Alcator C-Mod Run 1010515 Information

Back to runs

Miniproposals
Miniproposal:
Date Filed:
Title:
First Author:
Session Leader:Bill Rowan (shots 1-34)
Session Leader:Jim Irby (shots 1-34)

Operators
Session leader(s):Bill Rowan,Jim Irby
Physics operator(s):Robert Granetz
Engineering operator(s):Bill Cochran,Gary Dekow

Engineering Operator Run Comment
Begin with Power System Tests then move on to DNB/MSE Testing with TF.

Session Leader Plans

Physics Operators Plans

Session Leader Summaries

Physics Operator Summaries
Entered: Jul 7 2004 04:37:12:973PM
Author: To Be Determined
Physics operator summary for run 1010515 (Tuesday):

MP # ?? Power tests, DNB tests
MP #259 MSE calibration

Session leader: J. Irby, W. Rowan
Physics operator: R. Granetz
Engineer: G. Dekow/B. Cochran

Summary: This was the first day of tokamak operation after a 4.5 month
shutdown. Not surprisingly, there were a host of minor, but
annoying problems with various faults, the TF scanner, etcetera.
Gary Dekow, Bill Cochran, and Dave Terry managed to solve all the
problems during the day, and with an extra half-hour of running,
we even managed to get a plasma (albeit short and dirty) on our
first attempt. Ned Eisner ran the DNB between shots initially,
but by the latter part of the day, he got it firing into the
machine during the shot cycle, with a beam voltage of up to 41 kV
and a current of 3.1 amps. Several new beam diagnostics were
brought online. Matt Sampsell got H-alpha, H-beta, and H-gamma
spectra of the beam, so we can figure out the energy component
mix, and also get information on quantum excitation in the beam.
Because of all the shakedown problems, we didn't get to the MSE
calibration today, but Howard Yuh was able to see some signal
above the background even at these reduced parameters and low fill
pressures. Hopefully we'll get to do the MSE calibration
tomorrow. From the one plasma shot, it is very clear that we need
to do a lot of plasma discharge cleaning.

Scorecard: 1 plasmas
0 fizzles
0 duds
33 tests
0 aborted and/or screwed up by computer problems
----------
34 total

-------------------------------------------------------------------------------
Engineering setup:

ECDC in D2 overnight.

Gas setup:
fill B-top with 6 psi of D2 Hybrid DISABLED (PG4)
fill B-side lower with 1 psi of Ar Hybrid DISABLED (PG1)
fill B-side upper with nothing Hybrid DISABLED (PG2)
fill C-side with 30 psi of H2 Hybrid DISABLED (PG3)
fill J-bottom with nothing Hybrid DISABLED (PG5)

Enable the following gate valves: none. (DNB will be enabled at some point.)

Run starts at 09:00 and ends at 17:00.

-------------------------------------------------------------------------------
RF Setup:

No RF power is required today.

-------------------------------------------------------------------------------
Run Plan:

Cycle tests, individual power supply tests, possible EF2 60 Hz test,
and TF tests.

During these tests, we will try to operate the DNB into the torus, with a
pre-fill of D2, to check out the beam itself, several new beam duct
monitors (H-alpha diodes, pressure gauges), and associated DNB
spectroscopic diagnostics. We would like to look at the shifted H-alpha
components to get the energy components, as well as H-beta and H-gamma to
get some information on excited states.

Once the power supply tests are completed, we will start on the MSE
calibration, which involves firing the DNB into a TF-only field and
measuring the MSE angle. If time permits, try TF + varying amounts of
EF4 to vary the field angle a known amount.

-------------------------------------------------------------------------------

Overnight ECDC in D2

Hybrid coldstart done; no errors found

-------------------------------------------------------------------------------

Shot 01 -- Test of shot cycle. OK.

There will be a delay here to manually charge and test the cap banks.

Shot 02 -- Test; no power. Bus Rogowski data came through.

Shot 03 -- Test of commutation cap banks. No power.

Shot 04 -- Test, no power.

Shot 05 -- Test, no power.

Shot 06 -- Test, no power.

Shot 07 -- Test, no power.

Shot 08 -- Test, no power.

