Alcator C-Mod Run 1000606 Information

Back to runs

Miniproposals
Miniproposal:233a
Date Filed: 3/28/2000
Title:Density Limits
First Author:Martin Greenwald
Session Leader:Martin Greenwald (shots 1-16)

Operators
Session leader(s):Martin Greenwald
Physics operator(s):Robert Granetz
Engineering operator(s):Bill Cochran

Engineering Operator Run Comment
MP# 233A Density Limits.Greenwald/Granetz/Cochran.

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:24:040PM
Author: To Be Determined
Run Plan
mp 233a Density limits
(H-mode task force)

Session Leader - Greenwald
Phys Op - Granetz mostly

============================

Plan:

1. scaling of pedestals/edge parameters near the density limit - in
particular we will be varying Bt and Prf to try to get a wide range
in beta. (The Rogers and Drake simulations have a significant
dependence on the mhd alpha parameter.)

2. fluctuations near the density limit (both H/L and disruptive).

The run follows the general approach of 980115 where we ran high
density H-modes then ramped the current down to the density limit.
The RF needs to be on steadily to the end of the shot.

The plan is to start at 5.3T then move to 4.5T and finally to 6.0.
The 6T shots will be ohmic and we will be looking at the disruptive
limit only

The outer gap should be in the range 1-1.5 cm so that we can get
good data from the Lyman alpha array.

=======================================================

Results:

Not a very productive day. Start was delayed by 4 1/2 hours
by a problem with a circuit board in a TF power supply cabinet.
We lost the last 1/2 hour to a breaker fault.

In between, we made a little progress on the mp. Early shots
007-010 were plagued with impurity injection. Speculating that
the source was with the RF, we shut it down for shot 011. That
shot lasted longer - the interferometer shut down half way through
that shot.

Starting with shot 012, we were able to extend the shot into the
high density region. 013 and 014 had brief H-modes and disrupted
roughly at 90% of the empirical limit. The H/L transition was at
relatively low density.

Shots 013 and 014 were also interesting in that they showed some
modest density peaking toward as the limit was approached. We
should look at the profiles.

Note: Two puff valves were required to reach the density range of
interest.


================================

Shots suitable for further analysis include:

1000606013
1000606014

Physics Operator Summaries
Entered: Jul 7 2004 04:37:11:083PM
Author: To Be Determined
Physics operator summary for run 1000606:

MP 233A -- Density limits

Session leader: M. Greenwald
Physics operator: R. Granetz
Engineering operators: B. Cochran

Summary: Once plasma operation began in the afternoon, things went pretty
smoothly, at least from an operations standpoint. But the entire
morning was spent trying to debug a faulty circuit board in one of
the TF cabinets, and consequently we only had 9 plasmas. Most of
these disrupted a little below the expected density limit (for
example, shots 12 and 16), but shots 13 and 14 apparently reached
the density limit. Brian got some interesting scanning probe data
on shot 14 as well. The RF had difficulty coupling into the high
densities. The run ended a little early due to a TF breaker
problem.

Scorecard: 9 plasmas
1 fizzles
0 duds
6 tests
0 aborted
----------
16 total

-------------------------------------------------------------------------------

Engineering setup for Tuesday, 06 June 2000:

Overnight ECDC in D2, stopping 1-2 hours prior to the run.

Run begins at 9:00 and ends at 17:00.

Power system setup as on 1000602001 (last Friday morning), including
fizzle delay settings

Gas setup - fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
leave B-side upper as is Hybrid DISABLED
fill C-side with 30 psi of D2 Hybrid enabled
leave J-bottom as is Hybrid DISABLED

The following gate valves should be enabled, assuming no vacuum problems:
ECE, VUV, DNB

The first two shots will be a standard OH test and an EF4 test.

-------------------------------------------------------------------------------
Run plan: MP# 233A -- Density limits

SL: M. Greenwald
PO: R. Granetz (and maybe J. Irby ?)

Ramp current down dynamically to get density limit disruptions. Get probe
fluctuation measurements and pedestal profile measurements as the density
limit is reached. Do this at three fields (5.3, 4.5, 6.0 T), keeping q95
the same (Ip=1.0, 0.85, 1.15 MA respectively). Have RF power from D and E
antennas for 5.3 and 4.5 T shots to get H-modes, and subsequent H-L
transitions just prior to density limit disruptions. High density is
desired (nebar=4-5e20 m-3 or more). Outer gap=1.0-1.5 cm.

