Alcator C-Mod Run 1001201 Information

Back to runs

Miniproposals
Miniproposal:268
Date Filed: 4/7/2000
Title:Conditioning of D-, E-, or J-Port ICRF Antenna
First Author:Gerd Schilling
Session Leader:Rejean Boivin (shots 1-16)

Operators
Session leader(s):Rejean Boivin
Physics operator(s):Steve Wolfe,Ian Hutchinson
Engineering operator(s):Gary Dekow,Bill Parkin,Bill Cochran

Engineering Operator Run Comment
Engineering Tests/MP268 SL:Boivin PO:Wolfe,Hutch EO:Cochran,Dekow,Parkin

Session Leader Plans

Physics Operators Plans

Session Leader Summaries

Physics Operator Summaries
Entered: Jul 7 2004 04:37:12:740PM
Author: To Be Determined
Physop Summary 1001201

Restart with Normal Field Direction

First 15 shots were power supply and coil connection tests.
Shot 16 plasma, under nl_zmeter control. Looks fine.
Shut down to work on the RF.

Session Leader Comments

Physics Operator Comments
Nov 30 2000 02:05:44:810PMSteve WolfeSetting up for tomorrow's run.
Load from 1001020005; acknowledge CONFIG warning- no action required.
Reduce current from 1.1MA to 0.8MA (seg2)
reduce IC_ef4u from 3000 to 2000 (seg2).
refuce tf from -153000 to -150000
LOAD/CLEAN into model

Should be all set; do a save_as cmod$test_shots:[hybrid.pcs] 1001201000 as well, just to be safe.
Dec 1 2000 07:44:13:077AMSteve WolfeBring up PCS and confirm model is as loaded yesterday
Modify seg 2 title, set pg4 pulse in seg1 to 20msec
Load/clean
coldstart at 07:43 - all matrices respond
Dec 1 2000 07:50:23:090AMSteve WolfeRun Plan for Friday, Dec 1, 2000

Engineering tests
Plasma Startup
MP#268 ICRF
SL: Boivin
PO: Wolfe,Hutch

Engineering Setup
------------------

Conditioning: overnight ECDC in D2, ending 2 hours before start of run

RF Setup:
---------
MTR 1 and 2 should be made ready, but NOT in run-on.

XMTR 4 should be warmed up and in run-on by approx 7:30.

If XMTR 3 is fully assembled, warm up transmitter
in local mode and going to dummy load.

Steps remaining:

XMTR 3, tune to 78 MHz (local mode, dummy load)
pulse in dummy load, computer control, higher power/longer pulse
vacuum tune, and fire into vacuum, check phase and instrumentation
couple to plasma, together with #4


For Engineering tests:
----------------------
Gas setup:
fill B-top with 6 psi of D2 Hybrid **ENABLED**
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid DISABLED
leave J-bot as is


The following gate valves should be enabled: DNB

For Plasma Startup and MP268:
-----------------------------
Power systems as on 1001020005
Note: EF4 current limit should be [-10,+4]ka
EFC start time should be -.035sec

Gas system:
fill B-top with 6 psi of D2 Hybrid ENABLED
fill B-side lower with 1 psi of Ar Hybrid DISABLED
fill B-side upper with 35 psi of D2 Hybrid DISABLED, for ECDC
fill C-side with 30 psi of D2 Hybrid ENABLED
leave J-bot as is


Gate valves: ECE, VUV, Beast,
DNB (if requested)

Plan
--------------------

We will start with standard post-bus reversal engineering PLC tests of each coil
system. During these tests, the DNB will be opening and firing into the
machine, and the pulse gas system should be under Hybrid control, as
indicated.

Once engineering tests are complete, we will move on to plasma startup shots
with normal field direction. PCS will be loaded from 1001020005, but with
current reduced to 0.8MA. DNB can continue to pulse if they want, assuming they
aren't perturning the breakdown pressure too much.

Assuming we get that far, the RF shots will be tests of J-port performance as
a four-strap. The target shot will be based on 1001020005 but with reduced
current. When we ran in October, we were having problems with the upper corners
of the antenna lighting up and generating injections. After verifying that the
transmitters are working and the control/fault circuits are functional, the
first thing to see is if this phenomenon reappears as the power is increased.

Fire J-port into plasma, nominal density, preferably lower current (0.8 MA) to
start with. Shot 100102005 is taken as the starting point, except for
current. Short pulse, check phase.

Increase power gradually.

When approx max power achieved, reduce power and increase pulse length.
At higher power we may want to go to upper null to stay in L-mode.

Also: Exercise D and E to make sure all is normal. Have those available for
further testing as needed.

We will continue on that plan on monday, if things are progressing reasonably.


Dec 1 2000 08:55:07:983AM1001201001Steve Wolfeshot#1: Data cyce test only
b-top enabled. DNB will fire with gate valve closed.
got .053mTorr - ok.

Dec 1 2000 10:16:59:793AM1001201001Steve WolfeBefore shot#2: Long delay to swap out the PF breaker.
Dec 1 2000 10:51:56:187AM1001201002Steve Wolfeshot#2: oh2u test. Looks ok.
Dec 1 2000 02:04:20:043PM1001201016Ian HutchinsonRestart with Normal Field Direction

Shots prior to 16 are all engineering tests of the different coils to
ensure that the bus reconnection is correct.

The interferometer was playing up. Got wire 14 from 1000913014 nl_zmeter into
segment 2 wire 14. Load.

Plasma. Good shot with fairly low density.

Shut down the run to work on the RF.

Engineering Operator Comments
ShotTimeTypeStatusComment
108:50:56:357AMTestOk
210:49:09:937AMTestOkOH2U Froward Bridge Test
310:59:39:607AMTestOkOH2L Polarity Test
411:10:37:123AMTestOkOH1 Polarity Check
511:24:41:810AMTestOkEF1U Polarity Test
611:34:26:263AMTestOkEF1L Polarity Test
711:46:08:077AMTestOkEF4 Polarity Test
811:56:57:547AMTestOkEF2U Polarity Test
912:07:05:827PMTestOkEF2L Polarity Test
1012:17:03:623PMTestOkEFC Polarity Test
1112:26:10:247PMTestBadEF3 test but not enabled
1212:35:45:797PMTestOkEF3 Polarity Test
1312:45:50:373PMTestOkTF 50 KA Test
1412:58:55:077PMTestOkTF 100KA Test
1501:11:19:890PMTestOkTF 150 KA Test
1601:55:08:983PMPlasmaOk