| Session leader(s): | Unknown |
| Physics operator(s): | Robert Granetz |
| Engineering operator(s): | Bill Cochran,Gary Dekow |
| Engineering Operator Run Comment |
| Power System Tests |
| Session Leader Plans |
| Physics Operators Plans |
| Session Leader Summaries |
| Physics Operator Summaries |
| Entered: Jul 7 2004 04:37:18:957PM |
| Author: Robert Granetz |
| Physics operator summary for run 1031008 (Wednesday): Purpose: Test power supplies; possibly go for plasma Session leader: -- Physics operator: R. Granetz Engineers in charge: W. Cochran/G. Dekow Summary: We got through most of the PF supplies, but data acquisition problems prevented us from finishing up. The OH's, EF1's, EF3, EF4, and EFC supplies are working fine. A problem with charging the cap banks was also discovered. So the power supply tests will have to continue tomorrow. Scorecard: 0 plasmas 0 fizzles 0 duds 21 tests or no-power shot cycles 0 aborted and/or screwed up by computer problems ---------- 21 total ------------------------------------------------------------------------------- Engineering setup for Wednesday, 08 Oct 2003 Purpose: Test power supplies; possibly go for plasma. Session leader: -- Physics operator: R. Granetz Engineering operator: W. Cochran/G. Dekow ECDC overnight in D2 at 2e-4 Torr, stopping by 07:00. Bake at 60 C overnight as well. Run begins at 09:00 and ends at 17:00. Power systems the same as on 1030715001 (1.0 MA, 5.4 T, lower single null) Gas setup: fill B-Top with 6 psi D2 Hybrid enabled (PG4) fill B-side lower with 1 psi Ar Hybrid enabled (PG1) fill B-side upper with 10 psi D2 Hybrid DISABLED (PG2) (for ECDC) fill C-side with 30 psi D2 Hybrid enabled (PG3) Enable the following gate valves, assuming no vacuum problems: none ------------------------------------------------------------------------------- RF Setup: no RF today ------------------------------------------------------------------------------- Run Plan: Test the power supplies, mostly under PLC control. Keep an eye on the flywheel bearing vibration. If we get through all the supplies, try for a plasma shot. ------------------------------------------------------------------------------- ECDC was done overnight, as well as a 60 C bake. Hybrid coldstart done by the engineering group; no errors found Loaded PCS from shot 1030715001 (1.0 MA, 5.4 T, nl_04=1.0e20 m-2, single null lower). (I didn't write this shot into the hybrid tree until after the first shot. ------------------------------------------------------------------------------- Shot 01 -- Test of shot cycle. Next shot: load PCS from 1030715001. Shot 02 -- OH1, -1 kA. All magnetics hybrid inputs look good. Shot 03 -- no power; should have been OH1, +1 kA. May have had some DAQ init problems. Next shot: repeat try for reverse OH1. Shot 04 -- no power. Might be some problem with OH1 control signals. Shot 05 -- OH1, +2 kA. Okay. Shot 06 -- OH2U, -1 kA. Okay. Shot 07 -- OH2U, supposed to be +1 kA, but there was just a 2 kA spike. Shot 08 -- OH2L, -2 kA. Okay. Shot 09 -- OH2L, +1.5 kA. Okay. Shot 10 -- EF1U, -2 kA. Okay. Shot 11 -- EF1U, +2 kA. Okay. Shot 12 -- EF1L, -2 kA. Okay. Shot 13 -- EF1L, +2 kA. Okay. Shot 14 -- EF3. Okay. (short blip, but that's good enough) Shot 15 -- EF4, -2 kA. All okay with EF4 supply. Simultaneous test of capacitor bank charging had problems. Shot 16 -- EF4, +2 kA. Okay. Most cap banks charged okay too, except for the EF1L bank. Shot 17 -- EFC. It worked, but there were lots of DAQ failures, including much of the EFC instrumentation. Shot 18 -- no power. Test of data acquisition. DAQ works if the crate in the alternator house is taken offline. Shot 19 -- EFC. Higher voltage. Okay. Shot 20 -- EFC. It worked, but again there were lots of DAQ failures, including much of the EFC instrumentation. This might mean the the crate in the alternator house is not the whole problem. Shot 21 -- no power. Another data system test. End of run. |
| Session Leader Comments |
| Physics Operator Comments | |||
| Oct 8 2003 10:00:28:773AM | Robert Granetz | ECDC was done overnight, as well as a 60 C bake. Hybrid coldstart done by the engineering group; no errors found Loaded PCS from shot 1030715001 (1.0 MA, 5.4 T, nl_04=1.0e20 m-2, single null lower). (I didn't write this shot into the hybrid tree until after the first shot. | |
