| Miniproposals |
| Operators | |
| Session leader(s): | |
| Physics operator(s): | Bill Rowan |
| Engineering operator(s): | Bill Cochran |
| Engineering Operator Run Comment |
| Engineering Tests EO: Cochran PO: rowan |
| Session Leader Plans |
| Physics Operators Plans |
| Entered: Feb 7 2006 07:35:58:830AM |
| Author: Bill Rowan |
| PhysOp Plan for 1060207
MP 298a. Power Tests SL: Cochran, Irby PO: Rowan Begin by operating the supplies individually under PLC control. Advance to hybrid control of supplies and thence to plasma shots as progress warrants. Two sets of non-standard shots are requested by Wolfe and Ferrara. These will accomplish 1) Testing of digital fizzle detector program 2. Testing of chopper response, noise spectrum. |
| Session Leader Summaries |
| Physics Operator Summaries |
| Entered: Feb 8 2006 07:00:18:657AM |
| Author: Bill Rowan |
| All shots were run under PLC control for 1060207. See the POWER_SYSTEMS log
for details. The run was delayed until noon by a leak at C-port. The seals were freezing. When heating was added to the seal area, the leak was reduced but did reappear later in the day. The EF4 supply was found to require some attention. B-Main puff valve was not working. |
| Session Leader Comments |
| Physics Operator Comments | |||
| Feb 7 2006 08:50:11:990AM | 1060207001 | Bill Rowan | 001. While the supplies are being tested under PLC control, progress can be followed in the POWER_SYSTEMS entries |
| Engineering Operator Comments | ||||
| Shot | Time | Type | Status | Comment |
| 8 | 12:33:32:857PM | Test | Ok | EFC Chopper Test 800V |
| 9 | 12:43:34:730PM | Test | Bad | EF2U PLC Test |
| 10 | 12:52:03:143PM | Test | Ok | EF2U PLC Test |
| 11 | 01:01:37:743PM | Test | Ok | EF2L PLC Test |
| 12 | 01:12:00:140PM | Test | Ok | C.Coil Test |
| 13 | 01:24:44:040PM | Test | Ok | EF3 PLC Test |
| 14 | 01:32:32:273PM | Test | Ok | EF4 Forward PLC Test |
| 15 | 01:41:22:130PM | Test | Bad | EF4 Reverse PLC Test |
| 16 | 01:59:24:357PM | Test | Bad | EF4 Reverse PLC Test |
| 17 | 02:14:35:663PM | Test | Ok | EF1U Forward Test |
| 18 | 02:22:16:940PM | Test | Bad | I2t Fault |
| 19 | 02:36:02:857PM | Test | Ok | EF1U Reverse PLC Test |
| 20 | 02:43:06:323PM | Test | Ok | EF1L Forward PLC Test |
| 21 | 02:50:05:960PM | Test | Ok | EF1L Reverse PLC Test |
| 22 | 03:00:47:113PM | Test | Ok | OH1U Forward PLC Test |
| 23 | 03:06:37:940PM | Test | Ok | OH1 Reverse PLC Test |
| 24 | 03:13:15:750PM | Test | Ok | OH2U Forward PLC Test |
| 25 | 03:22:46:780PM | Test | Ok | OH2U Reverse PLC Test |
| 26 | 03:29:01:853PM | Test | Ok | OH2L Forward PLC test |
| 27 | 03:35:52:257PM | Test | Ok | OH2L Reverse PLC Test |
| 28 | 03:42:31:613PM | Test | Ok | OH Commutation Test |
| 29 | 03:49:43:393PM | Test | Ok | EF1 Commutation Test |
| 30 | 04:00:32:607PM | Test | Bad | EF4 Double Swing Test |
| 31 | 04:18:20:883PM | Test | Ok | EF4 No Power Test |
| 32 | 04:30:52:860PM | Test | Ok | TF 50kA PLC Test |
| 33 | 04:45:52:590PM | Test | Ok | TF 100kA PLC Test |
| 34 | 04:59:41:020PM | Test | Ok | TF 150kA PLC Test |