Alcator C-Mod Run 1001005 Information

Back to runs

Miniproposals
Miniproposal:
Date Filed:
Title:
First Author:
Session Leader:David Gwinn (shots 1-11)
Session Leader:Steve Wolfe (shots 1-11)

Operators
Session leader(s):David Gwinn,Steve Wolfe
Physics operator(s):Bill Rowan
Engineering operator(s):Gary Dekow

Engineering Operator Run Comment
Engineering tests SL Wolf/Gwinn MP#268 ICRF PO:rowan SL:Wukitch/Boivin E

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:25:007PM
Author: To Be Determined
Run Plan for Friday, Oct 6, 2000

Experiments SL
------------- ----
MP#268 ICRF Wukitch/Boivin
MP#248 High Performance Greenwald
PO: Wolfe

Plan
--------------------
Now that the ground problem has been isolated to the commutation capacitor
bank, we will proceed with plasma operations, in parallel with further
testing to identify and replace the bad capacitor(s). The cap banks will
be put back in their original systems, so that the bad bank is on OH2L,
which has a 150 Ohm resistor in series with the ground fuse. Additionally,
the cap cases will be lifted off ground, and regrounded through an instrumented
line, in groups, so that the one carrying ground current can be determined.
In this configuration, it should be possible to operate the machine
"normally". Getting the cap bank set up may take some time in the morning,
so the run may start late. It will probably be necessary to run some
commutation tests before first plasma to verify the system.

Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicatewhether
we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with MP#248 (H-mode performance at high P_rf).

Engineering Setup
------------------

Overnight ECDC in D2, stopping 2 hours before the run.

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec
_______________________________________________________________________

Cancellation of yesterday's OPERATIONAL RESTRICTION:
--------------------------
Now that the ground problem has been isolated, and shown to pose no
danger to the tokamak, the previously posted requirement to monitor
the ground current and/or voltage on every shot and notify Gwinn, Wolfe or
Irby is RESCINDED.

001
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec

plasma - upper null, good comparison shot
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec one fault on #3

002
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 1.6 MW before #3 screen xbarred
antenna then ran as a monopole and injected junk which killed the plasma

003
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 0.8 MW #3 was faulted by false fault indication

antenna ran as a monopole and injected junk which killed the plasma
remove attempted combined fault indicator for J-port

004 power test
005
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #4 faulted and #3 screen xbarred

006
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #3 & #4 faulted and #3 screen xbarred

007 fizzle

008
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, H-mode with D and E @2 MW
D-port 1 MW 1.1-1.45 sec
E-port 1 MW 1.1-1.45 sec
J-port 2 MW 0.6-1.0 sec need to retune

next shot: inner wall limited008

009
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 2.5 MW 0.6-1. sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port MW 0.6-1.0 sec #3 screen xbarred on fault early

gap was 2 cm good for loading check as function of gap
010

Physics Operator Summaries
Entered: Jul 7 2004 04:37:12:207PM
Author: To Be Determined
PhysOp Summary for 1001005.

Experiments
---------------------------
Engineering tests
SL: Wolfe/Gwinn

MP#268 ICRF
SL:Wukitch/Boivin

PO: Rowan

EO: Dekow

Engineering Setup
------------------
We will presumably need PLC test shots for at least the OH and EF1
supplies (separately), since instrumentation has been modified or disturbed on
all of these since the last run. We may also need to conduct further tests of
the ground fault instrmentation using the hi-pot and ringing supplies.

Once we decide to go to plasma shots:

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec

IMPORTANT NEW RESTRICTION FROM WOLFE:
--------------------------
Throughout the run, someone (Physop, Eng Op, and/or Session Leader must
monitor the OH2L ground resistor voltage (see
cmod$models:[engineering.scopes]scope_gf.dat) on every shot. Any significant (
> 300V) signals must be evaluated by gwinn, wolfe, or irby before proceeding.


