Alcator C-Mod Weekly Highlights August 29, 2011 FY2011 weeks of research operations Target: 15 weeks Completed: 14.5 weeks Plasma Shots: 1706 Operations ---------- Fabrication of the new G-Port horizontal extension is complete, and it has been successfully leak-checked. The new extension allows for easier vessel entry and exit. Modifications to the B-Port horizontal flange are complete, and it also has been successfully leak-checked. The changes to this flange provide access for the new RFQ accelerator and associated diagnostics. ICRF Systems ------------ High voltage testing of FMIT#3 and #4 has been completed, including crowbar wire tests. These transmitters will be ready for plasma operation following rf testing into a dummy load. All forty-eight 1/2 inch studs required to support the new ARRA funded rotated antenna have been installed and pull tested to 10,000 lbs. Installation of the antenna back plates has begun. A picture of the plates in-vessel can be found at http://www.psfc.mit.edu/research/alcator/photos//INVESSEL/2011/4%20strap%20antenna/DSCN7859.JPG Lower Hybrid Systems -------------------- All components for the new LH limiter have been prepared for installation. The existing limiter has been removed. Installation in-vessel will begin soon. The new klystron filament power supplies arrived from the vendor last week. The components are being removed from their crates and inspected. Diagnostics ----------- Progress on the CECE diagnostic last week included laboratory testing of the mirrors and mirror assembly. The flat mirror and parabolic mirror were installed and aligned in the housing, and then the focusing properties of the two-mirror system were measured and found to agree with design specifications. Several different alignment procedures were tested in preparation for the up-coming in-vessel installation. All tests were done using a laboratory test stand with the same lasers and target sets that will be used during installation. Based on results of these tests, two new targets will be made to add additional constraints to the alignment during installation. Upgrades to the C-Mod Thomson scattering system include the replacement of two aging 30 Hz Nd:YAG lasers with two 50 Hz units, operating at similar levels of energy per pulse. The vendor has completed assembly and initial testing of the two units. QA is proceeding. The lasers are expected to ship to MIT in mid to late September. Remote Participation, Travel, and Visitors ------------------------------------------ Jerry Hughes traveled to Santa Clara, CA to meet with laser vendor representatives to discuss production status and to inspect the new lasers. While there, he received instruction from a training engineer in the detailed maintenance and troubleshooting of the units. Subsequently he visited LLNL to meet with X. Xu and other staff physicists to discuss C-Mod pedestal experimental results and modeling efforts related to the FY11 JRT, as well as plans for future collaboration. _______________________________________________ Cmod_weekly mailing list Cmod_weekly@lists.psfc.mit.edu http://lists.psfc.mit.edu/mailman/listinfo/cmod_weekly