Alcator C-Mod Run 1030716 Information

Back to runs

Miniproposals
Miniproposal:345
Date Filed: 6/20/2003
Title:Initial Mode Conversion Current Drive Experiments
First Author:Steve Wukitch
Session Leader:Steve Wukitch (shots 1-21)

Operators
Session leader(s):Steve Wukitch
Physics operator(s):Steve Wolfe
Engineering operator(s):Bill Cochran,Bill Byford,Bill Parkin,Gary Dekow

Engineering Operator Run Comment
Purpose: MP #345 MCCD/Wukitch/Wolfe/Cochran/Dekow

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:01:587PM
Author: Steve Wukitch
Engineering setup and run plan for Wednesday, July 16, 2003

MP#345 MCCD
SL: Wukitch
PO: wolfe

This run requires 8T operation. All required bus work inspections/re-torques
should be performed prior to the run. Bus temperatures need to be monitored
between shots.

Engineering Setup:

overnight ECDC in D2, stopping 1-2 hours prior to the run.

Power system as on 1010803010 Except:
TF PLC current limit at 175kA (we'll change this as the run proceeds)
digitizer start at -1.6sec
Acoils as on 1030711040 (+Dtop -Dbot -Jtop +Jbot) and enabled

Gas setup - fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid enabled
fill B-side upper with 15 psi of He3 Hybrid Enabled (as is)
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled, assuming no vacuum problems:
ECE, VUV, DNB, PCI, Zbolo-shutter

RF setup: in RUN ON by 8:00AM

----------------------------------------------------
Run Plan:

We will start with a lower single null 800kA discharge as on 1030710010
with target density of nl04=8e19.
Raise TF over 6 shots to 8T as follows:

Nominal BT hybrid current PLC limit
-------- ------------- ----------
5.4 150 175
6 170 175
6.5 185 190
7 200 205
7.5 215 220
8 230 235

Since we will just be verifying proper TF operation during this sequence, we
won't need to repeat shots because of fizzles.

While we're doing that we can try adjusting the He3 puff, starting with an
80msec pulse as on 1010803010 (but note that the plenum pressure was only 6psi for
that run).

Once we're up to 8T, we can scan the He3 puff to optimize the near-axis mode
conversion, then vary RF phasing for co and counter current drive. Assuming
MSE is seeing an effect, we may need to reserve the final 60 to 90 minutes for
calibration shots.
***********************************************************************************

Lost the driver bias on FMIT#2. We suspect a problem with its
transformer and fan. We will investigate later.


001 BT~5.4, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: no gate
J: ran one fault
next field is 6 T

002 BT~6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: ran clean
J: ran clean
next field is 6.5 T

Disconnected the driver bias at the output of the supply and the
supply appears fine.

003 BT~6.5, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.8 [0.7,1.3] sec
result: plasma
D: ran multiple faults
J: ran two faults
next field is 7 T

004 BT~7, Ip~0.8 MA, nl_04~0.8, SNL
D: 0. [0.7,1.3] sec
J: 0. [0.7,1.3] sec
result: plasma
next field is 7.6 T
005 BT~7.6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.2] sec
J: 1.8 [0.7,1.2] sec
result: plasma
D: ran faults
J: ran faults
next field is 8 T

fairly strong response in the e- temperature at ~0.75 m

006 BT~8, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.2] sec
J: 1.8 [0.7,1.2] sec
result: plasma - marfe
D: ran faults
J: ran faults
mode conversion is inside q=1
lower He3 puff from 80 msec to 60 msec

007 BT~8, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 6 faults
J: ran max faults
next field is 8.1 T
008 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran 3 faults
lower target density to 0.6
008 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran 3 faults
next field is 8.0T
009 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 1.2 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran clean
observe two (for 78 and 80.5) mode conversion surfaces
sawtooth inversion radius appears to shrink with electron heating
next phase is -90deg (digital phase shifter is 30deg)

010 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.9 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran 5 trips
sawteeth are modified
011 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran clean
J: ran faults but better towards end of shot
sawteeth are modified with J-port
012 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran clean
sawteeth become shorter with J-port
013 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 3 faults
sawteeth still change with J-port
014 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 2 faults
change gas puff to 30 msec
appears the He3 has creeped upward from Chromex
015 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran 2 faults
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
016 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran clean
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
nice shot
017 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
nice shot
018 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 3 faults
J: ran max faults
mode conversion is at 66 cm
019 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
good comparison to +/-90deg
dithering
020 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.75 [0.6,1.25] sec
J: 2.0 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 4 faults
J: ran 2 faults
mode conversion is at 66 cm
sawteeth period is no different than during D-port
dithering
021 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.75 [0.6,1.25] sec
J: 2.0 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran 3 faults
mode conversion is at 66 cm
sawteeth period is longer than during D-port
dithering

