Alcator C-Mod Run 1001006 Information

Back to runs

Miniproposals
Miniproposal:268
Date Filed: 4/7/2000
Title:Conditioning of D-, E-, or J-Port ICRF Antenna
First Author:Gerd Schilling
Session Leader:Rejean Boivin (shots 1-19)
Session Leader:Steve Wukitch (shots 1-19)

Operators
Session leader(s):Rejean Boivin,Steve Wukitch
Physics operator(s):Steve Wolfe
Engineering operator(s):Bill Byford,Bill Parkin,Gary Dekow

Engineering Operator Run Comment
MP268 and MP248 SL:Wukitch/Greenwald PO:Wolfe EO:Dekow/Cochran

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:25:040PM
Author: To Be Determined
MP#268 ICRF development (J 4-strap)
SL: Wukitch,Boivin
PO: Wolfe
EO: Dekow,Byford,Parkin

Plan
----
Now that the ground problem has been isolated to the commutation capacitor
bank, we will proceed with plasma operations, in parallel with further
testing to identify and replace the bad capacitor(s). The cap banks will
be put back in their original systems, so that the bad bank is on OH2L,
which has a 150 Ohm resistor in series with the ground fuse. Additionally,
the cap cases will be lifted off ground, and regrounded through an instrumented
line, in groups, so that the one carrying ground current can be determined.
In this configuration, it should be possible to operate the machine
"normally". Getting the cap bank set up may take some time in the morning,
so the run may start late. It will probably be necessary to run some
commutation tests before first plasma to verify the system.

Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicate
whether we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with MP#248 (H-mode performance at high P_rf).

Engineering Setup
------------------

Overnight ECDC in D2, stopping 2 hours before the run.

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec
----------------------------------------------------------------------------

001
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec

plasma - upper null, good comparison shot
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec one fault on #3

next shot: 2 MW pulses from J and D+E

002
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 1.6 MW before #3 screen xbarred
antenna then ran as a monopole and injected junk which killed the plasma
good power ramp on J-port

003
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 0.8 MW #3 was faulted by false fault indication

antenna ran as a monopole and injected junk which killed the plasma
remove attempted combined fault indicator for J-port

004 no power
005
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #4 faulted and #3 screen xbarred

006
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #3 & #4 faulted and #3 screen xbarred

007 fizzle

008
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, H-mode with D and E @2 MW
D-port 1 MW 1.1-1.45 sec
E-port 1 MW 1.1-1.45 sec
J-port 2 MW 0.6-1.0 sec need to retune

next shot: inner wall limited

009
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 2.5 MW 0.6-1. sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port MW 0.6-1.0 sec #3 screen xbarred on fault early

gap was 2 cm good for loading check as function of gap
010
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 2.5 MW 0.6-1. sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 1ishMW 4 alone, lots of junk
0.6-1.0 sec #3 screen xbarred on fault early

gap was 1 cm good for loading check as function of gap

011
D, 1 trip, DC0, good tune
E, 3 trips, DC0 , good tune
J3 screen crowbar after ~150 msec
J4 5 trips, all DC0

next shot
slowed down the ramp,
increased filtering on crowbar circuit (#3)

012 early disruption after J went monopole
J3 screen crowbar after ~150 msec
J4 ran until disruption

next shot
increased filtering on crowbar circuit (#3)

013
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 1.8 MW 0.6-0.84sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port J4 0.85MW 0.6-0.905 (1 trip-monopole)
0.6-0.84sec #3 screen xbarred at trip


next shot replace screen crowbar circuit by 480T5E
4800V, 5A fuse (150 msec at 20 amps)

014
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port 1.7 MW 0.6-1.0sec

plasma - inner wall limited, early disruption
D-port 0.9 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port J4 0.6MW max trips
0.9MW #3 max trips

fuse on XMTR 3 worked, removed the spurious screen crowbar firing
however, screen current spikes visible!

