Alcator C-Mod Run 930817 Information

Back to runs

Miniproposals
Miniproposal:
Date Filed:
Title:
First Author:
Session Leader:Martin Greenwald (shots 1-24)
Miniproposal:009
Date Filed: 7/14/1993
Title:Pellet Fueling Studies
First Author:Martin Greenwald
Session Leader:Martin Greenwald (shots 1-24)

Operators
Session leader(s):Martin Greenwald,Martin Greenwald
Physics operator(s):Steve Wolfe
Engineering operator(s):Frank Silva

Engineering Operator Run Comment
pellet/coldwll run

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:08:523PM
Author: To Be Determined
Run Summary for August 17, 1993

This was the first run with the pellet injector. As such it was probably
the most interesting and significant event for C-Mod to date. It was a good
run with very few fizzles or duds. On a Tuesday! The injector performed
well, firing pellets every time it was requested 22/22. On two shots, the
pellets did not arrive at the plasma, indicating some minor internal
alignment problem. We reached record plasma densities - line integral
ne > 1.6 x 10^20 implying line average > 3 x 10^20.

The first few shots were used to set up a target plasma. We were aiming
for about .4 MA a long flat-top and n average about 1 x 10^20. Plasma
shape and position were not considered critical - though we were looking
for more or less constant conditions.

Two pellet sizes were available on this day - with nominal particle contents
of .5x10^20 (barrel #4) and 1.x10^20 (barrel #3); for the rest of this
report I will refer to these as small and large pellets (Though these are
the smallest two sizes of the four the injector can make). The barrels
fired on each shot and the measured pellet velocity are stored signals and
can be found in \fueling::barrels and \fueling::velocity. These are very
sparse signals, with one point per pellet fired, thus when only one pellet
is fired you have only one pair of pts in the signal and you can't plot it -
it can still be retrieved however. Note that the time base for these
signals is approximately (+/- 100 microseconds) the time at which the pellet
reaches the plasma center. There is roughly 5 msec delay between the firing
of the pellet valves and its arrival at the plasma. Velocities are
typically near 1000 m/sec.

On shot 5 we began pellet experiments by firing a single small pellet(barrel
#4) into the plasma at .25 seconds. This raised the line integral density
by about .2 x 10^20: This is approximately .4-.5 x 10^20 line averaged which
is in rough agreement with the nominal pellet size which is .5 x 10^20
particles. The temperature, soft-xray emission, Zeff dropped as expected,
and we saw bursts of hard xrays while the pellet was ablating (about 150
microseconds). A slight change in sawtooth period accompanies the pellets.
There is also a burst of light, mostly hydrogen line emission, during
ablation, Some diagnostics may see this in direct or reflected light. Note
that since we are ionizing of order 10^20 particles in 10^-4 seconds, this
light is very bright.

Shots 7 and 10 were essentially repeats of shot 5.

On shot 11 we switched to barrel #3 firing at the same time (.25 sec) The
line integral density rise was then about .4 x 10^20, twice the size of
the rise seen from barrel #4, in agreement with their relative sizes.
Barrel #3 fires pellets with nominally 1.x10^20 particles. There was
evidence that we had accessed the enhanced confinement mode. In particular
the sawtooth period increased dramatically - conventional wisdom attributes
this to current profile modification from accumulating impurities. The
xray profile width narrows considerably from the same effect. There is
considerable MHD activity which is seen on the xrays, tci, etc.

On shot 14 we fired two pellets #4 at .25 sec and #3 at .28 seconds, line
integral densities were above 1 x 10^20. This puts the line average over 2
x 10^20, note that the calculated density limit for these conditions is
about 2.5x10^20. The plasma suffered a major disruption about .14 seconds
later.

Shots 15-17 were similar to shots 11-13

On Shot 17 we fired barrel #3 at .25 followed by #4 at .28. The line
integral density reached 1.6 x 10^20, well in excess of the density limit.
The plasma disrupted a few msec later resulting in the pumpout of all the
density increment.