Note: keep Btor flattopped (except for usual waggles for ECE) until after
the density limit is reached. Then rampdown Btor at the restricted rate
of 75-100 kA/s.

-------------------------------------------------------------------------------

Overnight ECDC in D2 was done, stopping 2 hours prior to the run

Hybrid coldstart done; no errors found

Loaded 1000602014 and set current to 1.0 MA, starting rampdown at
t=0.70 s, with dIp/dt=-0.9 MA/s. Btor=5.3 T (constant until t=1.5 s).
nl_04=2.0e20 m-2. RCUR changed to give outer gap = 13 mm.

-------------------------------------------------------------------------------

Shot 01 -- Test; Usual Tuesday OH coax test.

Coax Resis (uohm)
---- ------------
OH1 0.42
OH2U 0.21
OH2L 0.29

Irby says 'Go'.

Shot 02 -- Test; No-power cycle. This was supposed to be an EF4 shunt test,
but there was a problem with a PLC controlling communication with
the alternator.

Shot 03 -- Test; EF4 shunt test under PLC control. Looks good.

There's a problem with an IOC fault in one of the TF cabinets.
We are having a delay while Bill Cochran checks it out.

Shot 04 -- Test; 50 kA TF-only, under PLC control. All okay during the
current pulse, but the IOC fault popped up again after the
shot.

We'll have another delay while the engineers continue looking into the problem.

Jim Irby will be substituting for me from 12-14:00 today. That change will
start now, prior to shot 05.

Shot 05 -- Test; 50 kA TF-only test under PLC control. Okay.

Shot 06 -- Test; 100 kA TF-only test under PLC control. Okay.

Shot 07 -- Plasma. Disrupted at t=0.99 s, during the current rampdown.

Next shot: increase pre-fill puff by 3 ms.

Granetz returns as physop.

Shot 08 -- Plasma. Disrupted at t=0.97 s, during the current rampdown. Outer
gap was 2 cm and increasing. I think it may have been going
vertically unstable. This was not a density limit disruption.

Next shot: decrease outer gap by 1 cm (increase RCUR by 5 mm). This
will also help any vertical stability problem. Also increase
nl_04 to 2.4e20 m-2.

Shot 09 -- Plasma. Disrupted at t=0.94 s. This was a thermal quench,
due to some impurity problem.

Next shot: tweak CLEARIN to keep both gaps more constant during
the rampdown. Also fill J-bottom plenum with 30 psi of D2, but
don't enable the valve yet.

Shot 10 -- Plasma. Disrupted at t=0.98 s. This was another thermal quench,
but not a density limit disruption.

Next shot: no RF. Also tweak RCUR/outer gap a little more. Also
add 3 ms to pre-fill puff to compensate for the DNB, which will
now remain closed for the rest of the run.

Shot 11 -- Plasma. Disrupted at t=1.29 s, when Ip got down to 0.44 MA.
TCI has no signal after t=0.8 s. This was an ohmic shot. Outer
gap grows to 3 cm.

Next shot: turn RF back on. Program a 1 cm outward ramp in RCUR.
Enable J-bottom valve, using preprogrammed waveform. Also add
2 ms more to pre-fill puff.

Shot 12 -- Plasma. Disrupted at t=1.13 s. Density was higher, but RF faulted
early without any clear H-mode. Outer gap was steady at 1 cm.
J-bottom valve gave gas, but it's voltage doesn't show up on the
digitizer.

Next shot: repeat, with only minor tweaks to CLEARIN.

Shot 13 -- Plasma. Disrupted at t=1.14 s when Ip=0.59 MA. Outer gap is
6-10 mm. Inner gap=14-16 mm. RF faulted early again. Density
was nearly at the expected density limit. H-mode would have done
it easily.

Next shot: repeat, no PCS changes.

Shot 14 -- Plasma. Disrupted at t=1.14 s when Ip=0.56 MA. This might have
been at the density limit. RF needs more tweaking. Brian fired
the A scanning probe at 0.6, 0.8, and 1.05 s.

Next shot: repeat, no PCS changes.

Shot 15 -- Fizzle.