| Oct 8 2003 11:46:41:303AM | Robert Granetz | Engineering setup for Wednesday, 08 Oct 2003 Purpose: Test power supplies; possibly go for plasma. Session leader: -- Physics operator: R. Granetz Engineering operator: W. Cochran ECDC overnight in D2 at 2e-4 Torr, stopping by 07:00. Bake at 60 C overnight as well. Run begins at 09:00 and ends at 17:00. Power systems the same as on 1030715001 (1.0 MA, 5.4 T, lower single null) Gas setup: fill B-Top with 6 psi D2 Hybrid enabled (PG4) fill B-side lower with 1 psi Ar Hybrid enabled (PG1) fill B-side upper with 10 psi D2 Hybrid DISABLED (PG2) (for ECDC) fill C-side with 30 psi D2 Hybrid enabled (PG3) Enable the following gate valves, assuming no vacuum problems: none ------------------------------------------------------------------------------- RF Setup: no RF today ------------------------------------------------------------------------------- Run Plan: Test the power supplies, mostly under PLC control. Keep an eye on the flywheel bearing vibration. If we get through all the supplies, try for a plasma shot. ------------------------------------------------------------------------------- ECDC was done overnight, as well as a 60 C bake. Hybrid coldstart done by the engineering group; no errors found Loaded PCS from shot 1030715001 (1.0 MA, 5.4 T, nl_04=1.0e20 m-2, single null lower). (I didn't write this shot into the hybrid tree until after the first shot. | |
| Oct 8 2003 10:00:44:963AM | 1031008001 | Robert Granetz | Shot 01 -- Test of shot cycle. Next shot: load PCS from 1030715001. |
| Oct 8 2003 10:01:04:070AM | 1031008002 | Robert Granetz | Shot 02 -- OH1, -1 kA. All magnetics hybrid inputs look good. |
| Oct 8 2003 10:01:13:057AM | 1031008003 | Robert Granetz | Shot 03 -- no power; should have been OH1, +1 kA. May have had some DAQ init problems. Next shot: repeat try for reverse OH1. |
| Oct 8 2003 10:24:44:397AM | 1031008004 | Robert Granetz | Shot 04 -- no power. Might be some problem with OH1 control signals. |
| Oct 8 2003 10:42:00:230AM | 1031008006 | Robert Granetz | Shot 05 -- OH1, +2 kA. Okay. |
| Oct 8 2003 10:46:46:413AM | 1031008006 | Robert Granetz | Shot 06 -- OH2U, -1 kA. Okay. |
| Oct 8 2003 10:58:22:560AM | 1031008007 | Robert Granetz | Shot 07 -- OH2U, supposed to be +1 kA, but there was just a 2 kA spike. |
| Oct 8 2003 11:30:33:317AM | 1031008008 | Robert Granetz | Shot 08 -- OH2L, -2 kA. Okay. |
| Oct 8 2003 11:46:11:257AM | 1031008009 | Robert Granetz | Shot 09 -- OH2L, +1.5 kA. Okay. |
| Oct 8 2003 12:00:32:620PM | 1031008010 | Robert Granetz | Shot 10 -- EF1U, -2 kA. Okay. |
| Oct 8 2003 12:14:02:393PM | 1031008011 | Robert Granetz | Shot 11 -- EF1U, +2 kA. Okay. |
| Oct 8 2003 12:34:29:890PM | 1031008012 | Robert Granetz | Shot 12 -- EF1L, -2 kA. Okay. |
| Oct 8 2003 12:33:45:407PM | 1031008013 | Robert Granetz | Shot 12 -- EF1L, +2 kA. Okay |
| Oct 8 2003 12:40:45:013PM | 1031008014 | Robert Granetz | Shot 14 -- EF3. Okay. (short blip, but that's good enough) |
| Oct 8 2003 12:56:58:140PM | 1031008015 | Robert Granetz | Shot 15 -- EF4, -2 kA. All okay with EF4 supply. Simultaneous test of capacitor bank charging had problems. |
| Oct 8 2003 01:09:37:943PM | 1031008016 | Robert Granetz | Shot 16 -- EF4, +2 kA. Okay. Most cap banks charged okay too, except for the EF1L bank. |
| Oct 8 2003 01:28:14:370PM | 1031008017 | Robert Granetz | Shot 17 -- EFC. It worked, but there were lots of DAQ failures, including much of the EFC instrumentation. |
| Oct 8 2003 02:46:18:210PM | 1031008018 | Robert Granetz | Shot 18 -- no power. Test of data acquisition. DAQ works if the crate in the alternator house is taken offline. |
| Oct 8 2003 03:03:46:827PM | 1031008019 | Robert Granetz | Shot 19 -- EFC. Higher voltage. Okay. |
| Oct 8 2003 03:18:29:083PM | 1031008020 | Robert Granetz | Shot 20 -- EFC. It worked, but again there were lots of DAQ failures, including much of the EFC instrumentation. This might mean the the crate in the alternator house is not the whole problem. |
| Oct 8 2003 06:16:09:590PM | 1031008021 | Robert Granetz | Shot 21 -- no power. Another data system test. |
| Engineering Operator Comments | ||||
| Shot | Time | Type | Status | Comment |
| 1 | 09:15:18:107AM | Test | Ok | Data System Test |
| 2 | 09:33:02:157AM | Test | Ok | OH1 Fwd PLC |
| 3 | 09:49:37:627AM | Test | Bad | OH1 reverse plc test |
| 4 | 10:00:01:900AM | Test | Bad | OH1 reverse plc test |
| 5 | 10:32:44:267AM | Test | Ok | OH1 reverse plc test |
| 6 | 10:41:49:930AM | Test | Bad | OH2U fwd plc test |
| 7 | 10:54:52:907AM | Test | Bad | OH2U reverse plc |
| 8 | 11:27:19:647AM | Test | Ok | OH2L fwd plc test |
| 9 | 11:39:02:763AM | Test | Ok | |
| 10 | 11:57:39:547AM | Test | Ok | EF1U fwd plc test |
| 11 | 12:10:38:580PM | Test | Ok | EF1U reverse plc |
| 12 | 12:19:06:623PM | Test | Ok | EF1 fwd plc test |
| 13 | 12:27:53:473PM | Test | Ok | EF1L reverse plc test |
| 14 | 12:35:47:547PM | Test | Ok | EF3 plc test |
| 15 | 12:47:43:210PM | Test | Ok | |
| 16 | 01:05:28:853PM | Test | Ok | |
| 17 | 01:21:13:027PM | Test | Ok | |
| 18 | 02:41:55:460PM | Test | Ok | |
| 19 | 02:59:59:170PM | Test | Ok | |
| 20 | 03:12:31:957PM | Test | Ok | |
| 21 | 06:03:19:053PM | Test | Ok | |