Summary

The run was successful in that mode conversion electron heating was
readily obtained. Monitoring the GPC measured electron temperature
response, a 3He transition at ~469 nm with the Chromex, and the H/D,
we could obtain fairly repeatable deposition profiles. The deposition
was peaked at Rmaj~0.66. On shot 010, strong modification of the
central channels was observed. We were unsuccessful obtaining a
comparable discharge at heating or +90deg for a number of reasons.
More experiments will be necessary and these early results strongly
motivate developing an RF scenario at ~ 5 T for MCCD.

Entered: Jul 7 2004 03:49:34:240PM
Author: Steve Wukitch
Engineering setup and run plan for Wednesday, July 16, 2003

MP#345 MCCD
SL: Wukitch
PO: wolfe

This run requires 8T operation. All required bus work inspections/re-torques
should be performed prior to the run. Bus temperatures need to be monitored
between shots.

Engineering Setup:

overnight ECDC in D2, stopping 1-2 hours prior to the run.

Power system as on 1010803010 Except:
TF PLC current limit at 175kA (we'll change this as the run proceeds)
digitizer start at -1.6sec
Acoils as on 1030711040 (+Dtop -Dbot -Jtop +Jbot) and enabled

Gas setup - fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid enabled
fill B-side upper with 15 psi of He3 Hybrid Enabled (as is)
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled, assuming no vacuum problems:
ECE, VUV, DNB, PCI, Zbolo-shutter

RF setup: in RUN ON by 8:00AM

----------------------------------------------------
Run Plan:

We will start with a lower single null 800kA discharge as on 1030710010
with target density of nl04=8e19.
Raise TF over 6 shots to 8T as follows:

Nominal BT hybrid current PLC limit
-------- ------------- ----------
5.4 150 175
6 170 175
6.5 185 190
7 200 205
7.5 215 220
8 230 235

Since we will just be verifying proper TF operation during this sequence, we
won't need to repeat shots because of fizzles.

While we're doing that we can try adjusting the He3 puff, starting with an
80msec pulse as on 1010803010 (but note that the plenum pressure was only 6psi for
that run).

Once we're up to 8T, we can scan the He3 puff to optimize the near-axis mode
conversion, then vary RF phasing for co and counter current drive. Assuming
MSE is seeing an effect, we may need to reserve the final 60 to 90 minutes for
calibration shots.
***********************************************************************************

Lost the driver bias on FMIT#2. We suspect a problem with its
transformer and fan. We will investigate later.


001 BT~5.4, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: no gate
J: ran one fault
next field is 6 T

002 BT~6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: ran clean
J: ran clean
next field is 6.5 T

Disconnected the driver bias at the output of the supply and the
supply appears fine.

003 BT~6.5, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.8 [0.7,1.3] sec
result: plasma
D: ran multiple faults
J: ran two faults
next field is 7 T

004 BT~7, Ip~0.8 MA, nl_04~0.8, SNL
D: 0. [0.7,1.3] sec
J: 0. [0.7,1.3] sec
result: plasma
next field is 7.6 T
005 BT~7.6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.2] sec
J: 1.8 [0.7,1.2] sec
result: plasma
D: ran faults
J: ran faults
next field is 8 T

fairly strong response in the e- temperature at ~0.75 m

006 BT~8, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.2] sec
J: 1.8 [0.7,1.2] sec
result: plasma - marfe
D: ran faults
J: ran faults
mode conversion is inside q=1
lower He3 puff from 80 msec to 60 msec

007 BT~8, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 6 faults
J: ran max faults
next field is 8.1 T
008 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran 3 faults
lower target density to 0.6
009 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 1.2 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran clean
observe two (for 78 and 80.5) mode conversion surfaces
sawtooth inversion radius appears to shrink with electron heating
next phase is -90deg (digital phase shifter is 30deg)