015
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port 1.7 MW 0.6-1.0sec

plasma - inner wall limited, early disruption
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port J4 0.5 MW max trips (max trip, too much cross-talk)
0.9MW #3 1 trip (but went monopole)

next shot go to lower null, use tune from upper null this
morning (shot 008)

016
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port 1.7 MW 0.6-1.0sec

plasma - inner wall limited, early disruption
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port
J4 0.8 MW went through, even short H modes
J3 0.9MW 6 trips, but got most of the power through

next shot, reduce gap a little and retune all 4 XMTRs

017
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port 1.7 MW 0.6-1.0sec

plasma - inner wall limited, early disruption
D-port 1.0 MW 1.1-1.45 sec
E-port 1.0 MW 1.1-1.45 sec
J-port
J4 0.8 MW went through, 2 H-modes
J3 0.6MW went through

next shot, overlap all 4 for ~300 msec, raise J a bit in power
little tune on all 4.

018
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.0 MW 0.8-1.45 sec
E-port 1.0 MW 0.8-1.45 sec
J-port 1.7 MW 0.6-1.0sec

plasma - inner wall limited, early disruption
D-port 1.0 MW 0.8-1.45 sec
E-port 1.0 MW 0.8-1.45 sec
J-port
J4 0.8 MW went through, H-modes 9 trips
J3 1.0 MW went through 6 trips

stub tuner appeared to have skipped getting ready for this shot.

next shot, overlap all 4 for ~500msec, raise D and E in power
Do a manual change for stub tuner on 3

019
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.3 MW 0.8-1.45 sec
E-port 1.4 MW 0.8-1.45 sec
J-port 1.7 MW 0.6-1.3sec

plasma - inner wall limited, early disruption
D-port 1.5 MW 0.8-1.45 sec 8 trips
E-port 1.4 MW 0.8-1.45 sec screen crowbar (same symptoms?) 4 trips
J-port
J4 1.0 MW, H-modes 10 trips eventually
J3 1.0 MW max trips


Ok shot overall, got in excess of 4MW for 100-200 msec. Best bettween
0.9 and 1.1 sec.

Summary:

In L-mode, we obtained a good comparison discharge (001). The
heating efficiency estimated from the stored plasma energy was ~50%.
Using H89P scaling, the absorbed power to obtain an H=1 is ~90%. We
also obtained some loading data. We obtained one discharge with 2 MW
from J-port. Higher power were not reliable because the antenna or
transmission line was arcing beyond DC2. FMIT#3 screen xbar continued
to fire RF trips. Installing a 480T5E (4800V, 5A) fuse (150 msec at
20 amps) in place of the screen xbar unit allowed us to observe the
screen current spikes associated with antenna arcs. One idea is the
screen xbar response is faster than the arc protection (both have
~5-10 usec response time) and the xbar is firing before the arc
protection removes the RF drive. The screen xbar in #2 will be
instrumented in the same manner to investigate if it suffers from a
similar problem. The consistent antenna faulting suggests that J-port
requires more voltage and power conditioning before it becomes
reliable. It is clear from the operation that if one transmitter
faults on J the other needs to fault as well. This will be
instrumented shortly.

Physics Operator Summaries
Entered: Jul 7 2004 04:37:12:223PM
Author: To Be Determined
Physics Operator Summary for Friday, Oct 6, 2000

MP#268 ICRF development (J 4-strap)
SL: Wukitch,Boivin
PO: Wolfe
EO: Dekow,Byford,Parkin

Plan
----
Now that the ground problem has been isolated to the commutation capacitor
bank, we will proceed with plasma operations, in parallel with further
testing to identify and replace the bad capacitor(s). The cap banks will
be put back in their original systems, so that the bad bank is on OH2L,
which has a 150 Ohm resistor in series with the ground fuse. Additionally,
the cap cases will be lifted off ground, and regrounded through an instrumented
line, in groups, so that the one carrying ground current can be determined.
In this configuration, it should be possible to operate the machine
"normally". Getting the cap bank set up may take some time in the morning,
so the run may start late. It will probably be necessary to run some
commutation tests before first plasma to verify the system.

