Alcator C-Mod Run 1070327 Information

Back to runs

Miniproposals
Miniproposal:298a
Date Filed: 5/20/2002
Title:C-Mod Plasma Startup
First Author:Jim Irby
Session Leader:Steve Wolfe (shots 1-24)

Operators
Session leader(s):Steve Wolfe
Physics operator(s):Jim Irby
Engineering operator(s):Bill Cochran,Bill Byford,Bill Parkin

Engineering Operator Run Comment
MP# 298a: Startup

Session Leader Plans

Physics Operators Plans
Entered: Mar 26 2007 05:37:56:083PM
Author: Jim Irby
Engineering setup for Tuesday 27 March 2007

C-Mod has been up-to-argon to remove a leaking sparker at B-hor. A new sparker has been installed at B-Hor using the impurity injector 4-1/8" gatevalve. A new cable has also been fabricated with what we hope is better shielding.

The vessel was baked at 100 C and ECDC was run over the weekend to recover from the up-to-argon. The RGA indicates that the vacuum today is no worse than last Thursday evening or even early Friday morning. However, there may still be plasma cleanup work to do that will delay the start of the LH operation.

Several no-power cycle tests will be required, taken I hope, before 9:00, to make sure that critical systems are back on-line following the sparker noise attack last Friday. The condition of the ACCESS system should also be checked out.

MP# 298a: Startup

Session leader: Wolfe
Physics operator: Irby

ECDC overnight in D2, pressure=2e-4 Torr. Rmin/Rdwell/Rmax = 44/45/103 cm.
Bake at 60 C.

The run will start at 09:00 and end at 17:00.

Power systems as on 1070322001.

A-coil configuration: normal [Dtop -Dbot -Jtop +Jbot] and enabled.

Gas Setup:
fill B-Top with 6 psi D2 Hybrid enabled (PG4)
fill B-side lower with 1 psi Ar Hybrid DISABLED (PG1)
leave B-side upper as is Hybrid DISABLED (PG2)
fill B-main (C-side) with 40 psi D2 Hybrid enabled (PG3)
NINJA pumped out disabled

Enable the following gate valves and shutters: ECE, VUV, Z-bolo shutters

Torvac setup: Gate valves open during pulse.

-------------------------------------------------------------------------------
ICRF Setup: None

LH Setup: Can be turned on if we regain reliable plasma operation

-------------------------------------------------------------------------------
Run plan: Start from 1070322001 and resume plasma operation

Session Leader Summaries
Entered: Mar 28 2007 08:09:20:810AM
Author: Steve Wolfe
Session leader summary for Tuesday, March 27, 2007

MP#298a C-Mod startup
SL: wolfe
PO: irby
EO: the Bills (Cochran, Byford, Parkin)

The run got off to a very late start, mostly due to data system problems
but also because we were agonizing about the OH mis-control event last
Thursday (1070322012). Dave Gwinn feels we should look into taking 
additional precautions to avoid a recurrence. Before taking any plasma
shots we ran several cycle tests and power tests with PLC control on the OH's
to convince ourselves that the new sparker arrangement was not generating
similar noise problems. We also discussed possible additional hardware and
software safeguards to be implemented ASAP. 

The first plasma shot was #11, taken around 1:30PM. This was a short, 
marfing, disruptive shot, not unlike 1070321001. It also produced a
change in the sparker current , so we took another test shot to be sure
things hadn't gone bad again. Shot #13 was a good full length LSN plasma, 
which actually called for some gas in flattop. 

We therefore went on to limited plasmas, continuing the program from last
Thursday in an effort to clean/degas the inner wall. We ran ran several 
different settings of clearin, mostly staying marginally limited with
some sharing to the lower divertor. The nl04 remained above 8e19, with
no demand on the pg3 puff in flattop. We got ten plasmas under these 
conditions, all but one full length. Shot #17 disrupted with an injection,
and the following shot fizzled. 

All things considered, a reasonably good run. Plasmas were reproducibly
obtained, though the runaways could use some taming. The new sparker 
configuration seems to be working, with small but noticeable noise 
prodced when it arcs. The dozen total plasmas, 20sec total duration, 
should help with the cleanup. H/D is still high, 0.5

Physics Operator Summaries
Entered: Mar 27 2007 06:33:29:883PM
Author: Jim Irby
A new sparker (type I) was installed on B-Hor last night along with a
new cable. It performed well all day with about 180 uA of current at
t=0. Break-down time was very reliable, staying close to 5 ms all
day. The only adjustment "required" to startup today was a 10 Amp
drop in EF4 to bring down Bz0 following the disruption on shot 17 and
the fizzle on shot 18.

