* Verify no magnetic material (magnet) * Pierson/Vieira test on components (yank on them...) * Torque spec of : Divertor modules- Mother bolts 55 ft/lbs Sliding bolt 25 ft/lbs Limiters- Beehive nut 15 ft/lbs Antennas- Moly tiles 22 ft/lbs 5/16 x 16 13 ft/lbs ¼ x 20 7 ft/lbs * Check various brackets for tight bolts/nuts * Cable tray cover plates secured (lift side ears to block nut) - top - down * Verify glow discharge (not shorted) - verify continuity with ohm-meter - HI-POT * verify Diborane - check all tubes, and fittings (B) * Remove unneeded T/C top (cut) - verify underneath outer divertor * Measure position of LH couplers in relation to LH Limiter * - Top right/left corner gaps - Bottom right/left corner gaps * Secure capillaries - K bolo (main and ledge) * Secure telescopes * Measure locations (radial) - antennas - limiters * Verify Thomson dumps and baffles * Check below/above and behind antennas * Operate shutters one last time * Verify (black) dump for - Z meter array (wall)(BC area) * Others * Digital camera survey * Remove covers * - vertical ports - shutter (A) - F (scanning probe cover) - F poloidal view telescope (foil) - tex wipes * Final Vacuum