010 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.9 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran 5 trips
sawteeth are modified
011 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran clean
J: ran faults but better towards end of shot
sawteeth are modified with J-port
012 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran clean
sawteeth become shorter with J-port
013 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 3 faults
sawteeth still change with J-port
014 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 2 faults
change gas puff to 30 msec
appears the He3 has creeped upward from Chromex
015 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran 2 faults
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
016 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran clean
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
nice shot
017 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
nice shot
018 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 3 faults
J: ran max faults
mode conversion is at 66 cm
019 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
good comparison to +/-90deg
dithering
020 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.75 [0.6,1.25] sec
J: 2.0 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 4 faults
J: ran 2 faults
mode conversion is at 66 cm
sawteeth period is no different than during D-port
dithering
021 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.75 [0.6,1.25] sec
J: 2.0 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran 3 faults
mode conversion is at 66 cm
sawteeth period is longer than during D-port
dithering

Summary

The run was successful in that mode conversion electron heating was
readily obtained. Monitoring the GPC measured electron temperature
response, a 3He transition at ~469 nm with the Chromex, and the H/D,
we could obtain fairly repeatable deposition profiles. The deposition
was peaked at Rmaj~0.66. On shot 010, strong modification of the
central channels was observed. We were unsuccessful obtaining a
comparable discharge at heating or +90deg for a number of reasons.
More experiments will be necessary and these early results strongly
motivate developing an RF scenario at ~ 5 T for MCCD.

Physics Operator Summaries
Entered: Jul 7 2004 04:37:18:833PM
Author: Steve Wolfe
Physop Summary for Wed., 7/16/03

MP#345: MCCD
SL: wukitch
PO: wolfe
EO: Cochran/Dekow/Byford/Parkin
CW*: Irby

* CW=Chief Worrier

Engineering setup and run plan for Wednesday, July 16, 2003

MP#345 MCCD
SL: Wukitch
PO: wolfe

This run requires 8T operation. All required bus work inspections/re-torques
should be performed prior to the run. Bus temperatures need to be monitored
between shots.

Engineering Setup:

overnight ECDC in D2, stopping 1-2 hours prior to the run.

Power system as on 1010803010 Except:
TF PLC current limit at 175kA (we'll change this as the run proceeds)
digitizer start at -1.6sec
Acoils as on 1030711040 (+Dtop -Dbot -Jtop +Jbot) and enabled

Gas setup - fill B-top with 6 psi of D2 Hybrid enabled
fill B-side lower with 1 psi of Ar Hybrid enabled
fill B-side upper with 15 psi of He3 Hybrid Enabled (as is)
fill C-side with 30 psi of D2 Hybrid enabled

The following gate valves should be enabled, assuming no vacuum problems:
ECE, VUV, DNB, PCI, Zbolo-shutter

RF setup: in RUN ON by 8:00AM

----------------------------------------------------
Run Plan:

We will start with a lower single null 800kA discharge as on 1030710010
with target density of nl04=8e19.
Raise TF over 6 shots to 8T as follows:

Nominal BT hybrid current PLC limit TFstart
-------- ------------- ---------- -----------
5.4 150 175 -1.0
6 170 175 -1.1
6.5 185 190 -1.2
7 200 205 -1.3
7.5 215 220 -1.4
8 230 235 -1.5

Since we will just be verifying proper TF operation during this sequence, we
won't need to repeat shots because of fizzles.

While we're doing that we can try adjusting the He3 puff, starting with an
80msec pulse as on 1010803010 (but note that the plenum pressure was only 6psi for
that run).

Once we're up to 8T, we can scan the He3 puff to optimize the near-axis mode
conversion, then vary RF phasing for co and counter current drive. Assuming
MSE is seeing an effect, we may need to reserve the final 60 to 90 minutes for
calibration shots.



Execution
----------

Prior to the run, modified the engineering setup to put the TF start at -1.0;
we'll bring that earlier as we increase the current. TF invert set back to
+1.6sec since we aren't using the back porch

Also, noted fizzle detector on 1010803 was off at 1.0; moved that to 1.8.

From the physop standpoint, everything went as planned. We had 21 shots, 16 at
8.0T or above (one at 8.1T). All plasmas were full length. Startups were
robust, and only a few gas tweaks were needed to get rid of runaways. No
adjustment was needed to compensate for the increased TF at t=0, which got to
-7.07T for the 8.0T shots with TFstart at -1.5sec. The actual PCS waveform to
get 8.0T turned out to be 225kA, with a PLC limit of 230. From shot #5 on we
moved the TF invert time to 1.2sec (from 1.6) to reduce magnet heating. Also
from shot#5 on, we waited a minimum of 20min in recool.