Shots 18-23 were similar to shots 11-13

Shot 24 had both small and large pellets were fired at .25 sec. We reached a
line integral density of 1.5 x 10^20 - which held over 1 x 10^20 for about
.5 sec.

Additional notes:

The pellet tracker diagnostic worked well. The signals were slightly
saturated on some early shots. After the cameras were stopped down we
were able to get pellet trajectories.

Marfes were a problem again. They may be corrupting some of the tci
inner channels.

The target plasma are dirty. There was a great deal of xray emission early
in each shot, probably due to Mo. Since impurities accumulate in the
enhanced confinement mode, we need to start with relatively clean plasmas.

Physics Operator Summaries
Entered: Jul 7 2004 04:36:50:317PM
Author: To Be Determined
Operations Summary for Run 930817
Session Leader: Greenwald
Physics Operator: Wolfe
Assistant Operator: Terry
Engineering Operator: Silva

Primary: MP#009 Pellet Injection
Piggy-Back: MP#022 Cold Walls

The goal of the run was to test pellet fueling. The secondary goal was to
evaluate operation with cold (-40C) walls. Both goals were achieved.

Discharge cleaning was carried out as usual, after which the vessel and
coil pockets were cooled toward -40C. "Average" vessel temperature for the
first plasma attempt was -28C, and reached -36C during the run. The 28 peak
began slowly rising during cooldown, and remained somewhat higher than
normal throughout the run. H-port and K-port pumpout lines had a large
pressure excursion (outer seal opening) during the cooldown which then
recovered.

Starting point for the run was based on 930812023 (Ip=400:450kA, nel =
3.8e19). It was necessary to recalculate the filament and FLUXIHH
predictors to account for the replacement of the BP17_BC coil by BP17_DE.
Small adjustments were made to gas programming during the day. The only
changes to the equilibrium were extending the time the plasma was
programmed low to 600msec, and extending the negative current on EF4
similarly. Fill pressure was started at 1.2e-5, as on 8/12. This was
lowered to 1.0e-5 when the pellet operation started to compensate for the
expected gas influx; while the lower pressure worked fine, it was
eventually raised back to 1.1e-5 on shot 11 (to reduce hards) and to 1.2e-5
on shot 20, following a dud.

Pellets were fired at around 250 and/or 280msec beginning on shot 5. Most
worked, although the post-pellet phases of the later, larger pellet shots
eventually disrupted at between 350 and 500msec (non-pellet shots had been
running over 600msec) The timing of the pellets was into the limited phase
of the discharge, which diverted around 300:350msec. The target density on
shot was raised to 6.7e19 (integral ndl) by bridging the pulses on the
A-side valve, ie holding the valve at 90V from 140:210 msec; the pellet at
255 raised this to 1.6e20, or nbar around 3e20. This seemed to exceed the
density limit; the shot finally disrupted around 350msec. The target
density was lowered to around 4.2e19 for the rest of the run, by dropping
the A-side programming to 60V from 155 to 210msec.

Cold wall operation did not cause any noticeable problems, despite the
somewhat elevated N2 level. Whether it helped or not is not clear; this was
the best Tuesday run in recent memory, but we were running based on a well
behaved shot from a high-consistency run from last week.

Problems:
--------
There was another sump/dewar backup problem prior to the run; no vacuum
problem this time. There may have been a similar problem during the run, as
it was noted that the TV view under the dewar was conpletely obscured by
vapor around 16:00.

The chopper was not functioning from the beginning of the run till shot 14.
The first plasma attempt (shot 2) was killed off at 40msec by the fact that
the chopper failed to chop and caused the plasma to go screaming up.The
plasmas were not seriously unstable without it, although there were some
vertical oscillations which were cured when the chopper was put back
online. The problem was traced to a loose wire at the control cabinet.

There was a delay due to a logbook problem at shot 22; SYSTEM SERVICE
REQUEST Errors on Make Entry, and apparently on the automatic entries. TWF
got us back in operation, but it wasn't clear what caused the problem.