Goals of the ICRF experiment are:

1. Measure loading as a function of power comparing D, E, and J-port. (1 shot)

2. Measure J, D, and E-port heating efficiency up to 1.5 MW each -
L-mode required. (3 shots)

3. In L-mode and diverted plasmas, verify simultaneous operational
capability of D, E, and J-port antennas. (2 shots)

4. Evaluation of maximum reliable power from J-port, and maximum total
power from D, E, and J

5. Assuming total achievable power exceeds 3MW, determination of
H-mode accessibility for upper-null targets; this will indicate
whether we will do reverse the field for next week.

Depending on the results of the ICRF evaluation, and on time remaining,
we will proceed with MP#248 (H-mode performance at high P_rf).

Engineering Setup
------------------

Overnight ECDC in D2, stopping 2 hours before the run.

Power systems as on 1001003009

Gas System Setup:

fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled: ECE, VUV, PCX "beast" at B-port

RF systems:

Complete the checklist and have FMIT#1-4 to run-on by 8:00 am
Use match from 1001003009.
Initial waveforms from 1001003009:
D-port 1.5 MW 1.2-1.45 sec
E-port 1.5 MW 0.6-0.85 sec
J-port 1.5 MW 0.9-1.15 sec


Results:
--------

We accomplished many of the RF goals, including comparison shots and loading
measurements in L-mode. We actually obtained an upper null H-mode at 2MW using
just D&E. J ran clean at 2MW into an L-mode target, and seemed to have quite
comparable heating to D&E when the both transmitters managed to stay on. We
only had a couple of shots to attempt simultaneous operation of all four
transmitters in normal lower null diverted plasmas, and got short periods up
to 4.5MW into EDA H-mode on the last shot. Some more development is needed to
reach the goal of reliable high power operation into H-modes using the
four-strap, but there is light at the end of the tunnel. Obviously, we did not
get as far as starting the high performance experiments.

The ground problem has been identified and the bad capacitor taken out of the
circuit. We will run without replacing this cap for the time being.

Details:
--------

We started right off with plasma operation, continuing from the PCS setup of
1001005011. The OH2L cap bank was instrumented in groups of six. The ground
fault showed up immediately, and was now present for the whole shot after
commutation. The bad capacitor was quickly identified (two shots) as being the
on the end closest to the control room, which Bill Cochran had suspected last
night based on slight oil leakage around one terminal. This capacitor was
taken out of the circuit, and the charging voltage raised to 1600V to compensate.

Jport showed good heating at 1.4MW into an upper null L-mode target on the
first shot. After a disruption on shot 2, the RF group tried to re-work their
fault circuitry to force both J3 and J4 to fault out on a fault to either,
preventing monopole operation which leads to injections and often disruptions.
However, this was not successful. They also replaced a screen crowbar circuit
on J3, but the screen crowbars continued for a series of shots.

Shot #8 went into H-mode (our first upper null H-mode with normal field?) at
2MW from D&E. J also put out 2MW but stayed in L-mode; the balance of J3/J4
was not 1:1 on this shot, so the phase may have been funny, although it did
heat.

Shot#9 we went back to inner wall limited discharges, to try to stay in L-mode
for a high power comparison shot. J3 continued to fault with screen crowbar
trips, with J4 then running by itself and inducing disruptions. This was
finally "fixed" by removing the screen crowbar and replacing it with a fuse
sized to prevent damage to the tube from exceeding the screen dissipation
(D. Gwinn's suggestion).

