Alcator C-Mod Run 1060202 Information

Back to runs

Miniproposals

Operators
Session leader(s):
Physics operator(s):Steve Wolfe
Engineering operator(s):Gary Dekow

Engineering Operator Run Comment
Cycle, Scanner and Gas System Tests

Session Leader Plans

Physics Operators Plans

Session Leader Summaries

Physics Operator Summaries
Entered: Feb 2 2006 04:01:20:763PM
Author: Steve Wolfe
Cycle and Gas tests
SL: Irby
EO: Dekow
PO: wolfe

We ran off four test cycles. 
The purpose of today's exercise was to 
1) Verify operation of the cycle and data system in advance of next
   week's operation
2) Test the possibility of puffing diborane into a discharge. The
   main issue tested is whether we need a plenum or can just puff 
   from the line, and what PLC programming changes might be needed
3) Verify that some new features in dpcs aren't going to break the cycle
4) Check out some of the data acquisition system
5) Verify that the gate valve toggling is still working

All the tests went well. 

The "diborane" valve was wired to the output from the B-side upper
piezo driver by moving the cable in the cell (near B-port). The line
pressure indicated 31psi. Tests were run using programmed V waveform 
on PG2 in PCS. The fizzle detector gate was delayed until 1.7sec.
A programmed 100V pulse from 0.3sec to 2sec was terminated successfully
at 1.7sec by the dpcs_fizzle async routine in dpcs; the hardware 
fizzle detector presumably took out the valve permissive shortly thereafter.
The pressure rise with this long pulse was enough to switch off the ion
gauges. The divertor pressure manometer peaked out at ~33mTorr. We also
took shots with durations of 1.0 and 0.5sec, resulting in machine 
pressures of 23 and 12mTorr; it seems to be pretty linear. The rise rate 
is about 20mTorr/sec with a slight delay after the valve is energized. 

In order to get the diborane line to fill it was necessary for Joe to 
defeat the logic that requires the torus ion gauge to be off. Since we
wanted to be able to watch the pressure (and we were just puffing He), 
this was necessary. Whether we want to expose the ion gauge to diborane
during operation is a question that remains to be answered. 

The only problem with the cycle was that Pat's voice wasn't announcing 
until we restarted the routine on cmodws02, which was acting a little
funny until we moved the keyboard. She was on the air for the first shot.

The camac signals from the gas valve drivers were disconnected for the
first shots. Joe and Yuri recovered these (again). Ratiomatic was there
and working from the beginning. There were no data system problems. 

The dpcs_fizzle routine seems to be working as intended. The dpcs_init 
was taking 28 to 29sec, which is consistent with off-line testing 
results. The response to the fizzle gate is immediate. There is a one
sample glitch on the digitized output (on the dt200_1, at 50kHz) that
may or may not be a real transient.

Gate valves were closed in pulse on shot#4. Seemed to work. Jim was 
also running the rga in run mode, so we should have before and after 
data. 

The i2t circuits were operational and their interlock had to be bypassed
since there were coils above -25C (we're still baking). An ok test.

After the "run" the cabling on B-side upper and the diborane system
was restored to normal, and I put back a more normal (200msec) puff on 
the PG2. 

Session Leader Comments

Physics Operator Comments
Feb 2 2006 12:21:22:097PM1060202001Steve Wolfe
Shot#1: Got plenty of gas (shut the gauge off)
Ratiomatic reached .002 gauge and went into caniptions
at ~1sec. 

next shot: back down on pg2

Feb 2 2006 03:24:30:357PM1060202001Steve Wolfe
Getting set up for cycle tests. 
We are going to be testing gas puff through the diborane
valve. 
FOR PURPOSES OF THIS TEST - B-side upper (pg2) cable has been 
connected to the diborane piezo. There is no diborane installed. 
There is a helium bottle in the diborane cabinet for testing
purposes.

I will draw a long pulse in seg2 on pg2 (300ms to 2.2sec)
Fizzle detector gate should start at 1.7sec
I have dpcs_fizz enabled, so I should see the waveform 
go to zero at 1.7sec

Load at  2-Feb-2006 11:59:14.00
Open tree /home/wolfe/pcs_scratch      -1
Open tree done


Feb 2 2006 12:36:39:060PM1060202002Steve Wolfe
Shot#2: pg2 program off at 1.3sec (still starting at 0.3)
Gauge turned off again. 
Div pressure gets to 20mTorr. 

I'm not seeing a signal on the bside-upper digitizer.
I guess that digitizer is actually on the valve, not
on the driver? Or maybe the cable aren't connected again. 

Feb 2 2006 12:50:23:727PM1060202003Steve Wolfe
Shot#3: No program change. Jim wants to try
toggling gate valves. Joe and Yuri are looking for
the valve drive signals in the cell. Yes, they were 
disconnected; Gary blames the HIREX move (instead of
LH) this time. 

Turned off the gauge again. 
This time we've got signal on the valve driver camac for
B-side upper (really the diborane valve)

next shot: back the pg2 puff back to 500msec

Feb 2 2006 01:14:00:077PM1060202004Steve Wolfe
After the last shot, put the pg2 waveform back to 
ending at .5sec, so we don't leave a long pulse 
around for tests next week. I'll probably change it
by then anyway, but load this for now so we're somewhat
back where we were. 

Load at  2-Feb-2006 13:13:33.00
Open tree /home/wolfe/pcs_scratch      -1
Open tree done


Feb 2 2006 04:06:49:280PM1060202004Steve Wolfe
Shot#4: back the pg2 puff from 0.3 to 0.8sec
got around 11 or 12 mTorr on the divertor pressure gauge
F-side pressure is saying ~4.5, but that's a ratiomatic
and the gauge factor for He is lower. 

I think we're done with these tests. 

Engineering Operator Comments
ShotTimeTypeStatusComment
112:16:45:753PMTestOkCycle, Gas and Sanner test
212:28:01:563PMTestOkCycle, Gas and TF Scanner test
312:46:15:743PMTestOkCycle, Gas and TF Scanner Test
412:57:09:460PMTestOkCycle, Gas and TF Scanner
511:47:00:810AMTestOkEFC Chopper Test 400V
611:56:19:073AMTestOkEFC Chopper Test 400V
712:05:13:930PMTestOkEFC Chopper Test 600V