Generally the machine ran extremely well all day. The first plasma
was obtained on shot 11 lasting about 300 ms, which was followed by a
fizzle on shot 12.

The lower hybrid system was running into dummy loads early in the
C-Mod shot cycle at about 1.5 MW.


score
-----

tests and data system issues 1-10

plasmas 11,13,14,15,16,17,19,20,21,22,23,24
fizzles 12,18
disruptions 11,17


Problems
--------

The data system took much of the morning to be brought back into
operation. However, it appears that the upgrade has greatly improved
the speed of the data acquisition system. Initialization seems much
faster and well as data retrival (about 1.3 Gbytes of data/shot thus
far)

We took several no power shots today to verify that there was no noise
issue from the sparker on the Rogowski signals. We also took a couple
of OH only shots. No problems were found during these tests.
However, we did see glitches on the magnetics probably associated
with sparker tickdowns (typically one sample according to SMW).

TCI, particularly nl04, has some +-4e18/m^2 glitches generated when the CO2 counters are toggling between counts. I am not at this point sure why these glitches are showing up, but will investigate.

Session Leader Comments
Mar 27 2007 12:12:46:930PM1070327006Steve Wolfe
Shot#6: Another data cycle test. 
I'm not getting updates on new scopes. Have to actually
blow them away and bring up new ones, not just load saved 
settings from. 

Data all seems to be there. Granetz is complaining the beam
did not go, but beam data did. 



Mar 27 2007 12:29:42:913PM1070327007Steve Wolfe
Shot#7: Data system is supposedly fixed (We've heard this
before). 
Do an oh 10kA PLC test. 
Breaker pulled before PULSE. 
No excitation on Alternator. 

Try again 



Mar 27 2007 12:50:57:960PM1070327008Steve Wolfe
Shot#8: Try again for 10kA oh PLC test. 

Rog signals are fine, no magnetics errors. 
Actually, the bus rogs look a little noisy. 
Looks like a little bit of 60Hz.
It turns out this was under dpcs control, with a 
plc current limit of 10kA. 


Mar 27 2007 01:04:36:523PM1070327009Steve Wolfe
Shot#9: Try again for 10kA oh PLC test. 

This time it was as planned. 
Looks ok


Mar 27 2007 01:14:27:760PM1070327010Steve Wolfe
Shot#10: Try for plasma. 
Consider backing off the plc reverse current limit from 
26/27kA to 20kA, but decide not to. 

Run a no power, the pcs shot for today was never loaded into 
model. 



Mar 27 2007 01:37:09:727PM1070327011Steve Wolfe
Shot#11: Another try at plasma.
Short plasma, to .29sec, marfing and runaways. 
Strange spike on magnetics at .018sec
f11 has a baseline offset, otherwise just a little spike on
several loops and on Btor. Is it important? 
The spike at .018 is coincident with a sparker arc. 
There is also a sparker arc around -.0127, which does not
seem to line up with additional noise on the magnetics
at -.025 and -.011 (as seen at the dpcs inputs). 



Mar 27 2007 02:03:21:133PM1070327012Steve Wolfe
Shot#12: Sparker test before this shot gave low current,
no increase to >300uA at -.5sec, and a few large arcs. 
Do another OH PLC test like shot 9, just for the sake of caution. 

Rogowski signals look  ok, no glitches on magnetics at dpcs.
Sparker went to 200uA, may be responding to gas puff. 
 


Mar 27 2007 02:17:36:010PM1070327013Steve Wolfe
Shot#13: Another plasma try
plasma full length
startup is ugly, bounced once on outside. 
Lots of runaways. Lots of injections on 2pi diode.
nl04=6e19, puffing a little gas on pg3. 

Next: try for marginally limited plasma
 


Mar 27 2007 02:36:37:120PM1070327014Steve Wolfe
Shot#14:  try for marginally limited plasma
Looks like we got it. EFIT claims 3mm inner gap.
NL04 is a little higher and the gas is off.
Wide2 view shows a clear stripe in the inner wall,
despite EFIT claiming it's still diverted. Jant
view does look like there is a lot of flux to the divertor. 
(Auto update not working, may need to restart something
after all the aborts this morning). 
Loop voltage is up about 100mV. 

