Alcator C-Mod Run 1111209 Information

Back to runs

Miniproposals
Miniproposal:669
Date Filed:10/17/2011
Title:Rotated Antenna Commissioning and Initial Characterization
First Author:Steve Wukitch
Session Leader:Steve Wukitch (shots 1-14)

Operators
Session leader(s):Steve Wukitch
Physics operator(s):Ron Parker
Engineering operator(s):Bill Cochran,Bill Parkin

Engineering Operator Run Comment
MP355C ICRF Testing and Conditioning MP669 Rotated Antenna Commissioning

Session Leader Plans
Entered: Dec 8 2011 10:26:29:303PM
Author: Steve Wukitch
Run Plan

Use vanilla 5.4 T, 0.8 MA discharges to condition D/E and J antennas. Initial discharges will be used to raise J power and explore J voltage limit in L-mode plasmas. LH-SOL reflectometer will require cell accesses to insert it to reasonable position. GPI will also be utilized to measure SOL turbulence changes with RF.

We will also use a few discharges to explore D/E/J neutral pressure limit.

If time permits, we will examine voltage limit, impact on SOL density profile, and gpi at monopole phasing.

Physics Operators Plans
Entered: Dec 8 2011 12:08:02:637PM
Author: Ron Parker
====================================
Physop Plan for Friday, 9-Dec-2011
====================================
MP355C ICRF Testing and Conditioning
MP669 Rotated Antenna Commissioning and Initial Characterization

SL: Wukitch
PO: Parker

-----------------
Engineering Setup
-----------------

Run begins at 9:00 and ends at 17:00

Power systems as on: 1111206034

Acoil: +Dtop -Dbot -Jtop +Jbot (standard) Hybrid Enabled

Gas setup:
----------
Fill B-Top with 6 psi D2 Hybrid enabled (PG4)
Fill B-side lower with 1 psi Ar Hybrid DISABLED (PG1)
Leave B-side upper as is Hybrid DISABLED (PG2)
fill B-main (C-side) with 40 psi D2 Hybrid enabled (PG3)
Fill H-bot with 15psi D2 Hybrid DISABLED (PG5)
DO NOT fill B-div, Hybrid DISABLED (PG6)
DO NOT fill H-div, Hybrid DISABLED (PG7)
fill NINJA with 10 psi Ne DISABLED

Gate-valves and shutters: Enable ECE, HiREX Sr, B spectrometer (Xeus and LoWEUS)
Z-bolo shutter should be closed unless requested by physop

Check with the physop before opening other diagnostic gate-valves or shutters.

Torvac gatevalve toggle (yes/no): no

Boronization(yes/no): no
Overnight ECDC (yes/no): YES
ICRF(yes/no): yes - all transmitters
LH(yes/no): no
Cryopump (yes/no): no
DNB (yes/no): no

Vessel temperature: 35/35/35

------------------------------
ECDC Parameters
------------------------------
gas and pressure: D2 at 2e-4 Torr
sweep: 44/45/103 cm
scan: 20/120 s

====================================
Physics Operator Plans:

Use the startup (segment 1) from yesterday and segment two from
Tuesday (1111206034, 800 kA, nl_04=8e19).

Assuming plasmas are reasonably reproducible, we will add a bit of
ICRF from D, E, and J antennas to assess J antenna's voltage and
neutral density limit, see Session leader plan for details.
====================================

Session Leader Summaries
Entered: Dec 10 2011 09:19:24:390AM
Author: Steve Wukitch
Run Summary

The run started out well. Vanilla 5.4 T, 0.8 MA plasmas were established on the first discharge and matches were quickly found for D and J antennas. J antenna reached 2 MW with faulting and dithering H-modes were complicating the matching and operations. We briefly switched to USN using 1110323032 but ran into disruption issues so we switched back to LSN with lower density to avoid H-mode. Unfortunately, the J antenna began to fault and the transmission line network, particularly the loops, appeared to malfunction. The power split between the antenna straps became asymmetric. Upon inspection, the decoupling appeared to have become particularly poor. We made measurements of the individual straps and found that strap three appears to be significantly different while the other three look identical. These measurements suggest a short somewhere in the circuit other than intended. We will need to keep removing coax until we can identify if the issue is on the air or vacuum side.