Well-localized mode conversion damping was observed on ECE in all
phasings. The species mix was varied by decreasing the He3 puff from the
initial value of 80ms to 15msec, which seemed to be the appropriate value to
move the layer close to the axis. Current drive effects were not so
clear. Changes in sawtooth period were observed, but it was not clear that the
effects made sense. Shot 16 seemed to indicate a significant increase in
period with co-current phasing, but shots 20 and 21, at higher power, seemed
to exhibit the opposite effect. The DNB had some problems but MSE did get some
data near the center, which hopefully will be suitable for analysis.

A vibration was noted in the alternator when the speed dropped to
1520rpm. This was avoided by increasing the initial speed from 1703 to
1718rpm at shot#12.

The interphase transformers on the TF ratcheted up to 75C on the outer
windings over the course of the day. We do need additional cooling but this
temp is well within allowables. The magnet temperature after the pulses showed
no ratcheting after we increased the recool time to 20min.

On the last shot (#21) we blew a fuse in one of the TF cabinets; the PLC
showed a "1 SCR not conducting" fault, but the shot ran through
normally. Since it was already after five o'clock, we did not take the planned
MSE calibration shot at the end of the day. If possible, we'll try to get it
in at the end of the run tomorrow.

Scorecard
---------

Tests 0
Duds 0
Fizzles 0
Plasmas 21
====== ==
shots 21

Session Leader Comments
Jul 16 2003 09:51:38:000AM1030716001Steve Wukitch001 BT~5.4, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: no gate
J: ran one fault
next field is 6 T
Jul 16 2003 09:55:10:507AM1030716001Steve Wukitch001 BT~5.4, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: no gate
J: ran one fault
next field is 6 T
Jul 16 2003 09:55:23:973AM1030716002Steve Wukitch002 BT~6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: ran clean
J: ran clean
next field is 6.5 T
Jul 16 2003 09:56:07:180AM1030716003Steve Wukitch003 BT~6.5, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.3] sec
J: 1.2 [0.7,1.3] sec
result: plasma
D: ran multiple faults
J: ran two faults
next field is 7 T
Jul 16 2003 10:12:28:440AM1030716004Steve Wukitch004 BT~7, Ip~0.8 MA, nl_04~0.8, SNL
D: 0. [0.7,1.3] sec
J: 0. [0.7,1.3] sec
result: plasma
next field is 7.6 T
Jul 16 2003 10:53:26:500AM1030716005Steve Wukitch005 BT~7.6, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.6 [0.7,1.2] sec
J: 1.8 [0.7,1.2] sec
result: plasma
D: ran faults
J: ran faults
fairly strong response in the e- temperature at ~0.75 m
next field is 8 T

Jul 16 2003 12:27:42:570PM1030716008Steve Wukitch008 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran 3 faults
next field is 8.0T
Jul 16 2003 12:27:56:897PM1030716009Steve Wukitch009 BT~8.1, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 2.0 [0.7,1.2] sec
phase is [0,pi,pi,0] (digital phase shifter is 140deg)
result: plasma
D: ran 4 faults
J: ran clean
observe two (for 78 and 80.5) mode conversion surfaces
next phase is -90deg (digital phase shifter is 30deg)
Jul 16 2003 01:01:00:743PM1030716010Steve Wukitch010 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 0.9 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran 5 trips
sawteeth are modified
Jul 16 2003 01:01:33:197PM1030716011Steve Wukitch011 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.7,1.2] sec
J: 1.5 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran clean
J: ran faults but better towards end of shot
sawteeth are modified with J-port
Jul 16 2003 01:40:32:023PM1030716012Steve Wukitch012 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 3 faults
J: ran clean
sawteeth become shorter with J-port
Jul 16 2003 02:20:12:570PM1030716013Steve Wukitch013 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 3 faults
Jul 16 2003 02:20:43:943PM1030716014Steve Wukitch014 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 2 faults
J: ran 2 faults
Jul 16 2003 02:43:25:823PM1030716015Steve Wukitch015 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran 2 faults
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
Jul 16 2003 04:11:48:117PM1030716016Steve Wukitch016 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
+90deg (dps=220deg)
result: plasma
D: ran 3 faults
J: ran clean
He3 is back to 010 but still off axis - H fraction has increased
lower puff to 15 msec
nice shot
Jul 16 2003 04:12:01:553PM1030716017Steve Wukitch017 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
-90deg (dps=30deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
nice shot
Jul 16 2003 04:12:14:757PM1030716018Steve Wukitch018 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 3 faults
J: ran max faults
mode conversion is at 66 cm
Jul 16 2003 04:27:06:810PM1030716019Steve Wukitch019 BT~8.0, Ip~0.8 MA, nl_04~0.8, SNL
D: 1.0 [0.6,1.25] sec
J: 1.3 [0.7,1.2] sec
0deg (dps=140deg)
result: plasma
D: ran 8 faults
J: ran clean
mode conversion is at 66 cm
good comparison to +/-90deg