Next shot: add 10 amps to IC_EF4.

Shot 16 -- Plasma. Disrupted at t=1.05 s when Ip=0.64 MA. Didn't quite make
it to the density limit.

After this shot, a motor in one of the TF mechanical breakers was found to
have burned up. That forced us to end the run early.

Session Leader Comments
Jun 6 2000 09:06:54:827AMMartin GreenwaldPlan:

1. scaling of pedestals/edge parameters near the density limit - in
particular we will be varying Bt and Prf to try to get a wide range
in beta. (The Rogers and Drake simulations have a significant
dependence on the mhd alpha parameter.)

2. fluctuations near the density limit (both H/L and disruptive).

The run follows the general approach of 980115 where we ran high
density H-modes then ramped the current down to the density limit.
The RF needs to be on steadily to the end of the shot.

The plan is to start at 5.3T then move to 4.5T and finally to 6.0.
The 6T shots will be ohmic and we will be looking at the disruptive
limit only

The outer gap should be in the range 1-1.5 cm so that we can get
good data from the Lyman alpha array.
Jun 6 2000 09:08:18:623AMMartin GreenwaldBackground:

Earlier work[1] has suggested that the tokamak density limit can
be explained fully only by consideration of transport effects. While
there is little dispute about the final stages of a density limit
collapse - edge cooling via radiation then shrinkage of the current
channel leading to MHD instability and disruption - theories based
on edge power balance physics alone can not explain important aspects
of density limit phenomenology. In particular, the power balance
theories predict a density limit with strong dependence on input power
and on impurity content. Neither of these dependences are generally
observed. These classes of theories also have difficulty explaining the
robustness of the density limit with respect to plasma configuration,
divertor topology, or operational regime. Finally there is data from
Alcator C, TEXT, and MTX (nee Alcator C) which show degradation of
particle confinement or enhanced fluctuations in the vicinity of the
limit.

The work by Drake and Rogers suggest a specific turbulence mechanism
for this phenomenon. The simulations show a boundary, above which
fluctuations increase dramatically from nominal ``L'' mode levels.
This boundary has somewhat complex parametric dependence but has
much in common with the empirical limit derived in reference [1]. The
edge pressure gradient is an important parameterization for the
computationally derived boundary - thus we propose a power scan as
part of this mp. We note in passing, the rough agreement with the
L/H threshold of simulations carried out with the same code [4].

Recent studies by LaBombard [2] have suggested that the edge
diffusivity increases strongly with local collisionality. Since the
edge temperature is roughly fixed by parallel transport, this
correlation is consistent with an increase in transport as the
density is increased.

A number of machines have reported a degradation in H-mode confinement
as the density limit is approached. This effect apparently sets in at
lower densities for P $\sim$ P$_{THRESHOLD}$. So far, C-Mod H-modes have
been in this regime. With additional RF power we should be able to
access the regime with P $>>$ P$_{THRESHOLD}$.

[1] M. Greenwald, et al., ``A New Look at Density Limits'', Nuclear Fusion
28 12 (1988) 2199

[2] LaBombard, 1999 APS

[3] Rogers and Drake, Phys. Rev. Letters 79 229 (1997)

[4] Hubbard et al, ``Measurements of the High Confinement Mode Pedestal
Region on Alcator C-Mod'' Phys. Plasmas, 5 (1998) 1744.



Jun 6 2000 01:31:10:607PM1000606007Martin GreenwaldFirst plasma shot after long delay for TF control electronics problem
disrupts at .95 sec

2 MW on RF
H-mode
Lots of little injectins

nice striations on the fast camera
Jun 6 2000 01:46:54:077PM1000606008Martin GreenwaldDisrupts before 1 second again

Jun 6 2000 02:09:32:607PM1000606009Martin Greenwaldjust about the same as the previous 2 shots
Jun 6 2000 02:47:22:263PM1000606010Martin Greenwaldsame again - maybe killed by discrete injections
Jun 6 2000 02:57:41:857PM1000606011Martin GreenwaldRF turned off for this shot
lasts til 1.3 seconds
interferometer not working
Jun 6 2000 03:18:34:857PM1000606012Martin GreenwaldRF back on, but trips early
lasts til 1.13 seconds
very brief H-mode
L-mode density near limit at disruption (0.85)
Jun 6 2000 04:33:22:543PM1000606013Martin GreenwaldShort RF pulse again
Short H-mode
essentially reaches density limit
density peaking seen toward end of shot
Jun 6 2000 04:33:05:390PM1000606014Martin GreenwaldSimilar to shot 13
scanning probe inserted
density peaking seen toward end of shot
Jun 6 2000 04:13:28:263PM1000606015Martin Greenwaldfizzle

Physics Operator Comments
Jun 6 2000 09:04:54:200AMRobert GranetzEngineering setup for Tuesday, 06 June 2000:

Overnight ECDC in D2, stopping 1-2 hours prior to the run.