Physics Operator Summaries
Entered: Dec 9 2011 02:02:36:727PM
Author: Ron Parker
The run started promptly at 9:00 and the first 5 shots ran full length with programmed conditions. The startup for these shots, as well as those that followed, was excellent (although the preprpogrammed gas pulse was on for only 15 ms.) These shots were all standard LSN with I_p = 800 kA, B_T = 5.4 T amd nL_04 = 8e20.

After shot 5 we switched to USN to avoid dithering H-Modes. There then followed a sequence of alternating disruptions and fizzles. The upper strike point apparently needs to be "worked in", probably starting with Ohmic shots. However, it was decided after shot 12 to revert to LSN shots by reloading shot 5 of this run at somewhat lower density (0.6 vs 0.8e20). Shots 13 and 14 ran full length with this programming. Unfortunately the J-port antenna stopped working and after ~ 1 hour of troubleshooting it was concluded that it would not be possible to fix J-port in time to resume the run, so the run was scrubbed after shot 14.

Scorecard: 14 plasma attempts, 7 full length, 4 disruptions and 3 post-disruption fizzles

Session Leader Comments
Dec 9 2011 09:14:43:173AM1111209001Steve Wukitch001 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz

result: plasma full length
lots of faults from all
few H-modes - may need to avoid these

next: repeat - different match point for J3 - try to get away from
lambda/2 position on the stub tuner

gpi He puff ~1.1 s

Dec 9 2011 09:37:43:203AM1111209002Steve Wukitch002 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz

result: plasma full length
lots of faults from all
few H-modes - may need to avoid these

next:
push LH launcher in ~1 cm (about 7 mm behind for LH-SOL reflectometer (cell access)
enable Ar
J3 match is off - not too bad since we made a big change
repeat

Dec 9 2011 09:47:38:457AM1111209003Steve Wukitch003 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz

result: plasma full length - dithering
lots of faults from all but J ran to 1.5 MW for short pulses
H/H+D is down below 20% so we see a bit of heating

next: raise J power and repeat
Dec 9 2011 09:58:41:840AM1111209004Steve Wukitch004 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 0.75 MW, 78.0 MHz

result: plasma full length - dithering
D/E are cleaning up nicely
J ran to 2 MW for short pulses
faulting appears to be arcing on J4 in particular

next: repeat
Dec 9 2011 10:21:41:907AM1111209005Steve Wukitch005 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz

result: plasma full length - dithering still
D/E are cleaning up nicely
J not as good as previous
faulting appears to be arcing is on both J3 and J4

next: switch to USN to avoid dithering
load segment 2 from 1110323032 - needed to make Ip change and zero pulse gas 5
Dec 9 2011 10:35:42:453AM1111209006Steve Wukitch006 demand:
5.4 T, 0.8 MA, nl04~0.8
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz

result: plasma - disruption
short J pulse prior to disruption
reflectometer data is better with USN

next: post disruption fizzle?
Dec 9 2011 10:56:59:410AM1111209007Steve Wukitchfizzle

Dec 9 2011 11:02:47:483AM1111209008Steve Wukitch008
5.4 T, 0.8 MA, nl04~0.8, USN
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz

result: plasma - disruption ~1.05
J still struggling

next: post disruption fizzle?

Dec 9 2011 11:18:21:990AM1111209009Steve Wukitchfizzle
Dec 9 2011 11:32:30:320AM1111209010Steve Wukitch010
5.4 T, 0.8 MA, nl04~0.8, USN
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz

result: plasma - disruption ~1.0s
J tuning off

next: post disruption fizzle?