Shot 09 -- Test, no power.

Shot 10 -- Test, no power.

Shot 11 -- Test, no power. Done with capacitor bank testing.

There will be a delay before Shot 12 to fix a problem with OH2L.

Shot 12 -- Test, TF only, 50 kA, PLC. 20 ms pre-fill puff of D2 is enabled.
Good. Magnetics looks good. Got gas puff.

Next shot: enable DNB gate valve. Turn on EDGE tree in order to
get F-side ratiomatic pressure.

Shot 13 -- Test, TF only, 100 kA, PLC. Looks good. Bus signals weren't
recorded because of the MDS/DAQ timing, but magnetics confirms that
Btor=3.4 T. DNB gate valve opened. DNB ionization gauge measures
5e-6 torr. F-side ratiomatic reads 6e-5 torr.

Next shot: 150 kA TF test. Turn on SPECTROSCOPY tree.

Shot 14 -- Test. No power cycle due to a problem with a thermocouple reading.

Next shot: 150 kA TF test. Turn on SPECTROSCOPY tree.

Problem with TF scanner. Cancel TF test.

Shot 15 -- Test, EF3, 2 kA, PLC. Looks good. All flux loops and necessary
Bp coils look good. DNB gas pufffed. It doubles the pressure to
0.15 mTorr.

Next shot: EF2U

Shot 16 -- Test, EF2U, 2 kA, PLC. Looks good. DNB gas puffed, got arc
current, but no HV.

Next shot: EF2L

Shot 17 -- Test, EF2L, 2 kA, PLC. Large 60 Hz component on EF2L output.
DNB had gas and arc, but still no HV.

Next shot: EFC test

Shot 18 -- Test, EFC. OK. DNB still can't get the HV to fire. It's not due
to a spurious alarm on the dump magnet.

Next shot: TF only at 150 kA

Shot 19 -- Test, TF, 150 kA, PLC. OK. DNB gas and arc fired, no HV.

Next shot: EF1U

Shot 20 -- Test, EF1U, -2 kA, PLC. OK. Problem with engineering CAMAC?

Next shot: EF1U, opposite polarity.

Shot 21 -- Test, EF1U, +2 kA, PLC. OK. Dave Terry figured out the problem
with the DNB HV...it's the fizzle detector!! For the next shot,
move the DNB pulse earlier (start at t=0.2 instead of 0.5 s), and
move the fizzle detector to 0.38 s, and delay start of power
supplies by 0.3 s as well (since fizzle detector is being used to
turn off the supplies).

Next shot: EF1L

Shot 22 -- Test, EF1L, -2 kA, PLC. There was current, but it was not in
regulation due to a wrong setting on the switch time. DNB HV supply
fired, but the arc didn't, for some unknown reason.

Next shot: repeat with proper switch time

Shot 23 -- Test, EF1L, +2 kA, PLC. OK. DNB fired, 31 kV, about 2 amps!

Next shot: OH1

Shot 24 -- Test, OH1, -10 kA, PLC. OK. Coax resistance = 0.12 uohms.

Next shot: OH1, opposite polarity

Shot 25 -- Test, OH1, +10 kA, PLC. OK. Beam fired again, ~31 kV, 1.9 amps.

Next shot: OH2U

Shot 26 -- Test, OH2U, -10 kA, PLC. OK. Beam fired again, same parameters.

Next shot: OH2U, opposite polarity

Shot 27 -- Test, OH2U, +10 kA, PLC. OK. Beam fired again, 36 kV, 1.9 amps.

Next shot: OH2L

Shot 28 -- Test, OH2L, -10 kA, PLC. OK. Coax resistance = 0.14 uohms.
Beam fired, 36 kV, 2.4 amps. Pressure=0.10-0.15 mTorr.
Howard sees unmistakeable signals above the noise level, even at
these parameters!!

Next shot: OH2L, opposite polarity

Shot 29 -- Test, OH2L, +10 kA, PLC. OK. No beam.

Next shot: EF4

Shot 30 -- Test, EF4s, -1 kA each, PLC. OK. Beam on. Matt Sampsell has been
getting H-alpha, H-beta, H-gamma spectra, so we'll have some info
on energy components and excitation.