Next: move it in some more. 
 


Mar 27 2007 02:48:43:680PM1070327015Steve Wolfe
Shot#15:  try for  limited plasma
plasma full length
Density up to 9e19, EFIT claims left gap zero this time. 
Small bounce on startup, hards are still bad. 

One big arc on sparker at -.95 sec. No pickup on bus rogs;
or on magnetics. 

Mar 27 2007 02:59:07:210PM1070327016Steve Wolfe
Shot#16:  Repeat. Startup a little better, fewer hards.
NL04 about 9e19 again. 

F11 is the only complainer on the magnetics. 

Keep doing this for a few 

Mar 27 2007 03:11:40:120PM1070327017Steve Wolfe
Shot#17:  Another short shot
Injection at 0.61sec. 


Mar 27 2007 03:17:52:807PM1070327017Steve Wolfe

A possible candidate for an upper null is
1060620013, segment 4, which is 800kA USN
with an early (1.0sec) Ip rampdown. Everything else
appears to be flat until 1.5sec, so it should be
possible just to extend it. Has a He3 puff (PG2)
 But not this shot. 



Mar 27 2007 03:25:05:773PM1070327018Steve Wolfe
Shot#18: repeat (without the injection, hopefully)
fizzle. CIII level is way up, then an additional jump
at 16msec. Disruption effect, I guess. 
Jim thinks Bz was up a mT. 



Mar 27 2007 03:38:59:743PM1070327019Steve Wolfe
Shot#19: Jim tweaking startup. 
plasma full length
Nl04 down to 8e19, Vloop~1.3V, no pg3 in flattop
Startup better, sparker down to 150uA at t=0

next: repeat, but with gate valves closed in pulse.


Mar 27 2007 04:04:14:460PM1070327020Steve Wolfe
Shot#20: plasma full length
nl04 has  fringe jumps. 
Lots of runaways this time. nl04 back up near 9e19 again. 
Closing the gate valves had no noticeable effect on startup.

Mar 27 2007 04:19:46:133PM1070327021Steve Wolfe
Shot#21: repeat (gate valves back open). 
plasma full length. 
nl04 still jumping; Jim says HeNe #3. 
Startup has early bounces or injections; lots of runaways. 

Tweak the early gas a little to see if the density comes down
any more. 

Mar 27 2007 04:39:54:477PM1070327022Steve Wolfe
Shot#22: Tweak the early gas a little to see if the density comes down
any more. 
plasma full length. 
runaways are down, survived a huge injection at 1.11sec (halpha
and nl4, not much on bolo or current). 

Arc on sparker shows up on dpcs magnetics around -.285sec (spike on 
zcur at -.285sec, one sample at 100usec). 

Mar 27 2007 04:54:05:523PM1070327022Steve Wolfe
Shot#22: There may be timing issues on some channels on 
this shot: The bolo perturbation from the injection seems
to lead the halpha rise and the density rise by over 10msec.
So does the current perturbation. GPC coincides with Halpha.


Mar 27 2007 04:53:37:320PM1070327023Steve Wolfe
Shot#23: plasma, a few more hards. 
nl04 down a little, but still well over programmed value;
not degassing the wall very well. 

For the last shot, go another 5mm on clearin, make it 
more limited. 


Mar 27 2007 05:19:04:383PM1070327024Steve Wolfe
Shot#24: plasma full length. 
Hard xrays are back down again
NL04 flat at 8.7e19. Vloop~1.45Volts
Looks a little more limited, dsep=-0.3cm

END OF RUN


Physics Operator Comments
Mar 27 2007 09:02:59:337AM1070327001Jim IrbyLoaded 1070322001 into DPCS: Normal gap SLN at 800 kA
Density request: 6e19/m^2 on NL04
prepuff 20 mS gate

This shot is a cycle test

gas okay

Rogowskis okay


Mar 27 2007 09:15:02:777AM1070327002Jim IrbyWe were not getting updates on the last shot. Josh is restarting the cycle.