Dec 9 2011 12:11:38:800PM1111209011Steve Wukitchfizzle
Dec 9 2011 12:11:29:513PM1111209012Steve Wukitch012
5.4 T, 0.8 MA, nl04~0.8, USN
D : t = [1.25, 1.60] sec, 0.50 to 1.40 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.40 MW, 80.0 MHz
J3: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz
J4: t = [0.50, 0.90] sec, 0.25 to 1 MW, 78.0 MHz

result: plasma - disruption ~1.0s
something is off on J

next: post disruption fizzle?

Dec 9 2011 12:29:06:007PM1111209013Steve Wukitch013
5.4 T, 0.8 MA, nl04~0.6, LSN
D : t = [1.25, 1.60] sec, 0.50 to 1.00 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.00 MW, 80.0 MHz
J3: t = [0.55, 0.62] sec, 0.10 to 0.15 MW, 78.0 MHz
J4: t = [0.55, 0.60] sec, 0.10 to 0.15 MW, 78.0 MHz

result: plasma full length
something is off on J3

next: repeat
Dec 9 2011 12:31:15:643PM1111209014Steve Wukitch013
5.4 T, 0.8 MA, nl04~0.6, LSN
D : t = [1.25, 1.60] sec, 0.50 to 1.00 MW, 80.5 MHz
E : t = [0.90, 1.25] sec, 0.50 to 1.00 MW, 80.0 MHz
J3: t = [0.55, 0.62] sec, 0.10 to 0.15 MW, 78.0 MHz
J4: t = [0.55, 0.60] sec, 0.10 to 0.15 MW, 78.0 MHz

result: plasma full length
something is off on J3

next: delay to investigate J3 - likely on hold for an hour
Dec 9 2011 01:36:39:430PM1111209014Steve Wukitchend of run

Something in the J antenna has broken.

Physics Operator Comments
Dec 9 2011 08:50:59:077AM1111209001Ron ParkerGood morning. All systems ready, first shot coming up at 9:00.
Dec 9 2011 09:10:46:823AM1111209001Ron ParkerFirst shot looked good. No PCS changes for next shot.
Dec 9 2011 09:25:09:173AM1111209002Ron ParkerSlight delay due to switching gas in NINJA from Ne to He.

Also, we'll inject Ar on next shot
Dec 9 2011 09:28:12:567AM1111209002Ron ParkerShot 2 ran full length. So far, so good.

No PCS changes for next shot.
Dec 9 2011 09:50:48:003AM1111209003Ron ParkerShot 3 ran full length. No PCS changes for nest shot.

Breakdown is good, but H_alpha peak is growing -- from 0.6 on shot 1 to 0.8 on shot 3
Dec 9 2011 09:56:54:643AM1111209004Ron ParkerFull length, no PCS changes for next shot.
Dec 9 2011 10:26:56:617AM1111209005Ron ParkerShot 5 ran full length.

Next: switch to upper null, using 1110323032 seg 2, with density increased to 8e19 (nl_04).
Dec 9 2011 10:33:20:850AM1111209006Ron ParkerShot 6, SNU, disrupted.

Repeat, but 2 ms taken off prefill (from 15 to 13 ms)

H_alpha on shot 6 peaked at 0.9 after breakdown.
Dec 9 2011 10:44:21:763AM1111209007Ron ParkerShot 7 was the expected fizzle-following-disruption shot
Dec 9 2011 11:08:01:237AM1111209008Ron ParkerShot 8 disrupted at 1.05 s, longer than shot 6 which disrupted at 0.85 s.

Expect another fizzle-following-disruption for the next shot, shot 9.

Upper strike point seems to be moving toward teh corner, so we'll move RXL out 1.5 cm at 1 s
Dec 9 2011 11:19:11:087AM1111209009Ron ParkerFizzle, as expected.
Dec 9 2011 11:38:49:733AM1111209010Ron ParkerAnother disruption, this time at ~ 1 s.