Run Plan
--------------------
The run will start with Engineering Tests and these tests will be under the
direction of Wolfe, Dekow, and Gwinn. Once tests are completed, plasma operation
will proceed with a continuation of the evaluation of the J-port four-strap
antenna, as begun on Tuesday. In the event that a significant ground current
event is observed, operation may revert to testing, or terminate, as directed
by Gwinn and or Wolfe. Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicate
whether we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with either MP#282A (current ramps), MP#248 (H-mode
performance at high P_rf).


Summary
-----------------------
Shots 001 through 006 were engineering test shots and are described in the
SL log.

For shot 007, the run was returned to physics operation. Shot 1001003009
was loaded prior to shot 001 in preparation for working on MP 268,
Conditioning of D-, E-, or J-port ICRF Antenna.

Shot 007 was a fizzle. In comparing with the reference shot, the prefill pressure
seemed low. The prefill was increased by 2 ms to 24 ms.

On this shot, the ground fault was again detected.

The remainder of the day was devoted to looking for the problem. See SL
log for details.

Details of the run
------------------------
PCS started at 8:05. Shot 1001003009 was loaded and coldstart completed
by 8:24

PCS started at 8:05
Loaded from 1001003009
Did a Load/Clean
Load at 5-Oct-2000 08:19:51.00
Open tree SCRATCH_DISK:[ROWAN] -1
Open tree done

Did coldstart . No occurences of err.
rtnode -- data loaded, A matrix responds
rtnode -- data loaded, M matrix responds
rtnode -- data loaded, PID matrix responds
RT_NODE Done
5-OCT-2000 08:24:10.62 doing TCL command TYPE *************** END COLD
START ******************
*************** END COLDSTART ******************


001-006. Engineering test shots.

007. Fizzle
3 amps on OH2_L GF at 0.0197 s to 0.217 s
Pressure seems low at approx 0.047 mT

Next shot: Increase prefill by 2 ms. This brings the prefill to 24 ms

008-011. Engineering test shots.

Session Leader Comments
Oct 5 2000 09:51:11:797AM1001005001Steve Wolfeshot#1: EF1 test. All bus signals are present and look ok.
Note that the ef2u bus voltage signal is (and was previously) inverted.

There is a spike on the oh2l ground resistor at .065 sec, amplitude -450V.
No associated signals on anything else, except perhaps a .05A glitch on the
oh2l gf pearson.
Oct 5 2000 10:08:18:060AM1001005002Steve Wolfeshot#2:repeat EF1 test with oh2 resistor divider shorted; common mode test.
noise level is similar with the input shorted. We've bought considerable noise
by putting the divider on the wall.

Gwinn feels we should concentrate on the gf pearsons, and watch for signals of
1 amp or more, instead of the resistor voltage.

Oct 5 2000 10:53:16:107AM1001005003Steve Wolfeshot#3: ef3 test, jumper on resistor divider removed.
clock on machine gf pearsons increased to 3khz
(moved to different ddecoder channel, now on ch3)

Fizzle detector did not take out the ef3. operator hit
the e-stop to turn off the current. It didn't invert
at 2sec either. Actually the supply did invert at 3.47sec,
probably on the backup timer.
Oct 5 2000 12:04:01:750PM1001005004Steve Wolfeshot 4: Engineers found a bad OR gate in the EF3 control circuit.
This will be a no-power test to verify that the fix has worked.

That seemed to work. Next shot, another live EF3 test
Oct 5 2000 12:10:27:140PM1001005005Steve Wolfeshot 5: another live EF3 test
Ok, fizzle detector took it out, as programmed.
Oct 5 2000 12:18:56:200PM1001005006Steve Wolfeshot 6: oh test. sounded good.
There is a single sample spike of 3A on the EF3 gf pearson at -1.090 sec,
just after the OH supplies turn on; otherwise less than .5A
Oct 5 2000 12:48:26:873PM1001005007Steve Wolfeshot 7: set up for a plasma shot. Wukitch in charge, until something bad happens.
Which it just did. POsitive 3A on the oh2l pearson at .0198-.0215sec;
resistor sees +2000V spike followed by +600V flat
There is something on the common mode rogowski, but probably pickup.

