retro-reflectors has been successfully operated in-vacuum a sufficient number of cycles to indicate a long lifetime relative to a C-Mod campaign. The in-vessel installation of the tubing required to operate the shutter is also complete. Installation of the new liquid nitrogen feedlines, and GN2 exhaust system refurbishment continued last week. Long Pulse Diagnostic Neutral Beam ---------------------------------- The DNB has been moved back into position at F-Port and aligned to its new toroidal angle of 7 degrees. Re-connection of subsystems has begun, and installation of beam duct components including the ceramic break, bellows, and gate valve will begin soon. Diagnostic installation on F-Port horizontal flange continues. Lower Hybrid System ------------------- Klystron conditioning for the next run campaign was completed last week with all twelve lower hybrid klystrons operating for half-second pulses at at least 230 kW each. Our investigation of the faulted klystron circulator indicates that partial braze flow at the joints between waveguide flanges and the circulator housing resulted in below spec operation of this component. Several other circulators may have similar issues. We are now in communication with the vendor. Work continued on the klystron test stand as equipment enclosures and instrumentation boards were completed and testing was begun. ICRF Systems ------------ The J-Port horizontal flange has been installed and passed its first leakcheck. E-Port horizontal flange installation has begun. Cabling for the Fast-Ferrite-Tuner (FFT) is now in-house and being installed, and the FFT interlock board is ready to test as soon as field programmable gate array programming is done. Tests of the system with the magnet supplies will then be possible. Travel and Visits ----------------- Xinjun Zhang, a visiting graduate student from ASIPP, China, completed an 8-month visit to the C-Mod group. He worked with Paul Bonoli and John Wright using the TORIC code to study the ICRF physics scenarios on the new EAST tokamak in ASIPP. _______________________________________________ Cmod_weekly mailing list Cmod_weekly@lists.psfc.mit.edu http://lists.psfc.mit.edu/mailman/listinfo/cmod_weekly