Big Lift Checklist v10/19/98 jhi The following tests should be done before the big lift. They should be done in addition to any test already in Jim Rosati's assembly procedure. Please date and initial line items as they are performed. Perform 100 volt mega of TF core (and lower arms) Perform Hi-pot of first-to-last turn TF feltmetal check drive 100 amps through arm and core plates measure voltage across feltmetal pads all voltages should be below 25 uOhms Measure OH2L feltmetal resistance drive 100 amps through OH2L coil feltmetal contact resistance should be less than 1 uOhm check operation of both TCs Check OH position sensors check coil continuity check for faults to ground make sure leads are protected for big lift Check OH flux loops check loop continuity check for ground faults Check Heater and TC procedure provided by Willy Burke