Physics Operator Comments
Jul 15 2003 05:31:08:680PMSteve WolfeBegin PCS setup for 1030716 run

Startup from 1030715033
Seg2 from 1030710010 (change title)
Do a build, get two factor ack messages and a wirename warning.
Touch the wire and rebuild.
Save as /home/wolfe/pcs_trees/pcs_1030716999
Jul 16 2003 08:05:40:500AMSteve WolfeLoaded from previously prepared (and mis-named) /home/wolfe/pcs_trees/pcs_1030717999
replace pg2 (He3 in bside-upper) waveform as on 1010803010 : 80msec at .3sec
copy a pg3 waveform from seg3 (seg2 was basically zero pre-program)
load/clean
Load at 16-Jul-2003 08:05:28.00
Open tree /home/wolfe/pcs_scratch -1
Open tree done
Jul 16 2003 09:18:42:537AM1030716001Steve Wolfeshot#1: setup for standard 5.4T 800kA SNL shot, w/80msec He3 puff
E-port will not be operational today - crowbar ready problem

plasma, full length.

next shot:Tf to 170kA, start at -1.1sec
Jul 16 2003 09:34:48:020AM1030716002Steve Wolfeshot#2:Tf to 170kA (6T) in seg1 and 2, start at -1.1sec
pg4 from 23 to 25msec

plasma full length. 6.1T, bad bounce on startup.

next shot: TF to 6.5T, 185ka (PLC to 190) start at -1.2sec
pg4 up again.
Jul 16 2003 09:50:12:123AM1030716003Steve Wolfeshot#3: TF to 6.5T, 185ka (PLC to 190) start at -1.2sec
pg4 to 28msec

plasma full length, startup looks good.

next shot: tf to 7.1T (200kA) PLC to 205, start at -1.3sec
Jul 16 2003 10:07:53:570AM1030716004Steve Wolfeshot#4: tf to 7.1T (200kA) PLC to 205, start at -1.3sec
RF off for this shot, avoid resonance in antenna boxes

plasma, full length 7.1T (6.6@t=0)

next shot: 7.6T (215ka) 220 on PLC, TF start at -1.4s
Jul 16 2003 10:08:59:060AM1030716004Steve Wolfeshot#4: tf to 7.1T (200kA) PLC to 205, start at -1.3sec
RF off for this shot, avoid resonance in antenna boxes

plasma, full length 7.1T (6.6@t=0)

next shot: 7.6T (215ka) 220 on PLC, TF start at -1.4s
Jul 16 2003 10:33:48:410AM1030716005Steve Wolfeshot#5: tf to 7.6T (215ka) 220 on PLC, TF start at -1.4s
rf back on. Now waiting 20 minutes in recool.
Move tf invert to +1.2sec for now to reduce heating; will move it out once we
start doing physics.

plasma full length, 7.65T reaches flattop at ~.6sec
RF not too happy.

next shot:8.0T (225kA) PLC to 230 tstart=-1.5sec

Jul 16 2003 11:02:41:487AM1030716006Steve Wolfeshot#6: tf to 8.0T (225kA) PLC to 230 tstart=-1.5sec

7.99T plasma full length but marfed early. flattop at ~.62sec
TCI feedback went nuts. TS says density got to 6e20
Steve says on-axis heating based on ece.

next shot: drop He3 puff from 80 to 60msec
also drop pg4 by 2msec
Jul 16 2003 11:30:15:183AM1030716007Steve Wolfeshot#7: drop He3 puff from 80 to 60msec
also drop pg4 by 2msec to 26msec

plasma full length, current rise still a little slow.
No marfe this time
RF still not staying on.

next shot: drop pg4 to 24msec
slow down density rise
Go to 8.1T (228kA) PLC to 235
Jul 16 2003 11:48:09:773AM1030716008Steve Wolfeshot#8: drop pg4 to 24msec
slow down density rise
Go to 8.1T (228kA) PLC to 235

8.1T plasma full length; startup was faster this time.

next shot: drop nl4 to 6e19
Jul 16 2003 12:16:33:490PM1030716009Steve Wolfeshot#9: drop nl4 to 6e19, lower pg3 in seg2
Drop tf back to 8.0T, 225kA, PLC to 230