You know what to expect next,
Dec 9 2011 12:00:16:013PM1111209011Ron ParkerAnother fizzle-following-disruption shot
Dec 9 2011 11:59:22:200AM1111209012Ron ParkerAnother disruption, we're not making any progress.

So, after the next fizzle-following-disruption shot, we'll go back to shot 5 with nL_04 = 0.6e20.
Dec 9 2011 12:32:50:843PM1111209013Ron ParkerShot 13 actually ran full length (in spite of the expected fizzle-following-disruption).

No change for next shot.
Dec 9 2011 01:43:24:653PM1111209014Ron ParkerShot 14 ran full length.

Something is wrong with J antenna. Steve will troubleshoot but this means a likely delay of an hour.

Engineering Operator Comments
ShotTimeTypeStatusComment
109:01:58:083AMPlasmaOk
209:22:21:650AMPlasmaOk
309:37:23:480AMPlasmaOk
409:52:04:657AMPlasmaOk
510:06:31:313AMPlasmaOk
610:25:59:167AMPlasmaOk
710:41:08:860AMPlasmaOk
810:54:26:423AMPlasmaOk
911:15:57:967AMPlasmaOk
1011:28:49:957AMPlasmaOk
1111:43:18:913AMPlasmaOk
1211:56:03:730AMPlasmaOk
1312:09:27:870PMPlasmaOk
1412:27:14:720PMPlasmaOk