We lost one (maybe two) shots around 16:30 because we had to evacuate the
building for a fire alarm. The alarm was apparently caused by welding going
on in the old computer room.

Scorecard:
----------
Tests 2 (#1,8)
Duds 1
Fizzles 1 (100kA in 40msec-Chopper malfunction)
Good 20
--
Total 24

Session Leader Comments
Aug 17 1993 11:12:40:580AM930817005Jim TerryFirst D_2 pellet attempt at 250 ms. Definite success.
Increases seen on H_alpha, visible brems., TCI at that time.
Increase on TCI ch. 5 is about 2e19. Decrease seen in ECE temp. at that time.

Aug 17 1993 11:02:38:260AM930817006Jim TerryD_2 pellet attempt at 250 ms. Nothing seen in the plasma. Pellet (probably slushy)
seen on time-of-flight diodes.

Aug 17 1993 11:06:09:170AM930817007Jim TerryD_2 pellet attempt at 250 ms. Definite pellet at 255 ms.
Plasma current max is 0.42 MA.

Aug 17 1993 12:21:16:880PM930817010Jim TerryGood discharge, Plasma current max of 0.43 MA.
Pellet attempt at 250 ms. Good pellet.
Hard x-rays increased somewhat from last shot.
Shark fin begins at about 550 ms.

Aug 17 1993 12:40:30:070PM930817011Jim TerryGood discharge, plasma current max 0f 0.43 MA.
Pellet attempt (next larger size - nominally 1e20 particles) at 250 ms.
Good pellet. delta Nel was 4.2e19.
Pellet slows the sawtooth period; large MHD prior to each subsequent
sawtooth.
Hard x-rays decreased significantly from last shot.

Aug 17 1993 01:04:37:600PM930817012Jim TerryGood discharge, Plasma current max 0f 0.43 MA.
Pellet attempt (size - nominally 1e20 particles) at 250 ms.
Good pellet. Delta Nel on channel 5 is again 4.2e19. Pellet slows the sawtooth period;
large MHD prior to each subsequent sawtooth.
Shark fin begins at 500 ms.

Aug 17 1993 01:46:48:030PM930817014Jim TerryDischarge disrupted at 420 ms. Plasma current max of 0.44 MA.
Large MHD after 335 ms.
Attempt for 2 pellets at 250 and 280ms.
Tiny pellet at 250 ms, bigger pellet at 280 ms.

Physics Operator Comments
Aug 17 1993 08:35:47:050AMSteve WolfeRun 930817
MP 009 Pellet Injection / Piggyback Cold Walls)
Session Leader : [g]
Physics Op: wolfe

Start from 930812023; update all Ip-type predictors to account for new BP17 loop
Walls will be at -40C (they are at -5.0 at 08:35)

Aug 17 1993 11:15:43:550AMJim TerryWe are beginning this run with 'cold' walls (part of MP 022). We start with the
vessel temp. at -31 deg.C with a set pt of 40 deg. C. If this temperature
changes significantly during the run, it will be noted according to shot.

Aug 17 1993 09:02:04:730AM930817001Steve WolfeData System test

Aug 17 1993 09:40:14:860AM930817002Steve WolfeVessel avg temp = -28C
Small N2 leak = 5.7e-10 on RGA

Result: Fizzle
EFC didn't chop.
It lasted until almost 50msec. EFC almost certainly killed it-- xray centroid says it
went screaming up.

Aug 17 1993 11:08:08:070AM930817002Jim TerryFizzle - about 40 ms long.
Chopper did not function properly - did not chop.
Until further notice; RF limiter is at R=96.0, antenna is at R=98.0 cm

Aug 17 1993 11:08:52:340AM930817003Jim TerryPlasma current max is 0.40; pulse length is about 700 ms.
Prefill was 1.2e-5 Torr.
Again the chopper did not commutate. For this shot it's charging voltage
was changed to -400 V and it's turn-on was delayed to 600 ms.
'Z_meter' INCAA digitized only for the 1st 100 ms.
Vertically unstable after about 500 ms. Low hard x-rays.