Run begins at 9:00 and ends at 17:00.

Power system setup as on 1000602001 (last Friday morning), including
fizzle delay settings

Gas setup - fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
leave B-side upper as is Hybrid DISABLED
fill C-side with 30 psi of D2 Hybrid enabled
leave J-bottom as is Hybrid DISABLED

The following gate valves should be enabled, assuming no vacuum problems:
ECE, VUV, DNB

The first two shots will be a standard OH test and an EF4 test.
Jun 6 2000 09:05:09:607AMRobert GranetzRun plan: MP# 233A -- Density limits

SL: M. Greenwald
PO: R. Granetz (and maybe J. Irby ?)

Ramp current down dynamically to get density limit disruptions. Get probe
fluctuation measurements and pedestal profile measurements as the density
limit is reached. Do this at three fields (5.3, 4.5, 6.0 T), keeping q95
the same (Ip=1.0, 0.85, 1.15 MA respectively). Have RF power from D and E
antennas for 5.3 and 4.5 T shots to get H-modes, and subsequent H-L
transitions just prior to density limit disruptions. High density is
desired (nebar=4-5e20 m-3 or more). Outer gap=1.0-1.5 cm.

Note: keep Btor flattopped (except for usual waggles for ECE) until after
the density limit is reached. Then rampdown Btor at the restricted rate
of 75-100 kA/s.
Jun 6 2000 09:05:22:623AMRobert Granetz Overnight ECDC in D2 was done, stopping 2 hours prior to the run

Hybrid coldstart done; no errors found

Loaded 1000602014 and set current to 1.0 MA, starting rampdown at
t=0.70 s, with dIp/dt=-0.9 MA/s. Btor=5.3 T (constant until t=1.5 s).
nl_04=2.0e20 m-2. RCUR changed to give outer gap = 13 mm.
Jun 6 2000 09:14:36:937AM1000606001Robert GranetzShot 01 -- Test; Usual Tuesday OH coax test.

Coax Resis (uohm)
---- ------------
OH1 0.42
OH2U 0.21
OH2L 0.29

Irby says 'Go'.
Jun 6 2000 09:28:50:607AM1000606002Robert GranetzShot 02 -- Test; No-power cycle. This was supposed to be an EF4 shunt test,
but there was a problem with a PLC controlling communication with
the alternator.
Jun 6 2000 09:53:52:153AM1000606003Robert GranetzShot 03 -- Test; EF4 shunt test under PLC control. Looks good.
Jun 6 2000 09:54:25:607AM1000606003Robert GranetzThere's a problem with an IOC fault in one of the TF cabinets.
We are having a delay while Bill Cochran checks it out.
Jun 6 2000 10:46:30:857AM1000606004Robert GranetzShot 04 -- Test; 50 kA TF-only, under PLC control. All okay during the
current pulse, but the IOC fault popped up again after the
shot.

We'll have another delay while the engineers continue looking into the problem.
Jun 6 2000 11:55:56:297AM1000606004Robert GranetzJim Irby will be substituting for me from 12-14:00 today. That change will
start now, prior to shot 05.
Jun 6 2000 02:02:38:763PM1000606005Robert Granetz50 kA TF test.

Looks good

(This is really Jim Irby substituting for Granetz.)
Jun 6 2000 02:03:03:577PM1000606006Robert Granetz100 kA TF shot

(This is really Jim Irby substituting for Granetz.)


