Alcator C-Mod Run 970626 Information

Back to runs

Miniproposals
Miniproposal:150a
Date Filed: 7/23/1996
Title:3He Minority Heating at 8T
First Author:Yuichi Takase
Session Leader:Steve Wukitch (shots 1-14)

Operators
Session leader(s):Steve Wukitch
Physics operator(s):John Goetz
Engineering operator(s):Vinny Bertolino,Frank Silva,Dave Terry,Bill Cochran

Engineering Operator Run Comment
mp150a/Terry/Cochran/Bertolino/Goetz

Session Leader Plans

Physics Operators Plans

Session Leader Summaries
Entered: Jul 7 2004 03:49:06:053PM
Author: To Be Determined
Beginning MP150A (He3 Minority Heating at 8T) today with the explicit purpose
of investigating RF absorption. However, we will probably spend considerable
amount of time developing the discharge because this is the first 8T run of the
campaign. We will begin with 5.4T discharges to test the TF scanner and move
to 8T discharges when this test is completed. In parallel, FMIT#2 will be
tested. Although it began to work more regularly yesterday, its
instrumentation has developed problems. These will not prevent it from running
but it could make it difficult to match. The arc and fault detection system
will also be tested. Once the physics run starts, the He3 concentration will
be scanned with RF power modulation.

005 plasma disrupted @1.0 sec
006 dud engineering
007 plasma BT=5.4, 1 MA, nel = 1.0
008 plasma BT=6.1, 1 MA
009 dud breaker pull
010 dud breaker pull-->trying for 6.8T
011-013 problems with EF's
014 plasma BT=8T, 1.2 MA both transmitters ran, but separately

Developed a problem with the alternator which terminated the run after 014.
However, we solved part of the RF arc and fault detection problem and 014 is a
good shot from which to start the next 8T run. None of the physics program was
begun.

Entered: Jul 7 2004 03:49:17:227PM
Author: To Be Determined
Beginning MP150A (He3 Minority Heating at 8T) today with the explicit purpose
of investigating RF absorption. However, we will probably spend considerable
amount of time developing the discharge because this is the first 8T run of the
campaign. We will begin with 5.4T discharges to test the TF scanner and move
to 8T discharges when this test is completed. In parallel, FMIT#2 will be
tested. Although it began to work more regularly yesterday, its
instrumentation has developed problems. These will not prevent it from running
but it could make it difficult to match. The arc and fault detection system
will also be tested. Once the physics run starts, the He3 concentration will
be scanned with RF power modulation.

005 plasma disrupted @1.0 sec
006 dud engineering
007 plasma BT=5.4, 1 MA, nel = 1.0
008 plasma BT=6.1, 1 MA
009 dud breaker pull
010 dud breaker pull-->trying for 6.8T
011-013 problems with EF's
014 plasma BT=8T, 1.2 MA both transmitters ran, but separately

Developed a problem with the alternator which terminated the run after 014.
However, we solved part of the RF arc and fault detection problem and 014 is a
good shot from which to start the next 8T run. None of the physics program was
begun.

Physics Operator Summaries
Entered: Jul 7 2004 04:36:57:863PM
Author: To Be Determined
Physics operator summary for 970626

EO: Terry/Bertolino/Cochran/Silva
PO: Goetz
SL: Wukitch

Run 970626 was in support of Mini-Proposal #150A - Helium-3 Minority Heating at 8T.
The goals for today are to try and run 8T plasmas and optimize the helium-3
minority heating scanario.

The goals were not reached today. Plasmas were produced at fields ranging from 5.3 to
8.1T. The problem was, there were not enough of them. See the Session Leader's
report for the physics results.

Good day for start-up. Four-for-four in startups. Breakdowns occured at around
5msec and were accompanied by current rises with hesitations. Burnouts were slow
but this was acceptable today.

Started today with 5.3T shots in order to test the TF scanner and then slowly worked
up in field reaching 8.1T on shot 14.

Wire 10 has been renamed PULSE_GAS5 and is now connected to the J-BOTTOM piezoelectric
valve. Using a shot from prior to 970626xxx will require the operator to move a point
in the all V's screen [for all segments] in order to pick up the name change. The
system was tested to the output of the high voltage op amp and nothing appeared at
the low voltage tap of this output, which is digitized in INPUT_05 of the PHA Incaa.

Engineering, computing, and diagnostics today: The TF scanner was debugged today and
is working acceptably. The EF1U supply began crowbarring before t=0 when the
toroidal field was raised. This was ultimately traced to the wrong IOC limits
on the first and second directions of the EF1's. This was remedied by changing
the setpoints. The alternator suffered through particulate and vibration faults,
thus ending the run. The status of the alternator is being investigated.