Aug 17 1993 11:09:44:120AM930817004Jim TerryPlasma current max is 0.42; pulse length is about 730ms.
Prefill was 1.2e-5 Torr.
Again the chopper did not commutate. For this shot it's charging voltage
was changed to -1000 V, and its turn-on was at t=0.
Vertically unstable after about 500 ms. Low hard x-rays.
Vessel temperature was -32 deg. C.
After the shot the set pt. was dropped to -50 deg. C.

Aug 17 1993 11:11:37:780AM930817005Jim TerryPlasma current max is 0.42; pulse length is about 740ms.
Prefill was 1.0e-5 Torr.
First D_2 pellet attempt at 250 ms. Increases seen on H_alpha, visible brems.,
TCI at that time. Increase on TCI ch. 5 is about 2e19.
Decrease seen in ECE temp. at that time.
Again the chopper did not commutate.
Vertically unstable after about 500 ms. Low hard x-rays.
Vessel temperature was -39 deg. C. Set pt returned to -40 deg. C.

Aug 17 1993 11:14:45:800AM930817006Jim TerryPlasma current max is 0.42; pulse length is about 740ms.
Prefill was 1.0e-5 Torr.
D_2 pellet attempt at 250 ms. No pellet at that time.

Changes in pulsed gas programming:
Pulsed gas valve 2 programming at 47 and 100 ms changed from 27 V to 20 V.
Pulsed gas valve 1 (Argon) programming set to open valve at 0 ms instead of 100 ms.

Vessel temperature was -34 deg. C.

Aug 17 1993 11:05:17:350AM930817007Jim TerryPlasma current max is 0.42; pulse length is about 740ms.
Prefill was 1.0e-5 Torr.
D_2 pellet attempt at 250 ms. Definite pellet at 255 ms.
Plasma current max is 0.42 MA.
Prefill is still 1.0e-5 torr.

Changes in pulsed gas programming:
Pulsed gas valve 2 programming shortened by 30 ms.
Pulsed gas valve 3 (A side) programming extended to 0.77 s at a level of 33 V.

Vessel temperature was -34 deg. C.

Aug 17 1993 11:44:11:770AM930817008Jim TerryTMX-chopper test only. No plasma attempted.

Aug 17 1993 11:58:21:420AM930817008Jim TerryResult of the TMX-chopper test was that the commutation bank was charging
properly. Thus that does not seem to be the problem.

Aug 17 1993 12:10:05:690PM930817009Jim TerryThere was a long (about 50 min) delay between this shot and the previous plasma
attempt (Shot 930817007). This was to allow cell entry.

Good discharge, Plasma current max 0f 0.43 MA.
Pellet attempt at 250 ms. No pellet.

Aug 17 1993 12:19:51:680PM930817010Jim TerryOn the pulsed gas valve 3 programming a 65 V pulse between 500 and 550 ms
was added.

Good discharge, Plasma current max 0f 0.43 MA.
Pellet attempt at 250 ms. Good pellet.
Hard x-rays increased somewhat from last shot.
Shark fin begins at about 550 ms.

Aug 17 1993 12:38:05:950PM930817011Jim TerryPrefill raised to 1.1e-5 Torr.
On the pulsed gas valve 3 programming, we removed the 65 V pulse between
500 and 550 ms.

Good discharge, Plasma current max 0f 0.43 MA.
Pellet attempt (next larger size - nominally 1e20 particles) at 250 ms.
Good pellet. Pellet slows the sawtooth period; large MHD prior to each subsequent
sawtooth.
Hard x-rays decreased significantly from last shot.

Aug 17 1993 12:59:12:490PM930817012Jim TerryPrefill still 1.1e-5 Torr.

