Session Leader Plans

Physics Operators Plans
Entered: Jun 6 2007 11:39:13:030AM
Author: Bill Rowan
Engineering Setup for Thursday, 7 June 2007; Run 1070607

MP#: 490 "Assessing LHCD in ICRF -Heated L and H-modes"

SL: Amanda Hubbard
PO: Bill Rowan

Engineering Setup
------------------
ECDC overnight in D2, pressure=2e-4 Torr. Rmin/Rdwell/Rmax = 44/45/103 cm.
Bake at 60 C.

Run begins at 09:00 and ends at 17:00

Power systems as on 1070427008

Acoil: +Dtop -Dbot -Jtop +Jbot (standard) Hybrid Enabled

Gas setup:
---------
Fill B-Top with 6 psi D2 Hybrid enabled (PG4)
fill B-side lower with 1 psi Ar Hybrid DISABLED (PG1)
leave B-side upper as is Hybrid DISABLED (PG2)
fill B-main (C-side) with 40 psi D2 Hybrid enabled (PG3)
pump out NINJA then disable.

Enable the following gate valves and shutters, assuming no vacuum problems:
ECE, VUV, Z-bolo shutters
DNB permissive enabled


RF Systems:
----------
LH: Full power

ICRF: J-port at 2 MW essential; D and/or E desirable.
FMIT#1,2,3,4 in RUN-ON by 08:30


Diagnostics
----------
DNB: 50 kV, 6A by 09:00


Torvac setup
----------
Gate valves open

Session Leader Summaries

Physics Operator Summaries

Session Leader Comments

Physics Operator Comments

Engineering Operator Comments
ShotTimeTypeStatusComment