The two J systems continued to have problems running together in the limiter
configuration, but at shot#16 we moved on to a lower null target, so we would
have some chance at running all antennas together into a normal H-mode
plasma. On shot #17, J3 and J4 ran together successfully into H-mode at
1.4MW. On #18 all four overlapped briefly, but J3 and J4 weren't happy and
faulted out alternately. Shots 16-18 were accidentally run with a CLEARIN
ramping in between 1.0 and 1.5 sec, resulting in shrinkage of both gaps during
the D&E pulses. This was corrected for shot 19. On #19 all four stayed on
together for ~200msec at a total power of 4.5MW in EDA. The heating efficiency
was probably fairly low, with a nominal H-factor of only about 1.5, but we did
get up to 120kJ, Rneut~2e13, Te up to 3keV, betaN=1.2. The H/D ratio by this
shot had come up to over 10%, so there may be some room for improvement on
that score as well. Between shot ECDC was not employed in this run, and
probably should have been.

We had one strange power system problem on shot #12. EF1U stopped following
its command and bounced off its voltage rails several times around .7-.8 sec,
leading to a disruption (although the shot was likely to disrupt anyway due to
a J4 injection). The supply actually resumed following command after 0.8
sec. Cochran adjusted the phase reference voltage variac, which seems to have
been slightly out of position; the problem did not recur.

Scorecard:
----------
Tests 1 (no power cycle only)
Duds 0
Fizzles 1
Plasmas 17
------- --
Shots 19


Session Leader Comments
Oct 6 2000 09:23:48:093AM1001006001Steve Wukitch001
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec

plasma - upper null, good comparison shot
D-port 1.3 MW 1.2-1.45 sec
E-port 1.3 MW 0.6-0.85 sec
J-port 1.3 MW 0.9-1.15 sec one fault on #3

next shot: 2 MW pulses from J and D+E
Oct 6 2000 09:46:42:717AM1001006002Steve Wukitch002
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 1.6 MW before #3 screen xbarred
antenna then ran as a monopole and injected junk which killed the plasma
Oct 6 2000 10:55:22:763AM1001006003Steve Wukitch003
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 0.8 MW #3 was faulted by false fault indication

antenna ran as a monopole and injected junk which killed the plasma
remove attempted combined fault indicator for J-port
Oct 6 2000 12:02:22:077PM1001006005Steve Wukitch005
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #4 faulted and #3 screen xbarred
Oct 6 2000 12:02:40:450PM1001006006Steve Wukitch006
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, early disruption ~0.7 sec
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 2 MW until #3 & #4 faulted and #3 screen xbarred
Oct 6 2000 12:30:48:437PM1001006008Steve Wukitch008
request: Bt~5.2 T, Ip~0.8 MA, upper null
D-port 1. MW 1.1-1.45 sec
E-port 1. MW 1.1-1.45 sec
J-port 2 MW 0.6-1. sec

plasma - upper null, H-mode with D and E @2 MW
D-port 1 MW 1.1-1.45 sec
E-port 1 MW 1.1-1.45 sec
J-port 2 MW 0.6-1.0 sec need to retune

next shot: inner wall limited
Oct 6 2000 12:52:01:670PM1001006009Steve Wukitch009
request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 2.5 MW 0.6-1. sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port MW 0.6-1.0 sec #3 screen xbarred on fault early

gap was 2 cm good for loading check as function of gap
Oct 6 2000 02:14:46:420PM1001006010Steve Wukitch

shot 010

request: Bt~5.2 T, Ip~0.8 MA, inner wall limited
D-port 1.25 MW 1.1-1.45 sec
E-port 1.25 MW 1.1-1.45 sec
J-port 2.5 MW 0.6-1. sec

plasma - inner wall limited, early disruption
D-port 0 MW 1.1-1.45 sec
E-port 0 MW 1.1-1.45 sec
J-port 1ishMW 4 alone, lots of junk
0.6-1.0 sec #3 screen xbarred on fault early

gap was 1 cm good for loading check as function of gap
-

Oct 6 2000 02:01:34:327PM1001006011Steve Wukitch

shot 011
D, 1 trip, DC0, good tune
E, 3 trips, DC0 , good tune
J3 screen crowbar after ~150 msec
J4 5 trips, all DC0


next shot
slowed down the ramp,
increased filtering on crowbar circuit (#3)