Took shot too early; Josh was not done...
Mar 27 2007 11:35:24:603AM1070327004Jim Irbycontinuing data system tests

not good
Mar 27 2007 11:39:59:587AM1070327005Jim Irbydata system still broken --- aborting everything with bits
Mar 27 2007 12:00:42:993PM1070327005Jim IrbyAnother data system cycle test

We have some data


Mar 27 2007 12:08:10:057PM1070327006Jim IrbyJosh and Tom seemed happy with last shot

Try one more time

looks okay


Mar 27 2007 12:33:50:133PM1070327007Jim IrbyWill do OH test: 10 kA in OH1, OH2U, OH2L, no commutation
This test will verify proper operation of integrators

OP error, no power shot again. Data system still okay
Mar 27 2007 12:55:48:633PM1070327008Jim IrbyTry again ---

We got current: 10kA in all OHs

Looks like we had hybrid control with PLC limits

OH2U coax voltage measurement following current pulse noisy
Mar 27 2007 01:07:19:400PM1070327009Jim IrbyTry again under PLC control this time

Looks good

cell access for DNB


Mar 27 2007 01:17:12:120PM1070327010Jim IrbyTry for plasma

One more no power test --- PO "load from" shot 1070322001, but forgot to do a "load" --- may have been okay, but....


Mar 27 2007 01:46:57:667PM1070327011Jim IrbyTry again for plasma

plasma for 300 mS

starup looks good

ciii levels about 1/2 of those on 1070322001

pickup, probably from sparker, on magnetics


Mar 27 2007 02:03:43:650PM1070327012Jim IrbyRepeat shot 9, oh test to make sure sparker has not affected magnetics

test shots of sparker indicate lower current (< 50 uA, except during tickdowns)

dropped PG3 in seg 1 and seg 2

Rogs look good.

No tickdowns on sparker


Mar 27 2007 02:24:58:320PM1070327013Jim IrbyTry for plasma

sparker on at -1.9 for 1.920 s

plasma into rampdown

sparker looks good --- responds to gas and plasma

H/H+D 25%

Mar 27 2007 02:39:08:260PM1070327014Jim IrbyPlasma to wall:
clearin from 0.00 to -0.01 cm
rcur from 0.661 to 0.656 m

plasma into rampdown

sparker looks good --- overlay of shot 13

still 2 or 3 mm off wall
Mar 27 2007 02:55:17:587PM1070327015Jim Irbyclearin reduced by 0.5 cm
rcur reduced by 0.25 cm

impurity levels (RGA) still high from last shot --- BP at check 1.4e-6 Torr

plasma into rampdown

zero gap

sparker arc at -0.95 s does not show up elsewhere


Mar 27 2007 03:06:26:150PM1070327016Jim IrbyRepeat

plasma into rampdown


Mar 27 2007 03:19:23:180PM1070327017Jim Irbyrepeat

injection starting abt 0.5761 s
Mar 27 2007 03:29:59:697PM1070327018Jim Irbyrepeat (w/o injection)

fizzle

sparker okay

ciii up a factor of two relative to shot 17
Bz0 about 1 mT higher than shot 17 at 5 ms


Mar 27 2007 03:44:13:697PM1070327019Jim IrbyEF4 from -1345 to -1355 A

plasma into rampdown

1 MW of LH power into dummy loads during C-Mod cycle

2Pi around 0.4 MW w/o any large injections


Mar 27 2007 04:02:18:557PM1070327020Jim Irbyrepeat DCPS

have asked for gatevalve toggle remaining closed for 25 s

plasma into rampdown

1.5 MW early spike on 2Pi

gatevalves toggle worked --- basepressure at t=0 up from .044 to .050 mTorr, but no effect on startup

ciii light continues to decrease

h/h+d 37%


Mar 27 2007 04:27:03:227PM1070327021Jim Irbyrepeat of DCPS

D-Right vertical TF TC is taking 19 minutes in RECOOL to reach -162C

plasma into rampdown

ciii down a little, but early injections or waggles

density is not dropping very much shot to shot
Mar 27 2007 04:45:47:727PM1070327022Jim Irbyreduced pg3 gas in seg 1 and turned it off in seg 2

ciii continues to fall shot to shot

sparker tickdown seen on magnetics (-0.28 s)

large injection of something at about 1.08 s --- density, halpa, z-meter, 2pi, pressure rise.