Extend the "down" time on ZCUR to 650 ms.
Extend EF4 reverse voltage programming (at -400 V) until 635 ms.
This successfully held the plasma low 'til the end of the shot.
Good discharge, Plasma current max 0f 0.43 MA.
Pellet attempt (size - nominally 1e20 particles) at 250 ms.
Good pellet. Pellet slows the sawtooth period; large MHD prior to each subsequent
sawtooth.
Shark fin begins at 500 ms.

Aug 17 1993 01:17:50:390PM930817013Jim TerryPrefill still 1.1e-5 Torr.

Extend the "down" time on ZCUR to 650 ms.
Good discharge, Plasma current max 0f 0.43 MA.
Pellet attempt (size - nominally 1e20 particles) at 250 ms.
Good pellet.
Shark fin begins at 500 ms.

Vessel temperature now -36 deg. C

Aug 17 1993 01:39:57:840PM930817014Jim TerryPrefill still 1.1e-5 Torr.
Chopper is fixed - now chopping as programed.

Programmed pulsed gas valve 2 to give a 50 V pulse at 1 sec for calibration
of the machine pressure gauges.

Good discharge, Plasma current max 0f 0.44 MA.
Attempt for 2 pellets at 250 and 280ms.
Tiny pellet at 250 ms, bigger pellet at 280 ms.

Vessel temperature is still -36 deg. C.

Aug 17 1993 01:55:56:750PM930817015Jim TerryPrefill still 1.1e-5 Torr.
Chopper programmed to turn go from -1000 V at 30 ms to 0 V at 80 ms.
Chopper operational.
Removed the gas pulse at 1 sec (from pulsed gas valve 2).

Good discharge. Plasma current max 0f 0.44 MA.
Large MHD between 305 and 327 ms.
Attempt for 1 pellet at 250 ms.
Good pellet at 250 ms.

Vessel temperature is still -36 deg. C.

Aug 17 1993 02:22:25:820PM930817016Jim TerryPrefill still 1.1e-5 Torr.
Chopper charging voltage changed from 400 to 700 V.
Increased the width of the 1st 3 pulses on pulsed gas valve 3 from 2 ms
to 8 ms. This doubled the H_alpha sig (at K port). Density (channel 5) didn't
increase.

Good discharge. Plasma current max 0f 0.44 MA.
Attempt for 1 pellet at 250 ms. Good pellet at 250 ms.

Vessel temperature is still -36 deg. C.

Aug 17 1993 02:22:45:490PM930817016Jim TerryPrefill still 1.1e-5 Torr.
Chopper charging voltage changed from 400 to 700 V.
Increased the width of the 1st 3 pulses on pulsed gas valve 3 from 2 ms
to 8 ms. This doubled the H_alpha sig (at K port). Density (channel 5) didn't
increase.

Good discharge. Plasma current max 0f 0.44 MA.
Attempt for 1 pellet at 250 ms. Good pellet at 250 ms.

Vessel temperature is still -36 deg. C.

Aug 17 1993 02:44:52:370PM930817017Jim TerryPrefill still 1.1e-5 Torr.

Pulsed gas valve 3 programmed at 90 V from 140 'til 210 ms.
This saturated the H_alpha sig (at K port). Density (channel 5) increased
from 3.8 to 5.5 e19 at that time.

RF limiter moved into 95.0 cm.

Calibration gas pulse (80 V) at 1 sec from pulsed gas valve 3 (A side).

Discharge disrupted at about 350 ms. Plasma current max 0f 0.42 MA.
Attempt for 1 pellet at 250 ms. Good pellet at 250 ms. Density after the pellet
went to 1.62e20 !

Vessel temperature is still -36 deg. C.

Aug 17 1993 03:03:07:160PM930817018Jim TerryPrefill still 1.1e-5 Torr.
Pulsed gas valve 3 programmed at 60 V from 155 'til 210 ms.
Density (channel 5) was back to 4.2e19 at that time.
RF limiter at 95.0 cm.
Calibration gas pulse (80 V) at 1 sec from pulsed gas valve 3 (A side).