8.0 T plasma full length; bad bounce on startup, some hards.


next shot: raise pg4 back to 28msec
Wukie is going to start changing phase
Jul 16 2003 12:36:11:143PM1030716010Steve Wolfeshot#10: raise pg4 back to 28msec
Wukie is going to start changing phase

plasma full length, startup ok

next shot: no changes, RF still tweaking
Jul 16 2003 12:58:44:710PM1030716011Steve Wolfeshot#11: no changes, RF still tweaking

plasma full length, startup ok.

next shot: no change
Jul 16 2003 01:18:18:803PM1030716012Steve Wolfeshot#12: no changes, RF still tweaking

plasma full length, startup ok, rf moer or less clean.

next shot: change the phase
Jul 16 2003 01:50:30:413PM1030716013Steve Wolfeshot#13: no pcs changes; rf will change the phase
engineers have raised the alternator speed to 1718 to try to avoid a
vibration near the minimum speed on these pulses.

plasma full lenth, startup ok.
sawtooth effect looks the same to me.

next shot: no changes
Jul 16 2003 02:08:54:927PM1030716014Steve Wolfeshot#14: no pcs changes

plasma full length, startup ok
sawteeth are still smaller with J on.

next shot: drop pg2 from 60ms to 30ms
Jul 16 2003 02:33:28:933PM1030716015Steve Wolfeshot#15: drop pg2 He3 from 60ms to 30ms

plasma full length, startup ok.
still small sawteeth during J pulses

next shot:pg2 to 15msec
Jul 16 2003 02:55:23:560PM1030716016Steve Wolfeshot#16:pg2 He3 to 15msec

plasma full length, startup ok
some longer sawteeth.

next shot: change the phase again
Jul 16 2003 03:15:59:780PM1030716017Steve Wolfeshot#17: change the phase again

plasma full length, startup ok, moves back in a little bit
sawteeth look smaller. Maybe a result.

next shot: no changes, rf to 0-pi-pi-0
Jul 16 2003 03:41:28:287PM1030716018Steve Wolfeshot#18: no changes, rf to 0-pi-pi-0

plasma full length, startup ok
sawteeth are short, but J was mostly faulting.

next shot: repeat
Jul 16 2003 04:03:51:650PM1030716019Steve Wolfeshot#19: repeat rf at 0-pi-pi-0

plasma full length, startup ok
rf looks good.
next shot: raise the rf power in current drive phase
Jul 16 2003 04:32:22:740PM1030716020Steve Wolfeshot#20: raise the rf power in current drive phase

plasma full length, startup ok; J at 2MW
short sawteeth, not what we were expecting.

next shot: change phase to counter, same power
Jul 16 2003 04:51:34:397PM1030716021Steve Wolfeshot#21: change phase to counter, same power

plasma full length. startup ok
sawteeth are longer than previous shot.
There was a TF supply fault on the plc (1 scr not conducting)

next shot: if there is one, will be a TF +EF4 +EF3 for MSE cal.
Jul 16 2003 05:05:18:447PM1030716021Steve Wolfeshot#22: TF +EF4 +EF3 for MSE cal.

import seg1 from 1030521014, copy tf from seg2, turn off seg2
tf, ef4, ef3 enabled; all others off
f.d on at 1sec off at 1.1sec
btop gas enabled, all others disabled.

fuse was blown in tf suppply, and it's after five, so we won't take
this shot. It's loaded in PCS and we can take it tomorrow if there's
time.

Engineering Operator Comments
ShotTimeTypeStatusComment
109:14:24:043AMPlasmaOk
209:29:27:067AMPlasmaOk
309:46:08:960AMPlasmaOk
410:04:22:300AMPlasmaOk
510:27:20:900AMPlasmaOk
610:53:28:830AMPlasmaOk
711:17:35:820AMPlasmaOk
811:41:17:920AMPlasmaOk
912:04:05:140PMPlasmaOk
1012:28:04:333PMPlasmaOk
1112:50:49:370PMPlasmaOk
1201:14:09:733PMPlasmaOk
1301:37:12:160PMPlasmaOk
1402:00:45:977PMPlasmaOk
1502:24:29:310PMPlasmaOk
1602:48:02:910PMPlasmaOk
1703:11:22:943PMPlasmaOk
1803:35:21:247PMPlasmaOk
1903:59:06:003PMPlasmaOk
2004:21:55:520PMPlasmaOk
2104:45:37:543PMPlasmaOkShot OK, 1 SCR not cond in Aux cab