Mar 27 2007 04:58:28:070PM1070327023Jim Irby13:42 minutes in recool to get to -160C (pump has been at 8 psi all day)

repeat DCPS

plasma into rampdown



Mar 27 2007 05:15:06:307PM1070327024Jim Irbyclearin reduced by 0.5 cm
rcur reduced by 0.25 cm

plasma into rampdown


Engineering Operator Comments
ShotTimeTypeStatusComment
108:52:12:760AMTestOkShot cycle test
209:11:23:120AMTestBad
410:50:33:087AMTestBadack failure
511:37:51:620AMTestOk
612:04:56:150PMTestOk
712:27:12:947PMTestOk
812:37:20:273PMTestOkOH PLC Test
912:55:12:430PMTestOkOH PLC Test
1001:12:06:960PMPlasmaOk
1101:22:10:993PMPlasmaOk
1201:56:34:120PMTestOkOH and Gas
1302:09:15:960PMPlasmaOk
1402:26:56:167PMPlasmaOk
1502:40:31:320PMPlasmaOk
1602:53:14:337PMPlasmaOk
1703:06:51:900PMPlasmaOk
1803:20:15:197PMPlasmaOk
1903:33:05:103PMPlasmaOk
2003:51:37:417PMPlasmaOk
2104:14:00:273PMPlasmaOk
2204:30:24:260PMPlasmaOk
2304:46:28:807PMPlasmaOk
2405:02:10:070PMPlasmaOk

System Availability
Mar 27 2007 08:50:03:853AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDno Feb 05 2007 04:33PM (twf)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEnoOnly channel 17-32 available until after power test - connection problem on lower channels - ch 10 bad filter (off scale) - will check next chance.Mar 22 2007 10:52AM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. But, intermittent problems with preamps causing noise and drifts.Mar 23 2007 08:37AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,78,10,17) operational and calibrated. Fast signals not yet connected.Mar 22 2007 09:47AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPInoNot available 3/1-3/6Jan 23 2007 02:24PM (g)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPIno Jan 14 2007 02:03PM Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometerreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, DANT are operational; JANT and DIV (without an ND filter) are being debugged. WIDE2 has not yet been inserted into its re-entrant tube.Mar 16 2007 09:38AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes


Mar 27 2007 01:56:21:823PM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDno Feb 05 2007 04:33PM (twf)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEnoOnly channel 17-32 available until after power test - connection problem on lower channels - ch 10 bad filter (off scale) - will check next chance.Mar 22 2007 10:52AM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. But, intermittent problems with preamps causing noise and drifts.Mar 23 2007 08:37AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,78,10,17) operational and calibrated. Fast signals not yet connected.Mar 22 2007 09:47AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPInoNot available 3/1-3/6Jan 23 2007 02:24PM (g)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPIno Jan 14 2007 02:03PM Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometermlreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV (without an ND filter) are operational.Mar 27 2007 01:53PM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes


Mar 27 2007 02:09:04:197PM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDno Feb 05 2007 04:33PM (twf)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEnoOnly channel 17-32 available until after power test - connection problem on lower channels - ch 10 bad filter (off scale) - will check next chance.Mar 22 2007 10:52AM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. But, intermittent problems with preamps causing noise and drifts.Mar 23 2007 08:37AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,78,10,17) operational and calibrated. Fast signals not yet connected.Mar 22 2007 09:47AM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPIyesNew view just outside of the lower X-point is operational, but data is being archived locally , not to the tree. Midplane GPI is not operational.Mar 27 2007 01:59PM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPIno Jan 14 2007 02:03PM Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometermlreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV (without an ND filter) are operational.Mar 27 2007 01:53PM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes


Mar 27 2007 03:20:02:947PM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDno Feb 05 2007 04:33PM (twf)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEnoOnly channel 17-32 available until after power test - connection problem on lower channels - ch 10 bad filter (off scale) - will check next chance.Mar 22 2007 10:52AM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. Mar 27 2007 03:12PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,78,10,17) operational , but amplitudes low today for unknown reason.Mar 27 2007 03:13PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPIyesNew view just outside of the lower X-point is operational, but data is being archived locally , not to the tree. Midplane GPI is not operational.Mar 27 2007 01:59PM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPIno Jan 14 2007 02:03PM Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometermlreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV (without an ND filter) are operational.Mar 27 2007 01:53PM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes


Mar 27 2007 03:51:25:930PM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDno Feb 05 2007 04:33PM (twf)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEyesOnly channel 17-32 available (other channels will be added shortly) - ch 10 bad filter (off scale)Mar 27 2007 03:34PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. Mar 27 2007 03:12PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,8,10,17) operational , but amplitudes low today for unknown reason.Mar 27 2007 03:36PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPIyesNew view just outside of the lower X-point is operational, but data is being archived locally , not to the tree. Midplane GPI is not operational.Mar 27 2007 01:59PM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPIno Jan 14 2007 02:03PM Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometermlreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV (without an ND filter) are operational.Mar 27 2007 01:53PM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes


Mar 27 2007 04:46:17:023PM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDyesFully operationalMar 27 2007 04:35PM (snipes)Joe SnipesActive MHD Antennasears,snipes
BESyesvertical array of six views at R ~ 87.3 cm, radial array of three views out to R ~ 89 cm, both at outboard midplane. Three discrete fiber views of beam at R ~ 70.0, 76.5 and 82.5 cm.Feb 06 2007 10:00AM (bravenec)Ron BravenecBeam Emission Spectroscopybravenec
Bolometersno2Pi should be ready, but need plasma to confirm. Preparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 19 2007 01:59PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
Boronizationno Jan 14 2007 01:47PM Jim IrbyBoronizationdekow,irby
CNPAno Jan 14 2007 02:06PM Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoIn-vessel hardware is installed; in-vessel cryogenic systems are leak-tight. Work is proceeding on external LHe and LN2 transfer lines as well as PLC control system. We will do the first LN2 cool-down tests manually.Mar 13 2007 09:55PM (labombard)Brian LaBombardUpper Divertor Cryopumpirby,labombard
CXRSnoThe pedestal toroidal array was installed, spatially and absolutely calibrated. There are 10 chords intersects the beam at the range major_R=[75,4:87.4]cm. Spatial resolution: 1.2 cm. The F-top poloidal array was installed and spatially calibrated. There are 19 chords intersects the beam at the range major_R=[67.8:91.0]cm. Spacial resolution: 1.22 cm.Mar 06 2007 08:09PM (rowan)Bill RowanCharge Exchange Spectroscopybespam,blip,rachmcd,rowan
D Alphayes\ha2_bright and \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 are availableMar 11 2007 10:28PM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsayescamera is re-installed, and view has been calibratedFeb 26 2007 03:28PM (marmar)Earl MarmarVisible Bremsstrahlungmarmar
Disruption Mitigationno Jan 14 2007 02:02PM Bob GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,ldorf,terry
DNBno Jan 14 2007 01:46PM Bob GranetzDiagnostic Beambeals,granetz
FRC-ECEyesOnly channel 17-32 available (other channels will be added shortly) - ch 10 bad filter (off scale)Mar 27 2007 03:34PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsphillips
G-Side RatiomaticyesThe gauge is operational. Cross-calibration with G-Side MKS gauge is needed. Mar 13 2007 10:02PM (labombard)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
GPCyesChs 3-8 operational, cross-calibrated. Mar 27 2007 03:12PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPC2yesMost slow channels (except 1,8,10,17) operational , but amplitudes low today for unknown reason.Mar 27 2007 03:36PM (hubbard)Amanda HubbardECE Polychromaterhubbard,schmidt
GPIyesNew view just outside of the lower X-point is operational, but data is being archived locally , not to the tree. Midplane GPI is not operational.Mar 27 2007 01:59PM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyesspectral calibration needs to be checked, but system should be ready for the runFeb 26 2007 03:28PM (marmar)Earl MarmarH/D Ratiomarmar
Hirex IIIno Jan 14 2007 01:53PM John RiceHigh Resolution X-Rayince,rice
Hirex Jryes Mar 06 2007 08:59AM (rice)John RiceHigh Resolution X-Rayince,rice
HXRyesSomething might be wrong with channel 26; all others working fine.Mar 23 2007 10:43AM (schmidt)Ron ParkerHard X-Ray Arrayparker,schmidt
ICRF D-Antennano80.5 MHz. Transmitter ready. A little more work on the coaxial line.Mar 26 2007 03:18PM (ylin)Steve WukitchD-port antennawukitch,ylin