System Availability
Dec 9 2011 09:01:37:220AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesnoSecured for vessel entry/work. High voltage power supplies are turned off, all 8 cables HV cables are unplugged at J-port rackApr 14 2011 09:56AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at F-port rack.Apr 14 2011 09:56AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at A-port rack.Apr 14 2011 09:57AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at A-port and F-port racks.Apr 14 2011 09:58AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at F-port rack.Apr 14 2011 09:58AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPnoSecured for vessel entry. Power supplies turned off, air turned off and hose disconnected, all probe cables unplugged at A-port rack.Apr 14 2011 09:59AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPno Secured for vessel entry. Power supplies turned off, air turned off and hose disconnected, all probe cables unplugged at F-port rack.Apr 14 2011 09:59AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoSecured for vessel entry. Power supplies turned off, Kepco cable unplugged, all probe cables unplugged at F-port rack.Apr 14 2011 11:39AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 09:51:50:510AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesyesOperational. High voltage comes on during INIT and off at RECOOL.Dec 09 2011 09:48AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDyesOperational, except for probe #1 (open circuit) and probe #16 (not installed).Dec 09 2011 09:50AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at A-port rack.Apr 14 2011 09:57AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at A-port and F-port racks.Apr 14 2011 09:58AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVnoSecured for vessel entry. Power supplies turned off, all probe cables unplugged at F-port rack.Apr 14 2011 09:58AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPnoSecured for vessel entry. Power supplies turned off, air turned off and hose disconnected, all probe cables unplugged at A-port rack.Apr 14 2011 09:59AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPno Secured for vessel entry. Power supplies turned off, air turned off and hose disconnected, all probe cables unplugged at F-port rack.Apr 14 2011 09:59AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPnoSecured for vessel entry. Power supplies turned off, Kepco cable unplugged, all probe cables unplugged at F-port rack.Apr 14 2011 11:39AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 10:06:17:370AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesyesOperational. High voltage comes on during INIT and off at RECOOL.Dec 09 2011 09:48AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDyesOperational, except for probe #1 (open circuit) and probe #16 (not installed).Dec 09 2011 09:50AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesOperational, except for bottom-D probe (open circuit).Dec 09 2011 09:52AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesF-divertor ok. J-divertor ok, except for JDIV_06 which is shorted out.Dec 09 2011 09:54AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVyesOperational except for probes #4, 5 and 13 (open)Dec 09 2011 09:56AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesOperational. Fluctuation head was damaged. Will change to RFA/ISP heads next.Dec 09 2011 09:57AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesOperational.Dec 09 2011 09:57AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPyesA-port WASP is operational. K-port WASP is dead (all probes melted together).Dec 09 2011 09:58AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 10:25:45:873AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesyesOperational. High voltage comes on during INIT and off at RECOOL.Dec 09 2011 09:48AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDyesOperational, except for probe #1 (open circuit) and probe #16 (not installed).Dec 09 2011 09:50AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesOperational, except for bottom-D probe (open