Physics Operator Comments
Oct 6 2000 07:08:23:060AMSteve WolfeColdstart at 7:06.
all matrices respond, no errors.
Oct 6 2000 09:18:54:200AM1001006001Steve Wolfeshot#1: Continuing from last shot yesterday, 1001005011
Note that seg 3 is active segment, upper null plasma
The startup from this one was shaky, I think Br was too negative, but
today is a new day anyway, so leave it and see what happens.

plasma, full length.
3 heating pulses, injection at start of 3rd (D) at 1.24sec.
trip on J after 1sec, recovers. Heating looks good on all at
1.3-1.4MW.

The gf now occurs at t=0 to 12.7msec, +15Amps on OH2L gf
0-50msec on "bank closest to control room", -15A (1.5V)
Voltage on resistor stays up for 100's of msec, the pearsons
are both saturating. It looks like it now has a hard ground
failure.

breakdown is a tad late, and Br is about .5mT negative, but
leave it until it fails.

Oct 6 2000 09:41:14:920AM1001006002Steve Wolfeshot#2: repeat, with higher RF power.
Pearsons have been moved; no cap was found to have a dc short.
Pearson previously labeled "close to alternator" is now on
the prime suspect, the cap closest to the control room.

plasma, disrupts at .71sec, during J-port pulse (order was
switched.) J3 fulted, and J4 kept going, powering 2 straps in-
phase.

The single suspect cap, the one on the end,
shows 15A of ground current. J'accuse!
Engineers will take it out of the circuit.
Oct 6 2000 10:32:58:450AM1001006003Steve Wolfeshot#3: bad cap has been removed, comm bank voltage will be raised
to try to compensate; a spare cap is being prepared.
Shot will be a repeat.

plasma, disrupts at .81, but had an injection earlier.
J3 didn't come on, J4 ran; it looks like the fix didn't
work.

No ground faults.
Oct 6 2000 10:53:45:420AM1001006004Steve Wolfeshot#4:NO power shot; forgot to turn charging suplies back on.
Oct 6 2000 11:06:33:013AM1001006005Steve Wolfeshot#5: repeat of shot#3. J-port fault chain still not set up.
plasma, disrupted at .865, looks like #3.
J3 screen crowbar fault.
Oct 6 2000 11:42:08:890AM1001006006Steve Wolfeshot#6: replace screen crowbar unit on J3, and try it again.
plasma disrupted at 1.0sec, injections start around 0.9.
Again, both J3 and J4 fault at .88, but J4 comes back on.

Oct 6 2000 12:10:33:200PM1001006007Steve Wolfeshot#7: retune J3 and try again. Screen crowbars are apparently "real"
fizzle. probably the disruptions got us, but I may as well do something.

We blew a filament on IGT; now down to two good filaments.
Oct 6 2000 12:23:45:077PM1001006008Steve Wolfeshot#8: Br0 offset from .001 to .0015; Pg4 from 24msec to 22msec
plasma, full length. H-mode at 1.28sec.
Got J3=0.8, J4=1.2MW, L-mode; Dand E at 1 each and gets into H-mode, upper null!
Oct 6 2000 12:46:10:043PM1001006009Steve Wolfeshot#9: Go to an inner limiter discharge, to really keep it in L-mode
Switch to seg2, clearin from .005 -> -.018, rcur from .659->.649,
change TF current to 146600. Also, lower nl4 to 8e19, as in seg3.

plasma disrupted at 0.89 sec, outer gap was 18mm.

next shot: reduce outer gap by 8mm
Oct 6 2000 01:16:32:340PM1001006010Steve Wolfeshot#10: rcur from .649->.653. Reduce pg3 maint level to 10V.
plasma, disrupted at .97; injections start around .8.
Gap around 10mm.