Next shot: EF4, opposite polarity.

Shot 31 -- Test, EF4s, +1 kA each, PLC. OK. Beam on, 41 kV, 3.1 amps.

Next shot: commutation test of the OH's. Move DNB to t=0.7 s (from
t=0.2 s, in order to leave prefill pressure unaffected at t=0, for
possible plasma shot later today and/or tomorrow).

Shot 32 -- Test, commutation of OH1, OH2U, OH2L. OK. Beam is disabled by
the fizzle detector (as planned), which is now set at the normal
time.

Next shot: EF1 commutations

Shot 33 -- Test, commutation of EF1U, EF1L. OK.

Next shot: try for plasma. Enable ECE gate valve (along with DNB).
Turn on all trees except RF. Enable C-side valve (along with B-top)
Turn control over to HYBRID computer.

Shot 34 -- Plasma! Lasted until t=0.17 s. Plasma current got up to 0.48 MA
before it starting rolling over due to high resistivity. The
fizzle detector prevented the DNB from turning on. Some
spectroscopy and edge data were lost. The main H-alpha signal
and the TCI signals were zero. GPC says 13 keV.

End of run.

Session Leader Comments

Physics Operator Comments
May 15 2001 09:48:40:123AMRobert GranetzEngineering setup:

ECDC in D2 overnight.

Gas setup:
fill B-top with 6 psi of D2 Hybrid DISABLED (PG4)
fill B-side lower with 1 psi of Ar Hybrid DISABLED (PG1)
fill B-side upper with nothing Hybrid DISABLED (PG2)
fill C-side with 30 psi of H2 Hybrid DISABLED (PG3)
fill J-bottom with nothing Hybrid DISABLED (PG5)

Enable the following gate valves: none. (DNB will be enabled at some point.)

Run starts at 09:00 and ends at 17:00.
May 15 2001 09:49:13:377AMRobert GranetzRun Plan:

Cycle tests, individual power supply tests, possible EF2 60 Hz test,
and TF tests.

During these tests, we will try to operate the DNB into the torus, with a
pre-fill of D2, to check out the beam itself, several new beam duct
monitors (H-alpha diodes, pressure gauges), and associated DNB
spectroscopic diagnostics. We would like to look at the shifted H-alpha
components to get the energy components, as well as H-beta and H-gamma to
get some information on excited states.

Once the power supply tests are completed, we will start on the MSE
calibration, which involves firing the DNB into a TF-only field and
measuring the MSE angle. If time permits, try TF + varying amounts of
EF4 to vary the field angle a known amount.
May 15 2001 09:49:27:063AMRobert Granetz Overnight ECDC in D2

Hybrid coldstart done; no errors found
May 15 2001 09:50:03:707AM1010515001Robert GranetzShot 01 -- Test of shot cycle. OK

There will be a delay here to manually charge and test the cap banks.
May 15 2001 10:19:35:187AM1010515002Robert GranetzShot 02 -- Test; no power. Bus Rogowski data came through.
May 15 2001 10:28:53:873AM1010515003Robert GranetzShot 03 -- Test of commutation cap banks. No power.
May 15 2001 10:46:33:353AM1010515004Robert GranetzShot 04 -- Test, no power.
May 15 2001 10:46:41:840AM1010515005Robert GranetzShot 05 -- Test, no power.
May 15 2001 11:17:20:917AM1010515011Robert GranetzShot 11 -- Test, no power. Done with capacitor bank testing.
May 15 2001 11:32:42:423AM1010515011Robert GranetzThere will be a delay before Shot 12 to fix a problem with OH2L.
May 15 2001 12:16:30:557PM1010515012Robert GranetzShot 12 -- Test, TF only, 50 kA, PLC. 20 ms pre-fill puff of D2 is enabled.
Good. Magnetics looks good. Got gas puff.

Next shot: enable DNB gate valve. Turn on EDGE tree in order to
get F-side ratiomatic pressure.
May 15 2001 12:44:23:800PM1010515013Robert GranetzShot 13 -- Test, TF only, 100 kA, PLC. Looks good. Bus signals weren't
recorded because of the MDS/DAQ timing, but magnetics confirms that
Btor=3.4 T. DNB gate valve opened. DNB ionization gauge measures
5e-6 torr. F-side ratiomatic reads 6e-5 torr.