Scorecard: 14 shots = 4 plasmas + 0 fizzles + 4 eng. duds + 6 tests

Shot summary for Run 970626:

Load 970625003
coldstart hybrid - all matrices respond

Shot change result
____ _____ ______
1 test shot

2 test shot

3 test shot

4 test shot

5 see above plasma; b.d. @ .0055; slight hesitation
disrupts @ .97 due to no density feedback;

6 draw [100Vx0.1s] @ .8 on PG5 engineering dud; no OH2's, EF1L, EF2U
[output of HV amp not connected]
70min delay for RF CAMAC crate
and various other cell things

7 try again plasma; b.d. @ .0055; slight hesitation
nice shot

8 TF current to -175kA and start plasma; b.d. @ .0045; slight hesitation
time = -1.7s under PLC control; H-modes; heating; EF4 on a current limit
IP=-1000000

9 TF current = -195kA; EF4 PLC engineering dud; EF1L out before the shot
= [-9.,4.]kA; IP=-1200000; followed by EF1U and OH2's
RCUR = .667

10 try again engineering dud; EF1U out first this time

11 TF current = -215kA engineering dud; EF1U out @ -.21; Bt=7.4T

12 EF1 test only EF1 still tripping

13 EF1 test with IOC boards EF1's work
flipped for forward-reverse

14 TF current = -231kA plasma; b.d. @ .005; slight hesitation
Bt=-8.1T; Ip=-1.2MA; disrupts @ 1.53;
particulate and vibration faults in the
alternator. End of run.

Session Leader Comments
Jun 26 1997 11:36:37:330AMSteve WukitchBeginning MP150A (He3 Minority Heating at 8T) today with the explicit purpose
of investigating RF absorption. However, we will probably spend considerable
amount of time developing the discharge because this is the first 8T run of the
campaign. We will begin with 5.4T discharges to test the TF scanner and move
to 8T discharges when this test is completed. In parallel, FMIT#2 will be
tested. Although it began to work more regularly yesterday, its
instrumentation has developed problems. These will not prevent it from running
but it could make it difficult to match. The arc and fault detection system
will also be tested. Once the physics run starts, the He3 concentration will
be scanned with RF power modulation.
Jun 26 1997 03:01:17:140PMSteve WukitchDeveloped a problem with the alternator which terminated the run after 014.
However, we solved part of the RF arc and fault detection problem and 014 is a
good shot from which to start the next 8T run. None of the physics program was
begun.
Jun 26 1997 10:05:07:840AM970626005Steve Wukitchplasma disrupted @1.0s RF had crate problems
Jun 26 1997 10:12:04:210AM970626006Steve Wukitchdud engineering dud
Jun 26 1997 11:15:45:640AM970626007Steve Wukitchplasma BT=5.4, 1MA FMIT#2 worked with trips and modified instrumentation worked properly
Jun 26 1997 11:17:13:130AM970626008Steve Wukitchplasma BT=6.1, 1MA FMIT#2 worked with trips at 1.5 MW, FMIT#1 is primarily tripping on phase balance
Jun 26 1997 11:35:50:520AM970626009Steve Wukitchdud breaker pull
Jun 26 1997 11:45:07:900AM970626010Steve Wukitchdud breaker pull-->trying for 6.8T
Jun 26 1997 03:00:53:890PM970626014Steve Wukitchplasma BT=8T, 1.2 MA both transmitters ran, but separately

Physics Operator Comments
Jun 26 1997 08:34:01:920AMJohn GoetzRun 970626

MP 150A -- Optimization of 8T Heating

Engineering:
Overnight ECDC in deuterium.
Engineering setup as on 960905003
Begin with TF under PLC control, although it is possible
that hybrid control will be required later in the run
Gas setup - fill K-side with 20 PSI of D2, hybrid enable
fill B-top with 6 PSI of D2, hybrid enable
fill B-side-lower with 4 PSI of Ar, hybrid enable
fill B-side-upper with 15 PSI of Helium-3, hybrid enable
purge J-bottom
The following gate valves should be enabled, assuming no vacuum problems:
ECE, PCX, TCX, VUV, MolyMon

Physics:
Begin with 960905003 which is a 1.2MA, 8T discharge. A systematic
scan of helium-3 concentration and density will be performed
to try and optimize the minority heating scenario at 8T. RF power
absorption data will be obtained using the power modulation technique.

Jun 26 1997 08:35:37:110AMJohn GoetzRun 970626

First 4 shots were tests with no power to check out the TF scanner.