J3 faulted again. They think the stub tuner isn't really moving
when they try to tune it.
Oct 6 2000 01:53:17:547PM1001006011Steve Wolfeshot#11: repeat.
plasma, full length but saw an injection.
J3 still getting screen crowbars. D&E put in some gas
at 2.5MW, but they heat

Oct 6 2000 02:05:12:640PM1001006012Steve Wolfeshot#12: repeat,
plasma, disrupts at .76. Same thing.
EF1U hits a voltage rail at .73sec, looks like
it isn't following its hybrid command
Oct 6 2000 02:35:27:170PM1001006013Steve Wolfeshot#13: Cochran adjusted a variac on the EF1U supply.
plasma disrupts at .89sec
j3 faulted again. EF1U looks ok.
Oct 6 2000 02:57:20:327PM1001006014Steve Wolfeshot#14: J3 has had major surgery on the screen crowbar unit.
plasma, full length. Injection at 1sec, both J3 and J4 faulting,
this time J3 stays on longer. D drops to half power and continues.

Oct 6 2000 03:23:07:763PM1001006015Steve Wolfeshot#15: Repeat.
plasma, full length, no injection
j4 faulted early, j3 stays on. D&E at 1MW each.
Oct 6 2000 03:48:57:623PM1001006016Steve Wolfeshot#16: Go to a lower null.
crashed pcs, have to restart
copy shot 8, change to seg 2, copy tf and pg3 voltage traces,
drop the density to 8e19.

plasma, full length, eda h-mode with D&E, J3 faults and recovers,
J4 runs at .8MW. outer gap is ~12.5mm

next shot: reduce gap to 10mm
Oct 6 2000 03:50:11:107PM1001006016Steve Wolfeshot#16: Go to a lower null.
crashed pcs, have to restart
copy shot 8, change to seg 2, copy tf and pg3 voltage traces,
drop the density to 8e19.

plasma, full length, eda h-mode with D&E, J3 faults and recovers,
J4 runs at .8MW. outer gap is ~12.5mm

next shot: reduce gap to 9-10mm
Oct 6 2000 04:12:24:937PM1001006017Steve Wolfeshot#17: reduce gap to 9-10mm (rcur->.661)
Before the shot EF1L type 1 fault, conduction failure.
Reset and reclosed the breaker while in INIT,

plasma, full length, H-modes. No RF faults.
2 h-modes with J, one with D&E, better heating from D,E but they had more power.

next shot: overlap them
Oct 6 2000 04:41:23:340PM1001006018Steve Wolfeshot#18: Try to overlap J with D&E.
plasma full length, lots of h-modes.
Short four-way overlap, but J3 and J4 are alternating faults.
outer gap is shrinking toward the end of the shot.
There was a CLEARIN point at -.005 at 1.5sec, should have been
+.005.

next shot: Fix the CLEARIN program
Oct 6 2000 05:08:47:140PM1001006019Steve Wolfeshot#19: correct CLEARIN program from 1.0 to 1.5. Rf is retuning.
plasma full length, but some injections.
Neuts to 1.5e13, looks like some good overlap. 120kJ
4.5MW, for nearly 200msec EDA. J4 faulting more than J3,
D&E faulting some too.

Engineering Operator Comments
ShotTimeTypeStatusComment
109:02:49:090AMPlasmaOk
209:33:27:123AMPlasmaOk
310:27:41:700AMPlasmaOk
410:52:29:500AMPlasmaBadNo Power - Spellmans not powered up
511:03:14:170AMPlasmaOk
611:35:11:843AMPlasmaOk
711:56:06:000AMPlasmaOk
812:15:57:937PMPlasmaOk
912:39:31:700PMPlasmaOk
1001:06:22:560PMPlasmaOk
1101:31:10:530PMPlasmaOk
1201:54:43:857PMPlasmaBadEF1U not following Hybrid Command
1302:27:50:700PMPlasmaOk
1402:51:35:047PMPlasmaOk
1503:19:02:890PMPlasmaOk
1603:43:25:733PMPlasmaOk
1704:07:57:967PMPlasmaOk
1804:33:30:730PMPlasmaOk
1904:58:55:843PMPlasmaOk