ICRF E-Antennano80 MHz. FFT installation/coaxial line needs more workMar 16 2007 09:32AM (ylin)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanoNeed to tune from 70 to 78 MHz. Loop not finished.Mar 16 2007 09:31AM (ylin)Steve WukitchJ-port antennawukitch,ylin
Lower HybridnoAvailable after 3/20Jan 23 2007 02:24PM (g)Ron ParkerLower Hybriddterry,parker
LPInoavailable by 4/2Mar 27 2007 04:44PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoPreparing external amplifiers and DAQ. Midplane ready soon after first plasma, 2D ready by start of science runs.Mar 06 2007 01:09PM (mlreinke)Matt ReinkeLyman alpha cameraslabombard,mlreinke
McPhersonnowill check out system on shots with plasmaMar 11 2007 10:36PM (terry)Jim TerryVUV Spectrometermlreinke,terry
MichelsonyesOperational. Occasional DAQ failures, not understood. Speed increased 3/22.Mar 22 2007 12:04PM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyesE-Top, E-Bottom, F-top (cryo), G-side, and B-bottom are operational. F-top gauge has a 'sniffer tube' to measure pressures in cryopump gas box.Mar 20 2007 06:42PM (g)Brian LaBombardBaratron pressure gaugeslabombard
MLPnoBench tests are proceeding on a prototype MLP system. We hope to roll the system into the cell for testing in a few weeks, powering up a single electrode on the A-port scanning probe.Mar 13 2007 09:57PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEno Jan 23 2007 02:24PM (g)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesCalibrated detectors are positioned correctly; Voltage is on on the He3 bank; Remaining voltages will be turned on when plasma attempts startMar 13 2007 08:23AM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesoperationalMar 21 2007 04:29PM (irby)Jim IrbyX-Ray/Neutron Detector at K-Horirby
NINJAyesAll capillaries displayed by the NINJA_CONTROL GUI have been tested. The gas plenum needs to be purged.Mar 12 2007 10:08PM (labombard)Brian LaBombardNINJA gas pufflabombard,terry
PCIno Jan 14 2007 02:03PM Miklos PorkolabPhase Contrast Imagingedlund,lianglin,ntsujii,porkolab
Penning Gaugesyes8 in-situ Penning ionization gauges appear to be operational: CB_DivU, CB_OutL, CB_DivL, KA_OutU, KA_OutL, B_DivL, Cryo_1, Cryo_2. Cryo_1 and Cryo_2 are new and installed in the upper cryopump 'gas-box'.Mar 13 2007 10:01PM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV (without an ND filter) are operational.Mar 27 2007 01:53PM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoRetro shutter closedMar 15 2007 11:00AM (irby)Jim IrbyC-Mod Polarimeterirby
Probe Array - ISDyesProbes at 15 of the 16 poloidal locations ('ramped' geometry) are operational. n,Te, particle flux reported every 10 ms.Mar 13 2007 09:47PM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesAll 6 probes on the lower hybrid launcher (tungsten, 1.5 mm projection) are operational. Mar 13 2007 09:46PM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesProbes at 10 poloidal locations (one 'ramped' and one 'flush') are operational. n,Te, particle flux reported every 10 ms. Mar 13 2007 09:45PM (labombard)Brian LaBombardOuter Lower Divertor Probe Arraylabombard
Probe Array - UDIVyes14 probes are operational ('ramped' geometry). n,Te, particle flux reported every 10 ms.Two high-gain channels are installed and operational for ECDC plasma diagnosis.Mar 13 2007 12:46PM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
Reflectometerno Mar 05 2007 05:34PM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesPerpendicular Mach probe head is installed. The drive is operational.Mar 15 2007 09:09PM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesPerpendicular Mach probe head is installed. The probe drive is now operational.Mar 13 2007 09:51PM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoA-port and K-port WASPs were sucessfully scanned during recent TF only shots. A bit more control software needs to be written...Mar 15 2007 09:11PM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
TCIyesNL04 at 71.04 cm from 3/9/07 calibrationMar 09 2007 05:47PM (irby)Jim IrbyTwo-Color Interferometer (TCI)irby,murray
TS - CorenoLasers are aligned. Polychromators being reinstalled. Resolving issues with HVPS. Expect some channels available by Mar. 30. Mar 26 2007 08:29AM (jwhughes)Jerry HughesThomson Scattering - Corejwhughes
TS - EdgenoReplacement filter has been reinstalled. Bench recalibration needed. Should be ready sometime during the week of April 2. Mar 26 2007 08:31AM (jwhughes)Jerry HughesThomson Scattering - Edgejwhughes