Alcator C-Mod Run 960821 Information

Back to runs

Miniproposals
Miniproposal:160
Date Filed: 7/23/1996
Title:Divertor Cryopump Prototype Commissioning
First Author:Jim Irby
Session Leader:Jim Irby (shots 1-7)

Operators
Session leader(s):Jim Irby
Physics operator(s):Steve Wolfe
Engineering operator(s): Unknown

Engineering Operator Run Comment
cryopump commissioning/wolfe

Session Leader Plans

Physics Operators Plans

Session Leader Summaries

Physics Operator Summaries
Entered: Jul 7 2004 04:36:56:613PM
Author: To Be Determined
Physop Summary for 960821

This run was supposed to be in support of two MP's:
#160 Cryopump Commissioning and
#161 Low Triangularity development
The run was expected to start late because of the EF4 problem that ended
Tuesday's run. However, while the engineers were involved in replacing fuses
and devising schemes for instrumenting the fault and (hopefully) avoiding it,
there was a vacuum accident that scrubbed the run. The F-side ratiomatic was
observed to be inoperable, and when Joe Snipes went into the cell to change
filaments he accidentally broke a feedthrough, bringing the torus to atmosphere
in a few minutes.

EF4 tests were carried out in the afternoon. These were uneventful. New
instrumentation had been added to monitor the gate pulses on the rectifiers
and crowbars. IN addition, the half of the crowbar in the forward cabinet that
was implicated in each of yesterday's events was removed. There seems to be
evidence that this section fired without being properly triggered, causing the
problems.

EF4 was tested under PLC and under hybrid control, with double swings up to
3000A (6000A from the supply) and no faults were observed. Shot 7 included a
full TF (5.3T) PLC pulse. Details in the logbook under PHYSICS_OPERATOR.

Meanwhile, the ratiomatic was replaced and the machine pumped down. Pump-down was
slow probably due to water frozen out on cold surfaces. The pressure was down
to 1.e-4 at 17:30, and ECDC in D2 set up for overnight.

Session Leader Comments

Physics Operator Comments
Aug 21 1996 08:37:13:050AMSteve WolfeRun Plan for Wed. 960821

MP#160 Cryopump commissioning (1/2 run)
MP#161 Low triangularity development (1/2 run)
SL Irby, Hutch
PO Wolfe

Engineering setup:
------------------
No overnight ECDC
ECDC in D2 for 2 hours before run
Start with power system settings as on 960820004
Gas setup:
fill A-side with 20 PSI of D2
fill B-top with 5 PSI of D2
fill B-side-lower with 4 PSI of Ar

Aug 21 1996 08:37:55:350AMSteve WolfeSpecial Engineering:
--------------------
The EF4 problem which ended the Tuesday run, and proposed solutions, should be
reviewed and appropriate action taken prior to starting this run. Since the
second half of this run, and runs scheduled for later in the week, will
require parallel EF4 operation at relatively high currents, it is essential
that the EF4 faults be addressed. This may delay the start of this run by one
to two hours.

Aug 21 1996 08:39:14:160AMSteve WolfeRun Plan:
---------
The first half of the run is to be used for commissioning the divertor
cryopump. We will start with two fiducial-like baseline shots, based on
960820017, with the LN2 shield cold. The LHe pots will then be filled and we
will run 2-4 nominally identical shots, monitoring pressures and gas
consumption. Ar will be fired on all shots and the Ar levels determined. JT
will orient the McPherson to look at the divertor. After several shots with
the cryopump cold, we will close gatevalves and turn off all torus ionization
gauges (ITG and the ratiomatics) and allow the pots to warm up, measuring the
pressure rise as a measure of the total gas load. Finally a density scan will
be performed to try to determine pumping speed as a funciton of divertor
pressure, after which the pots will again be dumped into a closed-off machine.

Aug 21 1996 08:39:44:570AMSteve WolfeThe second half of the run will be an attempt to develop reduced triangularity
discharges, in support of the JET similarity experiment (MP161) and the h-mode
triangularity scan (MP143A). Assuming Yuichi is still attempting to do RF
conditioning we will operate with a flattop Bt=5.4T. Initial shape changes
will be done at 800kA (standard fiducial level), then once the target
equilibrium (delta_l <= 0.4, delta_u <= 0.2?, k=1.65) the current will be raised
in steps to approximately 1.2MA (q95=3.1).

Aug 21 1996 08:51:50:210AMSteve WolfeStart from 960820016, a so-so successsful startup from yesterday. It looks
to me like the OH voltage tweaks need to be modified, and there seems to
be a negative radial field that should be removed. Also, it is possible
that an adjuctment to the Segment 1 RCUR offset is indicated. I'll
start from #16, which did work, and tweak from there.

08:45 Load from 960820016 and Load_into_model
08:49 Coldstart -- ok.

Frnak predicts start of run at 10:30-11:00

Aug 21 1996 11:44:55:990AMSteve WolfeThe F-side ratiomatic seems to have died overnight. Snipes is changing
filaments before we get started.

Disaster! Broke vacuum at the F-port gauge. Machine is up-to-air.
We can still do some power tests, but no run today.

Aug 21 1996 03:53:45:640PM960821001Steve WolfeEF4 test (PLC): -1500A, Large difference current due to temperature
imbalance, but basically ok.

Aug 21 1996 04:11:52:450PM960821002Steve WolfeEF4 test (PLC): 1400A +direction, balance is better. No faults.

Aug 21 1996 04:24:46:770PM960821003Steve WolfeEF4 test (PLC): Same test again, with terminators on the pierson gate
current monitors. ok.

Aug 21 1996 04:39:25:350PM960821004Steve WolfeEF4 test (PLC): No power, test of crowbar instrumentation.
Too quick on the trigger button; try again.

Aug 21 1996 04:45:20:050PM960821004Steve WolfeEF4 test (PLC): 6kA(total) EF4 test (+ direction). Looks ok,
got 2923A in each coil. NO crowbar.

Aug 21 1996 04:45:35:870PM960821005Steve Wolfeshot 5: EF4 test (PLC): 6kA(total) EF4 test (+ direction). Looks ok,
got 2923A in each coil. NO crowbar.

Aug 21 1996 04:58:51:970PM960821006Steve Wolfe960821006
Hybrid control: -1000 to +3000
Use only segment 1, disable IP control.
Looks fine.

Aug 21 1996 05:13:10:350PM960821007Steve Wolfe960821007
TF and EF4 test:
Hybrid control on EF4: -1000 to +3000
Change V_EF4 to go to zero after 0.1sec (approx) to get rid of oscillation
around crossover.
TF under PLC control.
NO faults.

Engineering Operator Comments
ShotTimeTypeStatusComment
103:49:49:670PMTestOkef4 test forward
204:07:54:540PMTestOkef4 reverse
304:21:34:770PMTestOk
404:31:24:760PMTestOkxbar test no alternator
504:42:42:930PMTestOkef4 6ka reverse bridge
604:53:57:880PMTestOk
705:07:17:130PMTestOktf ef4 forward and reverse