circuit).Dec 09 2011 09:52AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesF-divertor ok. J-divertor ok, except for JDIV_06 which is shorted out.Dec 09 2011 09:54AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVyesOperational except for probes #4, 5 and 13 (open)Dec 09 2011 09:56AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesOperational. Fluctuation head was damaged. Will change to RFA/ISP heads next.Dec 09 2011 09:57AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesOperational.Dec 09 2011 09:57AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPyesA-port WASP is operational. K-port WASP is dead (all probes melted together).Dec 09 2011 09:58AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 10:40:54:697AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesyesOperational. High voltage comes on during INIT and off at RECOOL.Dec 09 2011 09:48AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDyesOperational, except for probe #1 (open circuit) and probe #16 (not installed).Dec 09 2011 09:50AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesOperational, except for bottom-D probe (open circuit).Dec 09 2011 09:52AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesF-divertor ok. J-divertor ok, except for JDIV_06 which is shorted out.Dec 09 2011 09:54AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVyesOperational except for probes #4, 5 and 13 (open)Dec 09 2011 09:56AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesOperational. Fluctuation head was damaged. Will change to RFA/ISP heads next.Dec 09 2011 09:57AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesOperational.Dec 09 2011 09:57AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPyesA-port WASP is operational. K-port WASP is dead (all probes melted together).Dec 09 2011 09:58AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 10:54:13:163AM
SystemAvailableCommentAvailability
Changed
OwnerDescriptionWho Can
Change
Active MHDnosecured - tagged outJun 02 2008 11:03AM (sears)Joe SnipesActive MHD Antennagolfit
BESyesBES system is onlineNov 22 2011 02:21PM (bespam)Bill RowanBeam Emission Spectroscopybespam,liao,rowan
Bolometersyes2pi and midplane AXUV diodes awaiting first plasma. Divertor diodes installed, but amplifiers need to be installed. Core and divertor bolometry not yet hooked upNov 17 2011 02:45PM (mlreinke)Matt ReinkeBolometershutch,mlreinke
BoronizationnoBottle Removed. Magnetron UnpluggedApr 11 2011 09:51AM (dekow)Jim IrbyBoronizationdekow,irby
CNPAyesMultiple channel CNPA available, no safety risk for in-vessel accessApr 14 2011 12:01PM (parker)Ron ParkerCompact Neutral Analyzerparker
Cryopump - Upper DivertornoShut down. Helium dewar removed. LN2 manual valve closed/ red-tagged and solenoid valves are closed Apr 15 2011 10:55AM (dekow)Brian LaBombardUpper Divertor Cryopumpdekow,irby,labombard
CXRSyescore-CXRS system is onlineNov 22 2011 02:21PM (bespam)Bill RowanCharge Exchange Spectroscopybespam,blip,liao,rachmcd,rowan
CXRS edgeyesMichael CHurchill has primary responsibility at the momentApr 19 2011 11:44AM (blip)Bruce LipshultzMeasurement of CXR light in the pedestal region at both the high- and low-field sidesblip,rmchurch
D Alphayes\ha2_bright is available; \SPECTROSCOPY::TOP.VUV.VIS_SIGNALS:MCP_VIS_SIG1 is not availableJul 01 2009 09:45AM (terry)Jim TerryBalmer Alpha Monitorirby,terry,wolfe
Dalsanosystem is is installed and aligned, but not functional (appears to be a broken cable)Dec 05 2011 02:41PM (marmar)Earl MarmarVisible Bremsstrahlung Imagingmarmar
Disruption Mitigationnogas jet valve disabled on 2011/04/13Apr 13 2011 02:04PM (granetz)Robert GranetzGas Jetgranetz,whyte
Divertor IRno Mar 06 2007 10:50AM Glen WurdenDivertor IR Digital Videogwurden,terry
Divertor IR Spectroscopyno Mar 06 2007 10:51AM Glen WurdenDivertor IR Spectroscopygwurden,terry
DMBolo AXUV diodesnoDiodes are taking data, but system is not fully operational yet. Post-acquisition data processing code is not yet functional.Dec 02 2011 03:27PM (golynyk)Geoff OlynykSet of six AXUV diodes in a toroidal array of midplane wall boxes.golynyk,granetz,mlreinke,whyte