The run will begin with 970625003 which is a 5.3T, 1.0MA shot to
do the TF scanner tests with power. After that Jim Irby will decide
how the run proceeds.
Jun 26 1997 08:37:23:820AMJohn GoetzRun 970626

Wire 10 has been renamed PULSE_GAS5 and is now connected to the J-BOTTOM
piezoelectric valve. Using a shot from prior to 970626xxx will require the operator to move
a point in the all V's screen [for all segments] in order to pick up the name change.
Jun 26 1997 09:12:44:180AM970626005John GoetzShot 970626005:
Load 970625003
coldstart hybrid - all matrices respond
test shot with power for TF scanner purposes

Results:
Plasma
breakdown @ 5.5msec - slight hesitation in the current rise
no density feedback - causes disruption @ 0.97s
computer network problem has lost some data
Jun 26 1997 10:13:32:250AM970626006John GoetzShot 970626006:
draw [100Vx0.1s] @ 0.8s on PULSE_GAS5 (there is no connection
from the output to the piezoelectric valve - this is just
a test of the system up to the output)
70 minute cell access for various and sundry things

Results:
power supply dud
shot cycle went like this: INIT->RECOOL->INIT due to an
alternator low RPM
no OH2's, EF1L, and EF2U
Jun 26 1997 10:31:33:260AM970626007John GoetzShot 970626007:
draw [100Vx0.1s] @ 0.8s on PULSE_GAS5 (there is no connection
from the output to the piezoelectric valve - this is just
a test of the system up to the output)
70 minute cell access for various and sundry things

Results:
plasma
breakdown @ .0055; slight current rise hesitation
disrupts @ 0.2MA
RF got some power in; H-modes; neutrons

Jun 26 1997 10:52:08:870AM970626008John GoetzShot 970626008:
draw IP = -1000000
TF start time = -1.7sec and TF current = -175kA (6.3T) under PLC control

Results:
Plasma
breakdown @ .0045; slight hesitation in current rise
H-modes and heating
EF4 at its current limit
J-Bottom waveform not getting to the low voltage output
Jun 26 1997 11:35:25:840AM970626009John GoetzShot 970626009:
draw IP = -1200000
TF start time = -1.7sec and TF current = -195kA (6.8T) under PLC control
EF4 PLC current limit = [-9.,4.]kA
RCUR = .667 for a bigger right gap

Results:
engineering dud
EF1L out at -.27sec followed by EF1U and the OH2's
Jun 26 1997 11:59:21:100AM970626010John GoetzShot 970626010:
draw IP = -1200000
TF start time = -1.7sec and TF current = -195kA (6.7T) under PLC control
EF4 PLC current limit = [-9.,4.]kA
RCUR = .667 for a bigger right gap

Results:
engineering dud
EF1U pulled out at -.14 followed by EF1L and the OH2's
TF made it to 6.8T
Jun 26 1997 12:27:32:700PM970626011John GoetzShot 970626011:
draw IP = -1200000
TF start time = -1.7sec and TF current = -215kA (7.5T) under PLC control
EF4 PLC current limit = [-9.,4.]kA
RCUR = .667 for a bigger right gap

Results:
engineering dud
EF1U out at -.21sec followed by the rest
toroidal field = 7.4T
Jun 26 1997 01:03:59:250PM970626012John GoetzShot 970626012:
test of EF1 only

Results:
EF1U pulls out at ~6kA at -0.9
Jun 26 1997 01:19:10:740PM970626013John GoetzShot 970626013:
EF1 test again with IOC limits switched for the forward and reverse directions

Results:
EF1's are operational
Jun 26 1997 02:09:01:580PM970626014John GoetzShot 970626014:
draw IP = -1200000
TF start time = -1.7sec and TF current = -231kA (7.9T) under PLC control
EF4 PLC current limit = [-9.,4.]kA
RCUR = .667 for a bigger right gap

Results:
plasma
breakdown @ .005; slight hesitation
Bt = -8.1T; Ip = -1.2MA
disrupts @ 1.53s (Ip = 0.4MA)
TF begins to invert @ 1.17s
alternator faults on smoke and vibration
last shot of the run as the investigation begins

Engineering Operator Comments
ShotTimeTypeStatusComment
106:56:00:020AMTestOktf scanner cycle no power
207:22:58:560AMTestOktf scanner cycle no power
307:38:29:630AMTestOktf scanner, no power shot
408:13:48:070AMTestOktf scanner, no power
508:46:53:860AMPlasmaOkno faults
610:04:00:990AMPlasmaOk
710:18:39:880AMPlasmaOk
810:34:20:910AMPlasmaOk175 ka tf no faults plasma
911:21:18:760AMPlasmaOkef1 fault
1011:39:50:460AMPlasmaOkef 1 fault
1112:08:55:960PMPlasmaOkef1 fault
1212:49:14:640PMTestOk
1301:15:05:970PMTestOk
1401:24:12:300PMPlasmaBadalternator vibration faults