Discharge disrupted at about 475 ms. Plasma current max of 0.43 MA.
MHD from about 315 ms to 330 ms.
Attempt for 1 pellet at 250 ms. Good pellet at 250 ms. Density after the pellet
went to 1.1e20 Channel 5 TCI.

Aug 17 1993 03:14:41:720PM930817019Jim TerryDud!
Prefill still 1.1e-5 Torr.

RF limiter at 95.0 cm.

Aug 17 1993 03:34:03:610PM930817020Jim TerryPrefill raised to 1.2e-5 Torr.

RF limiter at 95.0 cm.

Plasma disrupted at 525 ms. Decent discharge through the pellet injection.
Shark fin begins at 450 ms.

Attempt for 1 pellet at 250 ms. Good pellet.

Aug 17 1993 03:56:02:400PM930817021Jim TerryPrefill still at 1.2e-5 Torr.

RF limiter at 95.0 cm.

Plasma disrupted at 412 ms. Decent discharge through the pellet injection, unhappy
after the pellet.

Attempt for 1 pellet at 250 ms. Good pellet.

Aug 17 1993 04:29:55:800PM930817022Jim TerryPrefill still at 1.2e-5 Torr.
Removed the last 4 gas puffs (into plasma) starting at about 330 ms from gas valve 3.
Removed the calibration gas puff from valve 3 at 1 s.

RF limiter back to R=96.0 cm.
RF antenna back to R=98.0 cm

Good shot lasting 612 ms. Plasma current max was 0.43 MA.
Attempt for 1 pellet at 250 ms. Good pellet.

Aug 17 1993 04:54:21:630PM930817023Jim TerryPrefill still at 1.2e-5 Torr.

RF limiter at R=96.0 cm.

Shot disrupted at 450 ms - good until 2nd pellet. Plasma current max was 0.44 MA.
Attempt for 2 pellets at 250 ms and 280 ms. Both were successfull, although the
2nd one caused the plasma to go bad. Strong MHD from about 295 ms to 320 ms.

Vessel temperature still -36 deg. C.

Aug 17 1993 05:08:20:320PM930817023Jim TerryPrefill still at 1.2e-5 Torr.

RF limiter at R=96.0 cm.

Shot disrupted at 365 ms - good until pellet injection. Plasma current max was 0.44 MA.
Attempt for 2 pellets both at 250 m. Both were successful. Chan5 on TCI and
visible brems. stay high for 50 ms after the injection.


Vessel temperature still -36 deg. C.

Engineering Operator Comments
ShotTimeTypeStatusComment
108:37:58:430AMTestOkdata system test
209:25:47:600AMTestOkfizzel/ efc chopper o/c
309:46:51:630AMPlasmaOkplasma good shot
410:03:01:540AMPlasmaOkplasma
510:21:06:770AMPlasmaOkpellet shot
610:41:49:500AMPlasmaOkpellet
710:59:13:430AMPlasmaOkpellet
811:41:31:340AMTestOkefc chopper test
911:55:21:650AMPlasmaOkplasma
1012:12:51:920PMPlasmaOkpellet/plasma
1112:28:16:620PMPlasmaOkbig pellet
1212:49:28:540PMPlasmaOkplasma
1301:10:13:050PMPlasmaOkbigger pellet
1401:31:32:610PMPlasmaOkplasma
1501:48:07:370PMPlasmaOkchopper now operational
1602:09:48:090PMPlasmaOkplasma
1702:29:01:260PMPlasmaOkplasma
1802:49:03:720PMPlasmaOksparks
1903:08:55:280PMPlasmaOkfizzel
2003:24:16:270PMPlasmaOkshow shot for pacer
2103:41:35:140PMPlasmaOkplasma
2204:20:44:330PMTestBad
2304:29:58:380PMPlasmaOkdisruption, torvac gauges off
2404:56:41:840PMTestBad