Alcator C-Mod Weekly Highlights April 21, 2009 FY2009 weeks of research operations: Target: TBD Completed: 0 weeks Alternator ---------- Following a routine inspection of the alternator in the summer of 2008, the original equipment manufacturer recommended that the generator rotor not be returned to service. Subsequently, we embarked on a process to re-evaluate the rotor's fitness for service. This process has involved multiple steps: a complete non-destructive evaluation (NDE) re-inspection, including boresonic ultrasound imaging, visual inspection and surface eddy current probing; removal of two bore sample rings; extensive materials testing of the bore samples, including chemical analysis, tensile, fracture toughness and crack growth measurements, and microstructure and fractographic analysis. Two outside companies, experts in the field of generator rotor safety evaluation for the electrical utility industry, were contracted to examine all of the data (both NDE and from the materials samples), and to give their independent recommendations with regard to fitness for service of our rotor. All materials tests showed that the rotor steel has good properties, well beyond the “conservative” assumptions normally used by industry consultants in the absence of actual measurements on a specific rotor. Both outside expert companies have certified that the rotor is fit for continued service, with large margins of safety. A panel of experts assembled by MIT's Vice President for Research has concurred with these findings and recommendations, and last week the Vice President endorsed return to service for the alternator. Re-assembly of the alternator is scheduled to begin early next week. C-Mod Reassembly ---------------- The horizontal port extensions needed for installation of the ICRF antennas have been installed, and re-assembly of the antennas in-vessel has begun. Installation of the cryostat that surrounds the machine has also begun. After inspection and re-plating, re-assembly of the power room TF and PF bus system was started. Lower Hybrid System ------------------- Fabrication of the 4-way splitter prototype housing has been completed and preparations are being made to braze the windows into the waveguides for installation on the prototype. High power testing of the prototype is expected to begin next week. Four of the production 4-way splitters (out of sixteen) are complete and undergoing inspection before the four front waveguides housing the vacuum windows are welded in place. Development of rf probe electronics continued last week. Re-assembly of the alternator is scheduled to begin early next week. ICRF Systems ------------ All low power components needed for the RF Control System Upgrade have been specified and are on order. Layout of the Master Fault Processor Mezzanine board continued last week. The FMIT#3 transmitter driver will be ready for tests into a dummy load this week. The driver stage will be used to power the rf test stand. Travel and Visits ----------------- Steve Wolfe participated remotely in the Meeting of the ITER Research Plan Working Group in Caderache, France, April 15-17. This group, headed by David Campbell, IO, is updating and extending the ITER Research Plan Document. Version 2 is to be presented at the 6th meeting of the ITER Science and Technology Advisory Committee (May 25-27). The other U.S. members of the Working Group are Michael Bell, PPPL, Stan Milora, ORNL, Ed Synakowski, LLNL, and Mickey Wade, GA. _______________________________________________ Cmod_weekly mailing list Cmod_weekly@lists.psfc.mit.edu http://lists.psfc.mit.edu/mailman/listinfo/cmod_weekly