Next shot: 150 kA TF test. Turn on SPECTROSCOPY tree.
May 15 2001 12:48:35:167PM1010515014Robert GranetzShot 14 -- Test. No power cycle due to a problem with a thermocouple reading.

Next shot: 150 kA TF test. Turn on SPECTROSCOPY tree.
May 15 2001 01:24:34:393PM1010515015Robert GranetzProblem with TF scanner. Cancel TF test.
May 15 2001 01:29:35:073PM1010515015Robert GranetzShot 15 -- Test, EF3, 2 kA, PLC. Looks good. All flux loops and necessary
Bp coils look good. DNB gas pufffed. It doubles the pressure to
0.15 mTorr.

Next shot: EF2U
May 15 2001 01:40:32:980PM1010515016Robert GranetzShot 16 -- Test, EF2U, 2 kA, PLC. Looks good. DNB gas puffed, got arc
current, but no HV.

Next shot: EF2L
May 15 2001 02:33:28:470PM1010515017Robert GranetzShot 17 -- Test, EF2L, 2 kA, PLC. Large 60 Hz component on EF2L output.
DNB had gas and arc, but still no HV.

Next shot: EFC test
May 15 2001 02:40:02:413PM1010515018Robert GranetzShot 18 -- Test, EFC. OK. DNB still can't get the HV to fire. It's not due
to a spurious alarm on the dump magnet.

Next shot: TF only at 150 kA
May 15 2001 02:55:40:470PM1010515019Robert GranetzShot 19 -- Test, TF, 150 kA, PLC. OK. DNB gas and arc fired, no HV.

Next shot: EF1U
May 15 2001 03:19:47:100PM1010515020Robert GranetzShot 20 -- Test, EF1U, -2 kA, PLC. OK. Problem with engineering CAMAC?

Next shot: EF1U, opposite polarity
May 15 2001 03:19:59:757PM1010515021Robert GranetzShot 21 -- Test, EF1U, +2 kA, PLC. OK. Dave Terry figured out the problem
with the DNB HV...it's the fizzle detector!! For the next shot,
move the DNB pulse earlier (start at t=0.2 instead of 0.5 s), and
move the fizzle detector to 0.38 s, and delay start of power
supplies by 0.3 s as well (since fizzle detector is being used to
turn off the supplies).

Next shot: EF1L
May 15 2001 03:35:56:597PM1010515022Robert GranetzShot 22 -- Test, EF1L, -2 kA, PLC. There was current, but it was not in
regulation due to a wrong setting on the switch time. DNB HV supply
fired, but the arc didn't, for some unknown reason.

Next shot: repeat with proper switch time
May 15 2001 03:47:41:677PM1010515023Robert GranetzShot 23 -- Test, EF1L, +2 kA, PLC. OK. DNB fired, 31 kV, about 2 amps!

Next shot: OH1
May 15 2001 03:53:45:653PM1010515024Robert GranetzShot 24 -- Test, OH1, -10 kA, PLC. OK. Coax resistance = 0.12 uohms.

Next shot: OH1, opposite polarity
May 15 2001 04:03:15:137PM1010515025Robert GranetzShot 25 -- Test, OH1, +10 kA, PLC. OK. Beam fired again, ~31 kV, 1.9 amps.

Next shot: OH2U
May 15 2001 04:09:40:740PM1010515026Robert GranetzShot 26 -- Test, OH2U, -10 kA, PLC. OK. Beam fired again, same parameters.

Next shot: OH2U, opposite polarity
May 15 2001 04:23:47:467PM1010515027Robert GranetzShot 27 -- Test, OH2U, +10 kA, PLC. OK. Beam fired again, 36 kV, 2.4 amps.

Next shot: OH2L
May 15 2001 04:29:57:680PM1010515028Robert GranetzShot 28 -- Test, OH2L, -10 kA, PLC. OK. Coax resistance = 0.14 uohms.
Beam fired, 36 kV, 2.4 amps. Pressure=0.10-0.15 mTorr.
Howard sees unmistakeable signals above the noise level, even at
these parameters!!

