Alcator C-Mod Weekly Highlights January 16, 2007 Physics ------- Follow-on meetings to the C-Mod Ideas Forum were held last week on MHD, Lower Hybrid, Diagnostics and Operations, and the Integrated Scenarios (Advanced Scenarios) thrust. All follow-on meetings have now been held and summaries may be found at: http://www.psfc.mit.edu/cmod/sciprogram/ideas2007/ Operations ---------- The diesel generators that provide emergency backup power for the alternator and other critical C-Mod systems were successfully tested last week along with the system transfer switches. This test is done before beginning a C-Mod run campaign. The liquid nitrogen distribution block on the South cell wall has been removed for service and reconfiguration. The block will be fitted with new liquid nitrogen valves and insulation, and will be prepared to service both the DNB and the new in-vessel cryopump. A tablet PC based checklist for alternator startup has been developed for use during the next run campaign. The tablet PC will be carried by the technician as the checklist is performed, and the results will be archived. Installation of the new upper chamber Rogowski coil cabling was completed last week. Fabrication of components for bolometry, polarimetry, and other diagnostic systems continued. Cryopump -------- All fit-ups of the C-Mod upper chamber cryopump have been completed and all components are now prepared for installation. Last Friday a meeting was held to go over installation plans and resolve any last remaining issues before installation of the pump begins early this week. Long Pulse Diagnostic Neutral Beam ---------------------------------- The gatevalve between the Long Pulse DNB and C-Mod has been reinstalled. The DNB water cooling system is operational. The liquid helium gantry and vacuum lines have been re-installed. High voltage racks #6 and #7 have been moved into position and reconnected. The vacuum system has been reassembled, and control and vacuum gauge installations have been completed. The DNB vacuum chamber is now under vacuum. Lower Hybrid System ------------------- A teleconference with the vendor for the klystron circulators was held last week. After detailed discussions with the vendor about the faults that had been observed, and the construction of the circulators, one of the circulators was partially disassembled and repaired. The circulator has been successfully operated with 1 second pulses at 250 kW. We will continue to inspect, repair, and test the remaining circulators. Tests of the E-Plane waveguide prototype at 2 to 8 times the peak power expected during operation (depending on the assumed reflection coefficient) have been successfully completed. The gap and offset of the waveguide sections were varied during these tests to simulate potential assembly and fabrication errors. ICRF Systems ------------ The inter-rack cabling between cabinets has been completed for the Fast Ferrite Tuner (FFT). A terminal block assembly is also in place to manage the fan out connections from the cables to the PLC and other locations. The first draft of the program for the CPLD (Complex Programmable Logic Device) board has been completed and is being tested. The overload and sensor units should be operational in a few days. _______________________________________________ Cmod_weekly mailing list Cmod_weekly@lists.psfc.mit.edu http://lists.psfc.mit.edu/mailman/listinfo/cmod_weekly