We see spikes on the bus voltage traces for OH1, OH2U, OH2L, EF1L, EF2U, EF2L, maybe EF3.
The spike on oh2L is -1500V, OH2U is -400, others are smaller, and OH1 is +500V.

There are negative going spikes on several comm resistor signals, including the OH1 COMA;
thus at least the spike part of these voltage signals is still unreliable!
Oct 5 2000 01:34:42:153PM1001005007Steve Wukitch007 fizzle
3.4 A square pulse on OH2_L GF
Power system group is investigating
Oct 5 2000 03:26:56:933PM1001005008Steve Wolfeshot 8: We are going to investigate the hypothesis that the
ground is appearing in the OH2L commutation circuit. This shot
will be a "no current" commutation test, i.e. just firing the bank.

nothing on the gf signals

next shot: 10Ka oh commutaiton test
Oct 5 2000 03:34:17:810PM1001005009Steve Wolfeshot 9: 10Ka oh commutation test
No gf currents
Oct 5 2000 03:46:11:373PM1001005010Steve Wolfeshot 10: full current oh commutation test, under hybrid control (normal
current program).
No gf currents. no spikes

Oct 5 2000 03:57:48:047PM1001005010Steve Wolfeshot 10: full current oh commutation test, under hybrid control (normal
current program).
No gf currents. no spikes

next shot: swap the commutation banks between OH2U and OH2L
Oct 5 2000 04:49:31:200PM1001005011Steve Wolfeshot 11: swap the commutation banks between OH2U and OH2L;
this will be a plasma attempt

OH2U fuse blown. That was it!.
20A negative gf current in OH2U, goes positice for one sample first.

Physics Operator Comments
Oct 5 2000 08:28:20:153AMBill Rowan
#37 of 37 OPS
Date: 4-OCT-2000 21:54 Expires: 18-OCT-2000 00:00
From: BAROLO::WOLFE
Subj: Setup and run plan for Thursday, Oct 5

Run Plan for Thurs., Oct 5, 2000

Experiments SL
------------- ----
Engineering tests wolfe/Gwinn
MP#268 ICRF Wukitch/Boivin
PO: Rowan

Plan
--------------------
The run will start with Engineering Tests and these tests will be under the
direction of Wolfe, Dekow, and Gwinn. Once tests are completed, plasma operation
will proceed with a continuation of the evaluation of the J-port four-strap
antenna, as begun on Tuesday. In the event that a significant ground current
event is observed, operation may revert to testing, or terminate, as directed
by Gwinn and or Wolfe. Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicate
whether we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with either MP#282A (current ramps), MP#248 (H-mode
performance at high P_rf).

Engineering Setup
------------------

We will presumably need PLC test shots for at least the OH and EF1
supplies (separately), since instrumentation has been modified or disturbed on
all of these since the last run. We may also need to conduct further tests of
the ground fault instrmentation using the hi-pot and ringing supplies.

Once we decide to go to plasma shots:

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec
_______________________________________________________________________

IMPORTANT NEW RESTRICTION:
--------------------------
Throughout the run, someone (Physop, Eng Op, and/or Session Leader must
monitor the OH2L ground resistor voltage (see
cmod$models:[engineering.scopes]scope_gf.dat) on every shot. Any significant (
> 300V) signals must be evaluated by gwinn, wolfe, or irby before proceeding.