Next shot: OH2L, opposite polarity
May 15 2001 04:39:35:850PM1010515029Robert GranetzShot 29 -- Test, OH2L, +10 kA, PLC. OK. No beam.

Next shot: EF4
May 15 2001 04:48:56:847PM1010515030Robert GranetzShot 30 -- Test, EF4s, -1 kA each, PLC. OK. Beam on. Matt Sampsell has been
getting H-alpha, H-beta, H-gamma spectra, so we'll have some info
on energy components and excitation.

Next shot: EF4, opposite polarity.
May 15 2001 04:57:52:067PM1010515031Robert GranetzShot 31 -- Test, EF4s, +1 kA each, PLC. OK. Beam on, 41 kV, 3.1 amps.

Next shot: commutation test of the OH's. Move DNB to t=0.7 s (from
t=0.2 s, in order to leave prefill pressure unaffected at t=0, for
possible plasma shot later today and/or tomorrow).
May 15 2001 05:12:11:760PM1010515032Robert GranetzShot 32 -- Test, commutation of OH1, OH2U, OH2L. OK. Beam is disabled by
the fizzle detector (as planned), which is now set at the normal
time.

Next shot: EF1 commutations
May 15 2001 05:26:54:453PM1010515033Robert GranetzShot 33 -- Test, commutation of EF1U, EF1L. OK.

Next shot: try for plasma. Enable ECE gate valve (along with DNB).
Turn on all trees except RF. Enable C-side valve (along with B-top)
Turn control over to HYBRID computer.
May 15 2001 05:41:27:000PM1010515034Robert GranetzShot 34 -- Plasma! Lasted until t=0.17 s. Plasma current got up to 0.48 MA
before it starting rolling over due to high resistivity. The
fizzle detector prevented the DNB from turning on. Some
spectroscopy and edge data were lost. The main H-alpha signal
and the TCI signals were zero. GPC says 13 keV.

Engineering Operator Comments
ShotTimeTypeStatusComment
108:49:43:223AMTestOk
210:16:31:200AMTestOk
310:26:56:403AMTestOk
410:35:56:430AMTestOk
510:43:17:270AMTestOk
610:50:33:017AMTestOk
710:54:39:583AMTestOk
810:58:18:293AMTestOk
911:01:43:610AMTestOk
1011:05:35:913AMTestOk
1111:09:58:157AMTestOk
1212:09:39:747PMTestOkTF test at 50Kamps
1312:21:15:280PMTestOk
1412:44:25:927PMTestBadNo Power
1501:23:14:423PMTestOkEF3 Test, 1000V, 2Kamps
1601:34:30:737PMTestOkEF2U Test, 300V, 2Kamps
1701:45:33:427PMTestOk
1802:32:46:733PMTestOkEFC Test, 400V, 1Kamps
1902:42:00:683PMTestOkTF Test 150Kamps
2002:57:09:723PMTestOkEF1U Forward, 500V, 2Kamps
2103:06:39:520PMTestOkEF1U Reverse -500, 2Kamps
2203:21:16:743PMTestOk
2303:37:43:580PMTestOkEF1L Reverse Test -500, 2Kamps
2403:46:17:190PMTestOkOH1 Forward Test 1000V, 10Kamps
2503:55:34:830PMTestOkOH1 Reverse Test -1000V, 10Kamps0
2604:03:53:187PMTestOkOH2U Forward Test 300V, 10Kamps
2704:12:53:887PMTestOkOH2U Reverse Test -300V, 10Kamps
2804:21:20:100PMTestOkOH2L Forward Test 300V, 10Kamps
2904:30:10:257PMTestOkOHL Reverse Test -300V, 10Kamps
3004:38:55:567PMTestOkEF4 Forward Test 1000V, 2Kamps
3104:47:14:720PMTestOkEF4 Reverse Test -1000V, 2Kamps
3204:59:01:643PMTestOkOH1, OH2U, OH2L Commutation Test
3305:12:57:680PMTestOkEF1 Commutation Test
3405:26:45:313PMPlasmaOkFull System Shot