Jun 6 2000 02:04:19:700PM1000606007Robert GranetzPlasma to 0.995 seconds

Looks like current rise is a little fast

(This is really Jim Irby substituting for Granetz.)
Jun 6 2000 01:52:53:047PM1000606008Robert GranetzAdded 3 ms to pg4 width --- a little more prepuff

Plasma to 0.97 s

(This is really Jim Irby substituting for Granetz.)
Jun 6 2000 01:53:06:920PM1000606008Robert GranetzGranetz returns as physop
Jun 6 2000 01:56:24:687PM1000606008Robert GranetzShot 08 -- Plasma. Disrupted at t=0.97 s, during the current rampdown. Outer
gap was 2 cm and increasing. I think it may have been going
vertically unstable. This was not a density limit disruption.

Next shot: decrease outer gap by 1 cm (increase RCUR by 5 mm). This
will also help any vertical stability problem. Also increase
nl_04 to 2.4e20 m-2.
Jun 6 2000 02:19:24:653PM1000606009Robert GranetzShot 09 -- Plasma. Disrupted at t=0.94 s. This was a thermal quench,
due to some impurity problem.

Next shot: tweak CLEARIN to keep both gaps more constant during
the rampdown. Also fill J-bottom plenum with 30 psi of D2, but
don't enable the valve yet.
Jun 6 2000 02:50:55:763PM1000606010Robert GranetzShot 10 -- Plasma. Disrupted at t=0.98 s. This was another thermal quench,
but not a density limit disruption.

Next shot: no RF. Also tweak RCUR/outer gap a little more. Also
add 3 ms to pre-fill puff to compensate for the DNB, which will
now remain closed for the rest of the run.
Jun 6 2000 03:02:19:123PM1000606011Robert GranetzShot 11 -- Plasma. Disrupted at t=1.29 s, when Ip got down to 0.44 MA.
TCI has no signal after t=0.8 s. This was an ohmic shot. Outer
gap grows to 3 cm.

Next shot: turn RF back on. Program a 1 cm outward ramp in RCUR.
Enable J-bottom valve, using preprogrammed waveform. Also add
2 ms more to pre-fill puff.
Jun 6 2000 03:21:55:670PM1000606012Robert GranetzShot 12 -- Plasma. Disrupted at t=1.13 s. Density was higher, but RF faulted
early without any clear H-mode. Outer gap was steady at 1 cm.
J-bottom valve gave gas, but it's voltage doesn't show up on the
digitizer.

Next shot: repeat, with only minor tweaks to CLEARIN.
Jun 6 2000 03:37:29:730PM1000606013Robert GranetzShot 13 -- Plasma. Disrupted at t=1.14 s when Ip=0.59 MA. Outer gap is
6-10 mm. Inner gap=14-16 mm. RF faulted early again. Density
was nearly at the expected density limit. H-mode would have done
it easily.

Next shot: repeat, no PCS changes.
Jun 6 2000 04:01:29:983PM1000606014Robert GranetzShot 14 -- Plasma. Disrupted at t=1.14 s when Ip=0.56 MA. This might have
been at the density limit. RF needs more tweaking. Brian fired
the A scanning probe at 0.6, 0.8, and 1.05 s.

Next shot: repeat, no PCS changes.
Jun 6 2000 04:17:59:390PM1000606015Robert GranetzShot 15 -- Fizzle.

Next shot: add 10 amps to IC_EF4.
Jun 6 2000 05:00:05:950PM1000606016Robert GranetzShot 16 -- Plasma. Disrupted at t=1.05 s when Ip=0.64 MA. Didn't quite make
it to the density limit.

After this shot, a motor in one of the TF mechanical breakers was found to
have burned up. That forced us to end the run early.

Engineering Operator Comments
ShotTimeTypeStatusComment
109:09:56:497AMTestOkOH Coax Test
209:22:03:293AMTestBadAlternator PLc Fault during Init.
309:34:29:403AMTestOkEF4 Shunt Test
410:33:10:843AMTestOkTF 50 KA Test
512:48:50:640PMTestOk50ka TF test only
601:02:16:250PMTestOk100ka TF test only
701:17:45:390PMPlasmaOk
801:39:51:560PMPlasmaOk
902:05:44:013PMPlasmaOk
1002:25:06:810PMPlasmaOk
1102:47:27:140PMPlasmaOk
1203:07:47:420PMPlasmaOk
1303:27:47:543PMPlasmaOk
1403:49:02:310PMPlasmaOk
1504:10:29:200PMPlasmaOk
1604:27:06:420PMPlasmaOk