This OPERATIONAL RESTRICTION is in force for all runs until further notice.



pcs started at 8:05

Loaded from 1001003009
Did a Load/Clean
Load at 5-Oct-2000 08:19:51.00
Open tree SCRATCH_DISK:[ROWAN] -1
Open tree done

Did coldstart . No occurences of err.
rtnode -- data loaded, A matrix responds
rtnode -- data loaded, M matrix responds
rtnode -- data loaded, PID matrix responds
RT_NODE Done
5-OCT-2000 08:24:10.62 doing TCL command TYPE *************** END COLD
START ******************
*************** END COLDSTART ******************


Ready for first plasma shot. Awaiting completion of Engineering Tests
Oct 5 2000 12:24:46:420PMBill Rowan
#37 of 37 OPS
Date: 4-OCT-2000 21:54 Expires: 18-OCT-2000 00:00
From: BAROLO::WOLFE
Subj: Setup and run plan for Thursday, Oct 5

Run Plan for Thurs., Oct 5, 2000

Experiments SL
------------- ----
Engineering tests wolfe/Gwinn
MP#268 ICRF Wukitch/Boivin
PO: Rowan

Plan
--------------------
The run will start with Engineering Tests and these tests will be under the
direction of Wolfe, Dekow, and Gwinn. Once tests are completed, plasma operation
will proceed with a continuation of the evaluation of the J-port four-strap
antenna, as begun on Tuesday. In the event that a significant ground current
event is observed, operation may revert to testing, or terminate, as directed
by Gwinn and or Wolfe. Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicate
whether we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with either MP#282A (current ramps), MP#248 (H-mode
performance at high P_rf).

Engineering Setup
------------------

We will presumably need PLC test shots for at least the OH and EF1
supplies (separately), since instrumentation has been modified or disturbed on
all of these since the last run. We may also need to conduct further tests of
the ground fault instrmentation using the hi-pot and ringing supplies.

Once we decide to go to plasma shots:

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec
_______________________________________________________________________

IMPORTANT NEW RESTRICTION:
--------------------------
Throughout the run, someone (Physop, Eng Op, and/or Session Leader must
monitor the OH2L ground resistor voltage (see
cmod$models:[engineering.scopes]scope_gf.dat) on every shot. Any significant (
> 300V) signals must be evaluated by gwinn, wolfe, or irby before proceeding.

This OPERATIONAL RESTRICTION is in force for all runs until further notice.



pcs started at 8:05

Loaded from 1001003009
Did a Load/Clean
Load at 5-Oct-2000 08:19:51.00
Open tree SCRATCH_DISK:[ROWAN] -1
Open tree done

Did coldstart . No occurences of err.
rtnode -- data loaded, A matrix responds
rtnode -- data loaded, M matrix responds
rtnode -- data loaded, PID matrix responds
RT_NODE Done
5-OCT-2000 08:24:10.62 doing TCL command TYPE *************** END COLD
START ******************
*************** END COLDSTART ******************


Ready for first plasma shot. Awaiting completion of Engineering Tests

Modification to the procedure for monitoring for the ground fault: Monitor
the ground fault current OH2_L GF. Anything over an amp should be
evaluated by Gwinn, Wolfe, or Irby.

001-006 were the test shots
Oct 5 2000 12:58:34:187PM1001005007Bill Rowan007. Fizzle
3 amps on OH2_L GF at 0.0197 s to 0.021 s
Pressure seems low at approx 0.047 mT

Next shot: Increase prefill by 2 ms
This brings the prefill to 24 ms
Oct 5 2000 04:33:52:403PM1001005011Bill Rowan?0

Engineering Operator Comments
ShotTimeTypeStatusComment
109:37:11:763AMTestOkEF1L and U Test
209:56:19:700AMTestOkEF1L and U Test
310:27:09:607AMTestBadEF3 Test- Supply did not turn off
411:58:02:403AMTestOkEF3 NO Power Test for Invert/Fizzle signal test
512:05:44:280PMTestOkEF3 Power Test
612:12:43:327PMTestOkOH Test
712:28:13:483PMTestBadGF current on OH2L Pearson
803:18:09:653PMTestOkOH2L cap bank dump test only.
903:30:14:937PMTestOkOH Commutation Test
1003:41:33:390PMTestOkOH Hybrid Test
1104:10:10:200PMTestBadOH2U GF Fuse Blown