DNByes Dec 01 2011 11:46AM (granetz)Robert GranetzDiagnostic Neutral Beamdterry,granetz,mochung
ECDCyesOperational as of 11/19/11Nov 22 2011 03:01PM (irby)Jim Irby2.45 GHz, 3 kW, discharge cleaning systemdekow,irby,pfeiffer
FRC-ECEnoPower off to RF and IF sections- Power on to DAApr 11 2011 02:54PM (phillips)Perry PhillipsHeterodyne ECE-32 channelsbespam,liao,phillips,rowan,whitea
G-Side Ratiomaticyes Dec 02 2011 12:24PM (toland)Brian LaBombardG-side ratiomatic ionization gaugelabombard,toland
Glow DischargenoPower supply unplugged and redtagged, HV cables removedApr 14 2011 08:03AM (dekow)Jim Irby1 kV, 5 A, glow discharge systemdekow,dterry,irby
GPCyesUsing new preamps.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPC2yesDewar cold. Nov 21 2011 09:55AM (hubbard)Amanda HubbardECE Polychromaterhubbard
GPIyesThe Xpt-view, the midplane-view cameras are operational. The innerwall GPI (coupled to the fast-diodes) is available. Jul 01 2009 09:45AM (terry)Jim TerryGas Puff Imagingterry,zweben
H/Dyessystem is functional and taking dataDec 05 2011 02:42PM (marmar)Earl MarmarH/D Ratiomarmar
HEATnoBreakers off and red taggedApr 14 2011 11:27AM (dekow)Gary Dekow - Machine Heaters -burke,dekow
Hirex JryesHirex-Jr has been installedJun 28 2010 03:36PM (rice)John RiceHigh Resolution X-Rayince,rice
Hirex SryesInstalled and aligned. Will be available for Ti/Vr profiles after focusing tests and locked modes are taken.Dec 06 2011 08:21AM (ypodpaly)John RiceHigh Resolution X-Raycgao,ldelgado,rice,ypodpaly
HXRyes32 Channels operational,, no safety risk for in-vessel accessApr 14 2011 12:05PM (parker)Ron ParkerHard X-Ray Arrayfaust,parker,schmidt
ICRF D-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchD-port antennawukitch,ylin
ICRF E-AntennanosecuredApr 14 2011 08:55AM (wukitch)Steve WukitchE-port antennawukitch,ylin
ICRF J-AntennanosecuredApr 14 2011 08:56AM (wukitch)Steve WukitchJ-port antennawukitch,ylin
Impurity SpectroscopyyesBeing upgraded with better optics and new spectrographs. Dan Miller has primary responsibility.Apr 19 2011 11:46AM (blip)Bruce LipshultzMeasurement of recycling light and impurity source rates at multiple surfaces around the tokamakblip,miller
Laser Blow-OffnoBeamline disconnectedApr 14 2011 11:53AM (g)Martin GreenwaldImpurity Injection Systemg,nthoward
Lower HybridnoLH HV Breaker Opened and Tagged, TPS Upgrade UnderwayNov 10 2011 03:51PM (dterry)Ron ParkerLower Hybriddterry,parker,wallaceg
Lower Hybrid ReflectometernooffApr 15 2011 08:24AM (dominguez)Arturo DominguezLower Hybrid Reflectometerdominguez,marmar,parker,sgbaek
LoWEUSyesLoWEUS working with the shot cycle. Viewing Mo line-emission normally covered by McPherson. Raw data only in tree.Dec 01 2011 02:54PM (mlreinke)Matthew L. Reinke Long Wavelength Extreme Ultraviolet Spectrometermarkchil,mlreinke
LPInoBeam line removedMay 30 2008 02:09PM (bose)Earl MarmarLithium Pellet Injectorbose,marmar
Ly-alphanoMidplane Lyman awaiting first plasma. B-PORT and LEDGE arrays installed but do not yet have amplifiers hooked up.Nov 17 2011 02:42PM (mlreinke)Matt ReinkeLyman alpha camerasfaustian,labombard,mlreinke
Magneticsyes Dec 01 2011 11:51AM (g)Robert GranetzBp coils and flux loops for equilibrium controlgranetz,wolfe
McPhersonnonew turbo pump, installed, McP pumping down. Almost ready to open to machine.Dec 06 2011 12:16PM (mlreinke)Jim TerryVUV Spectrometermarkchil,mlreinke,terry
MichelsonyesFront end at 4.5e-8 T. Reduced speed for initial operation.Nov 30 2011 07:51AM (hubbard)Amanda HubbardECE Te Profileshubbard,schmidt
MKSyes Dec 02 2011 12:27PM (toland)Brian LaBombardBaratron pressure gaugeslabombard,toland
MLPnoSystem is in edge lab. Version 2 drivers ready to test. Needs a student to help work on it.Jul 14 2009 09:20PM (labombard)Brian LaBombardMirror Langmuir Probe Electronics Systemlabombard
MSEnono safety risk for in-vessel access as of 4/14/2011Apr 14 2011 11:48AM (sscott)Steve ScottMotional Stark Effectjinseok,sscott
NeutronsyesHigh voltage is on. We're ready for plasma.Nov 21 2011 12:58PM (fiore)Catherine FioreNeutron Detectorsfiore
Neuts and HardsyesAll detectors Powered On --- Waiting for neutrons for calibrationNov 22 2011 01:05PM (irby)Jim IrbyX-Ray/Neutron Detectors at K-Horirby
NINJAyesC-bottom and new F-bottom system ready.Dec 02 2011 12:28PM (toland)Brian LaBombardNINJA gas pufflabombard,terry,toland
PCIyesOperational.Nov 30 2011 12:45PM (ntsujii)Miklos PorkolabPhase Contrast Imagingemd,ennever,ntsujii,porkolab
Penning GaugesyesOperational. High voltage comes on during INIT and off at RECOOL.Dec 09 2011 09:48AM (labombard)Brian LaBombardPenning Ionization Gaugeslabombard
Plasma TVyesWIDE1, WIDE2 (chan 33), DANT, JANT and DIV are operational.Jul 01 2009 09:46AM (terry)Jim TerryVideo of plasma via several camerasdekow,irby,terry,wolfe
PolarimeternoSafe for Machine EntrySep 14 2007 12:17PM (irby)Jim IrbyC-Mod Polarimeterirby
Power - Alternator Air SwitchnoRed tagged offApr 12 2011 07:23AM (dekow)Gary Dekowfeeds all the other suppliescochran,dekow,dterry,irby
Power - PEInoBreaker opened and red taggedApr 11 2011 11:59AM (dekow)Gary DekowPEI Systemcochran,dekow,dterry,irby
Power - TMXnoBreakers opened and red taggedApr 11 2011 12:00PM (dekow)Gary DekowEf2s,. EFCs and A-Coilsbyford,cochran,dekow,dterry,irby
Power SystemsnoAll systems disabled for in-vessel entryApr 14 2011 11:29AM (dekow)Jim IrbyC-Mod Magnet Suppliesbyford,cochran,dekow,dterry,irby
Probe Array - ISDyesOperational, except for probe #1 (open circuit) and probe #16 (not installed).Dec 09 2011 09:50AM (labombard)Brian LabombardInner Lower Divertor Probe Arraylabombard
Probe Array - LHyesOperational, except for bottom-D probe (open circuit).Dec 09 2011 09:52AM (labombard)Brian LaBombardLower Hybrid Probe Arraylabombard
Probe Array - OSDyesF-divertor ok. J-divertor ok, except for JDIV_06 which is shorted out.Dec 09 2011 09:54AM (labombard)Brian LaBombardOuter Lower Divertor Probe Array (F and J)labombard
Probe Array - UDIVyesOperational except for probes #4, 5 and 13 (open)Dec 09 2011 09:56AM (labombard)Brian LaBombardUpper Divertor Probe Arraylabombard
ReflectometernooffApr 15 2011 08:24AM (dominguez)Earl MarmarReflectometerdominguez,marmar
Scanning Probe - ASPyesOperational. Fluctuation head was damaged. Will change to RFA/ISP heads next.Dec 09 2011 09:57AM (labombard)Brian LaBombardA-Port Scanning Probelabombard
Scanning Probe - FSPyesOperational.Dec 09 2011 09:57AM (labombard)Brian LaBombardF-Port Scanning Probelabombard
Scanning Probe - WASPyesA-port WASP is operational. K-port WASP is dead (all probes melted together).Dec 09 2011 09:58AM (labombard)Brian LaBombardInner Wall Scanning Probelabombard,nsmick
SOL reflectometeryesc-port waveguides operational, h-port waveguides are not.Nov 29 2011 12:04PM (cornwall)Cornwall LauSOL reflectometercornwall,wukitch,ylin
SparkeryesNew Type II sparker replaced Type I on 11/17/2011Nov 23 2011 08:53AM (irby)Jim IrbyField Emission Preionization for C-Moddekow,irby,parkin
Surface Science StationnoSSS is up to air, no safety issuesApr 14 2011 12:06PM (ochoukov)Bruce LipschultzRadially scanning probe located on K-portblip,ochoukov
TCIyesTCI Operational. Density feedback operational.Nov 10 2011 11:47AM (irby)Jim IrbyTwo-Color Interferometerirby,murray
TS - CorenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesCore Thomson scatteringjrwalk,jwhughes,yma
TS - EdgenoAll lasers are shut down and cannot be fired into cell.Apr 11 2011 01:20PM (jwhughes)Jerry HughesMillimeter resolution edge Thomson scatteringjrwalk,jwhughes,yma
Vispecno350 and 670 nm, 4 spatial channelsNov 28 2007 09:58AM (agraf)Alex GrafVisible Spectrometeragraf
XEUSyesXEUS working with the shot cycle. Viewing low-Z emission.Dec 01 2011 02:55PM (mlreinke)Matt ReinkeX-ray Extended Ultraviolet Spectrometermarkchil,mlreinke
XTOMOyesARRAY1->4 waiting first plasma, new core ARRAY5 needs debugging and the calibration data checkedNov 17 2011 02:44PM (mlreinke)Robert GranetzX-Ray Tomographyfaustian,granetz,mlreinke

Dec 9 2011 01:01:37:467PM
AB RFA Commissioning
--------------------
Switched Grid Bias boards after this shot to ones with proper wiring on relay.
Dec 9 2011 01:02:20:020PM
AB RFA Commissioning
--------------------
Changed current gain on Gird Cards to maximum of this shot.